| Administrative Score (SA) | Reason | ||||
|---|---|---|---|---|---|
| 0011123973441000 | Rp 3,752,604,750 | 91.81 | 93.45 | - | |
| 0018131466019000 | Rp 3,949,710,780 | 87.83 | - | Berdasarkan klarifikasi Tenaga Ahli HSE yang ditawarkan masih terikat kontrak pada pekerjaan lain | |
| 0014992440952000 | Rp 4,093,184,663 | 81.55 | 83.58 | - | |
| 0015011851121000 | Rp 4,199,112,240 | 88.98 | 89.05 | - | |
PT Yodya Karya (Persero) Wilayah IV Medan | 0010016160124001 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) |
| 0028689933027000 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) | |
| 0024769994615000 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) | |
| 0961174240526000 | - | - | - | Tidak lulus pembuktian kualifikasi | |
| 0018010751121000 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) | |
| 0018127886003000 | - | 66.87 | - | Tidak memenuhi nilai ambang batas Proposal Teknis | |
| 0013282181015000 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) | |
| 0018326082805000 | - | - | - | Tidak masuk ke dalam daftar pendek (shortlist) | |
| 0011247665731000 | - | - | - | - | |
| 0013421094016000 | - | 68.32 | - | Tidak memenuhi nilai ambang batas proposal teknis | |
| 0014232714812000 | - | - | - | Setelah diminta data kualifikasi tambahan tidak menyampaikan Sertifikat Standar terverifikasi (untuk Badan Usaha yang memiliki SBU KBLI 2020) atau Sertifikat Standar belum terverifikasi dan tangkapan layar laman OSS yang mencantumkan bahwa Sertifikat Standar sedang menunggu verifikasi | |
| 0018436196019000 | - | - | - | - | |
PT Atharrazka Tata Jaya | 00*0**5****32**0 | - | - | - | - |
| 0015259153517000 | - | - | - | - | |
| 0014308399124000 | - | - | - | - | |
| 0814168126429000 | - | - | - | - | |
| 0943074740216000 | - | - | - | - | |
| 0011048477423000 | - | - | - | - | |
| 0016741654003000 | - | - | - | - | |
| 0719817025432000 | - | - | - | - | |
| 0011008109124000 | - | - | - | - | |
| 0017635038122000 | - | - | - | - | |
| 0014311815123000 | - | - | - | - | |
| 0013472055017000 | - | - | - | - | |
| 0012164984429000 | - | - | - | - | |
| 0011191632424000 | - | - | - | - | |
| 0015378680113000 | - | - | - | - | |
| 0011191475424000 | - | - | - | - | |
| 0022282065822000 | - | - | - | - | |
PT Teknika Utama Konsultan | 09*0**8****44**0 | - | - | - | - |
| 0015418585064000 | - | - | - | - | |
| 0013095203062000 | - | - | - | - | |
| 0011050937441000 | - | - | - | - | |
| 0012030466609000 | - | - | - | - | |
| 0015899628121000 | - | - | - | - | |
| 0016147266722000 | - | - | - | - | |
| 0011444155614000 | - | - | - | - | |
PT Geoprodev Nusantara | 00*6**4****24**0 | - | - | - | - |
| 0015654437017000 | - | - | - | - | |
| 0013737945015000 | - | - | - | - | |
| 0020052080331000 | - | - | - | - | |
| 0013338884064000 | - | - | - | - | |
| 0013398508013000 | - | - | - | - | |
PT Virama Karya (Persero) Cabang Sumatera | 0010004851124001 | - | - | - | - |
| 0011278041441000 | - | - | - | - |
| Authority | |||
|---|---|---|---|
| 17 September 2015 | Paket 26 - Pengawasan Pekerjaan Konstruksi Dan Layanan Pemeliharaan Jalan Pada Kbk Karangnongko (Bts. DIY)-Wangon (Myc) | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 33,137,000,000 |
| 9 October 2021 | Project Management Unit For Komering Irrigation Project-3 (Pmu Kip-3) | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 15,115,300,000 |
| 23 June 2022 | Pengawasan Teknik Jalan Tol Ikn Segmen Karangjoang - Kkt Kariangau | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 14,784,529,000 |
| 18 July 2018 | Konsultan Pendukung Pelaksanaan Program Ipdmip | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 13,499,810,000 |
| 27 March 2018 | Jasa Konsultansi Pendukung Pelaksanaan Program Wilayah Timur (Npic-B1b.2) | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 12,963,000,000 |
| 11 August 2023 | Konsultan Pengendali Mutu Independen (Pmi) Ruas Jalan Tol Akses Pelabuhan Patimban | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 12,144,100,000 |
| 31 October 2016 | (Pr01) Perencanaan Teknis Jalan Perbatasan 1 | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 9,535,729,000 |
| 31 October 2016 | (Pr03) Perencanaan Teknis Jalan Perbatasan 3 | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 9,535,729,000 |
| 21 January 2022 | Supervisi Pembangunan Jaringan Irigasi Di. Gilireng Kiri Kab. Wajo | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 9,300,000,000 |
| 8 December 2022 | Supervisi Rehabilitasi D.I Saddang Sub Unit Jampue Kab. Pinrang (Sbsn) | Kementerian Pekerjaan Umum dan Perumahan Rakyat | Rp 9,000,000,000 |