Uraian Singkat Pekerjaan
PEKERJAAN : PEMASANGAN ACP GEDUNG FASILKOM
LOKASI : UNIVERSITAS JEMBER
ANGGARAN : DIPA UNEJ 2025
NO URAIAN PEKERJAAN VOLUME
1 2 3
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 3 ,00 titik
2 Pek. Bongkar Pasang Alat Bantu Kerja 5 35,80 m2
II PEKERJAAN LOKASI 1
A PEKERJAAN ACP
1 Pek. ACP Outdoor PVDF Dinding 6 5,60 m2
Pas. Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm
2 Pek. ACP Outdoor Cutting 3 2,00 m2
Pas.Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm
B PEKERJAAN LETTER ACRYLIC
1 Pek. Pasang Tulisan Letter Stainless "ILMU KOMPUTER" Tinggi 65 cm 1 2,00 bh
III PEKERJAAN LOKASI 2
A PEKERJAAN ACP
1 Pek. ACP Outdoor PVDF Dinding 6 5,60 m2
Pas. Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm
2 Pek. ACP Outdoor Cutting 3 2,00 m2
Pas.Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm
IV PEKERJAAN LOKASI 3
A PEKERJAAN ACP
1 Pek. ACP Outdoor PVDF Dinding 5 6,50 m2
Pas. Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm
2 Pek. ACP Outdoor Cutting 1 6,20 m2
Pas.Alumunium Composite Panel (ACP-Seven) tebal 3 mm
Rangka Hollow Uk.20.40.1,4 mm
Rangka Hollow Uk.40.40.1,4 mm