Pelebaran Jalan Menuju Standar Pada Ruas Palembayan Cs

Tender Ulang
Basic Information
Type: Public Tender
Tender Code: 24675016
Status: Tender Ulang
Date: 13 March 2023
Year: 2023
KLPD: Provinsi Sumatera Barat
Work Unit: Dinas Bina Marga, Cipta Karya Dan Tata Ruang
Procurement Type: Pekerjaan Konstruksi
Method: Tender - Pascakualifikasi Satu File - Harga Terendah Sistem Gugur
Contract Type: Harga Satuan
Financial Information
Value (Nilai Pagu): Rp 6,691,000,000
Estimated Value (Nilai HPS): Rp 6,690,999,000
Winner (Pemenang): PT Era Bangun Sarana
NPWP: 028849347801000
RUP Code: 39150938
Work Location: Kab. Agam - Agam (Kab.)
Participants: 70
Applicants
Reason
0028849347801000Rp 5,492,570,730-
0015597883831000Rp 5,820,697,560-
0719162018113000Rp 5,853,764,199-
0015080245221000Rp 5,918,964,351-
0829016450205000--
0748370616202000Rp 6,280,762,975-
0015796915713000Rp 5,904,114,799-
0020083242101000Rp 5,888,323,394-
0959247396201000Rp 6,155,919,740-
0316804467124000Rp 5,600,000,000Tidak menyampaikan tidak pernah mengalami denda keterlambatan akibat kelalaian Penyedia Jasa dalam kurun waktu 2(dua) tahun terakhir (TA 2021 dan 2022) pada surat pernyataan yang disampaikank pada isian kualifikasi SPSE maupun unggahan lainnya pada isian kualifikasi SPSE, sehingga tidak memenuhi ketentuan evaluasi kualifikasi berdasarkan IKP. point 30.1 bahwa Pokja Pemilihan melakukan evaluasi kualifikasi terhadap dokumen kualifikasi yang disampaikan (diunggah) oleh peserta melalui form elektronik isian kualifikasi dalam SPSE atau pada fasilitas upload data kualifikasi lainnya.
0421135245201000Rp 6,508,251,603-
0012298113201000--
0841405707101000Rp 6,222,222,222-
0018942979218000Rp 5,954,989,110-
0015201817204000--
Banyu Langit Perkasa
09*3**5****02**0--
0032330748201000--
0026934844216000--
0023608821201000--
0661472191124000--
0021792163211000--
0752255190106000--
0021146493201000--
Kunango Jantan
00*6**8****21**1--
CV Karya Global Persada
04*9**2****01**0--
0530327626205000--
0030451611219000--
0012302485201000--
0012684015201000--
0016890725201000--
0017367145202000--
0745984799202000--
0011292067201000--
0841483134201000--
PT Rajawali Jaya Konstruksi
06*4**2****47**0--
0910678101205000--
CV Design Engineering Consultan
00*5**9****01**0--
0019517556218000--
0021154349201000--
PT Putera Ciptakreasi Pratama
0020484660215000--
0011160801201000--
0424537637216000--
0535731095201000--
0028784296201000--
0012682100203000--
0015212921201000--
CV Pratama Jaya
0743107047203000--
0759630239202000--
0012337242617000--
0016130981609000--
0025513722201000--
0017588294203000--
CV Tuah Mora Jaya
06*7**4****02**0--
0017367053202000--
CV Ridho. A
09*8**2****03**0--
0022194062202000--
0012686754201000--
0026392670204000--
0012682043203000--
PT Nadya Ratu Permata
09*2**4****05**0--
0029549581201000--
0839354537216000--
0020500609203000--
0314761297429000--
0026097949332000--
0625397559205000--
0935270710202000--
0019170919201000--
0938634417201000--
PT Buana Kontrindo Cemerlang
03*7**3****34**0--
Attachment
PEMERINTAH  PROVINSI SUMATERA BARAT                  
             DINAS  BINA MARGA,   CIPTA  KARYA  DAN  TATA  RUANG           
                  Jalan Taman Siswa No. 1 Telp. (0751) 7051700 Fax. (0751) 7051783 Padang
                    http://www.bmcktr.sumbarprov.go.id - email:pdeisb@sumbarprov.go.id
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                        URAIAN   PEKERJAAN                                 
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                               PROGRAM                                     
                                                                           
                     PROGRAM PENYELENGGARAAN JALAN                         
                                                                           
                                                                           
                                                                           
                                                                           
                               KEGIATAN                                    
                                                                           
                     PENYELENGGARAAN JALAN PROVINSI                        
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                             SUB KEGIATAN                                  
                     PELEBARAN JALAN MENUJU STANDAR                        
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                              PEKERJAAN                                    
           PELEBARAN MENUJU STANDAR PADA RUAS PALEMBAYAN CS                
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                          TAHUN ANGGARAN 2023                              
METODA PELAKSANAAN                                                         
   Untuk mendukung proses pelaksanaan penyelesaian pekerjaan, Maka dibuat suatu metode/Standart
                                                                           
   Operation Procedure (SOP) yang akan menjelaskan tata cara bekerja dan urutan pekerjaan yang akan
   dilakukan. Dengan harapan dengan adanya SOP ini jalannya pekerjaan akan terarah dan waktu
   pekerjaan akan tercapai dengan hasil pekerjaan yang baik dan sesuai target yang telah direncanakan.
                                                                           
                                                                           
                                                                           
                                                                           
A. DIVISI 1 UMUM                                                           
1. Mobilisasi                                                              
     Pekerjaan ini meliputi :                                              
                                                                           
  -  Melaksanakan pengukuran kembali oleh tenaga surveyor terhadap lokasi pekerjaan (Melakukan
                                                                           
     rekayasa lapangan) untuk mendapatkan data kebutuhan lapangan yang sebenarnya sesuai budget
     (MC.0).                                                               
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
  -  Membuat Shop Drawing untuk acuan pelaksanaan berdasarkan data rekayasa lapangan yang
     didapat                                                               
  -  Pembersihan area pekerjaan dari segala sampah dan benda yang menjadi gangguan pada saat
                                                                           
     dilaksanakan pekerjaan.                                               
  -  Menyiapkan tempat untuk stok material                                 
  -  Menyiapkan Rambu – rambu yang dibutuhkan                              
  -  Mobilisasi alat yang dibutuhkan                                       
                                                                           
  -  Mobilisasi pekerja yang dibutuhkan                                    
  -  Mobilisasi bahan yang dibutuhkan                                      
  -  Pemasangan papan nama proyek                                          
  -  Pengambilan foto dokumentasi kegiatan pada kondisi 0%, 50%, dan 100% untuk tiap-tiap mata
     pembayaran.                                                           
                                                                           
  -  Menentukan titik – titik pekerjaan sesuai dengan data survey yang dilakukan
                                                                           
                                                                           
Mobilisasi akan diselesaikan sesuai dengan batasan yang ditetapkan dalam spesifikasi. Dalam masa
mobilisasi ini dilakukan rekayasa lapangan dan inventarisasi seluruh item pekerjaan dan bangunan
perlengkap pada seluruh lokasi pekerjaan, sehingga dapat diterbitkan perubahan kuantitas terhadap kontrak
                                                                           
sesuai dengan kondisi terakhir di lapangan.Personil-personil yang ditugaskan adalah mereka yang sudah
berpengalaman di bidang jalan dan jembatan dan mempunyai dasar keahlian serta sertifikasi di bidang
jalan.Selain memobilisasi peralatan untuk pekerjaan utama, juga akan dilakukan mobilisasi peralatan
pendukung lainnya, baik alat berat maupun alat bantu yang sesuai dengan lampiran yang ada di dalam
penawaran ini.                                                             
2. Manajemen Keselamatan dan Kesehatan Kerja                               
  1. Lingkup Kegiatan                                                      
     Bagian ini mengatur mengenai pelaksanaan program Kesehatan dan Keselamatan Kerja (K3l)
                                                                           
     dalam pelaksanaan pekerjaan.                                          
                                                                           
  2. Pedoman Standar                                                       
     -  Undang-undang No. 1 tahun 1970 tentang Keselamatan Kerja           
     -  Keputusan Menteri Tenaga Kerja R.I. No. Kep. 1135/MEN/1987 tentang Bendera Keselamatan
        Dan Kesehatan Kerja                                                
     -  Keputusan Menteri Tenaga Kerja R.I. No.: Kep.245/MEN/1990 tentang Hari Keselamatan Dan
                                                                           
        Kesehatan Kerja Nasional.                                          
     -  Peraturan Menteri Tenaga Kerja R.I. No. Per.05/MEN/1996 tentang Sistem Manajemen
        Keselamatan dan Kesehatan Kerja                                    
  3. Keselamatan Kerja                                                     
                                                                           
     Dari permulaan hingga penyelesaian pekerjaan dan selama masa pemeliharaan, Kontraktor
     bertanggung jawab atas keselamatan dan keamanan pekerja, material dan peralatan teknis serta
     konstruksi. Wajib menjaga keselamatan kerja di ruang kerja dengan melengkapi dengan
     perlengkapan keselamatan kerja seperti safety line, rambu - rambu, papan promosi keselamatan, dan
     lain - lain. Wajib menjamin keselamatan tenaga kerja yang terlibat dalam pelaksanaan pekerjaan
                                                                           
     dari segala kemungkinan yang terjadi dengan memenuhi aturan dan ketentuan kesehatan dan
     keselamatan kerja yang berlaku (Jamsostek). Menyediakan obat-obatan menurut syarat-syarat
     Pertolongan Pertama Pada Kecelakaan (PPPK) yang selalu dalam keadaan siap digunakan di
     lapangan, untuk mengatasi segala kemungkinan musibah bagi semua petugas dari pekerja lapangan.
                                                                           
     Setiap pekerja diwajibkan menggunakan sepatu pada waktu bekerja dan dilokasi harus disediakan
     Alat Pelindung Diri (APO) berupa safety belt, safety helmet, masker/kedok las terutama untuk
     dipakai pada pekerjaan pemasangan kuda-kuda baja dan pekerjaan yang beresiko tertimpa benda
     keras. Menyediakan air bersih, kamar mandi dan WC yang layak dan bersih bagi semua petugas dan
     pekerja. Membuat tempat penginapan di lapangan pekerjaan untuk para pekerja tidak
                                                                           
     diperkenankan, kecuali atas ijin PPK. Apabila terjadi kecelakaan, sesegera mungkin
     memberitahukan kepada Konsultan danmengambil tindakan yang perlu untuk keselamatan korban
     korban kecelakaan itu.                                                
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
  4. Prosedur Operasi Standar (SOP) Kesehatan Dan Keselamatan Kerja (K3)   
     Membuat SOP Kesehatan dan Keselamatan Kerja (K3). SOP diajukan kepada Konsultan untuk
                                                                           
     dievaluasi. Menyampaikan laporan pelaksanaan SOP kepada Direktur Keselamatan, Ditjen
     Perkeretaapian, Direktur Prasarana Ditjen Perkeretaapian, PPK, dan Konsultan.
                                                                           
  5. Matrik Program K3                                                     
     Safety Health and Environmental Induction Kegiatan ini dilaksanakan setiap ada tamu ataupun
     pekerja baru yang memasuki wilayah kerja proyek Safety Health and Environmental Talk Program
     ini bertujuan untuk sosialisasi dan pembahasan mengenai seluruh permasalahan penerapan K-3L
                                                                           
     dan Lingkungan selama masa pelaksanaan proyek. Pelaksanaan Safety talk setiap 1 minggu sekali
     Safety Health and Environmental Patrol / Inspection Kegiatan ini dilaksanakan secara rutin,
     bertujuan untuk memonitor pelaksanaan K-3L di seluruh lingkungan proyek dan menjaga
     konsistensi pelaksanaan K-3L. Safety Health and Environmental Meeting Program SHE meeting
     dilaksanakan seminggu sekali dimana dalam kegiatan ini membahas permasalahan dan kejadian
     yang terjadi dan rencana tindak lanjut untuk memperbaikinya serta membahas permasalahan yang
     mungkin terjadi serta langkah-langkah pencegahannya. Safety Health and Environmental Audit
                                                                           
     Program ini dilaksanakan insidental bertujuan untuk melakukan audit terhadap kedisiplinan dalam
     pelaksanaan standar K-3L di lingkungan proyek terhadap peraturan yang diberlakukan dalam
     lingkungan perusahaan. Safety Health and Environmental Trainning Pelatihan terhadap seluruh
     komponen proyek yaitu karyawan, subkon, mandor dan seluruh pekerja mengenai K-3L, P3K dan
     respon terhadap keadaan darurat. Housekeeping Kegiatan ini dilaksanakan setiap hari bertujuan
                                                                           
     untuk menjaga kebersihan, kerapihan, kenyamanan di lingkungan kerja.  
                                                                           
                                                                           
                                                                           
   B. DIVISI 2. DRAINASE                                                   
                                                                           
     1. Galian untuk Selokan Drainase dan Saluran Air                      
       Pekerjaan galian untuk drainase ini dilakukan dengan menggunakan alat excavator. Excavator
                                                                           
       menggali sesuai dengan bentuk dan dimensi saluran yang tertera pada gambar atau atas
       persetujuan pengawas lapangan.                                      
                                                                           
                                                                           
       Perlengkapan K3 yang harus disiapkan:                               
                                                                           
       1. Safety Helmet                                                    
                                                                           
       2. Masker                                                           
                                                                           
       3. Safety Gloves                                                    
                                                                           
       4. Safety Shoes                                                     
                                                                           
       5. Pembatas Area                                                    
                                                                           
       6. Rambu-rambu                                                      
                                                                           
       Urutan Kerja:                                                       
                                                                           
       Melakukan survey terhadap lokasi pekerjaan yang akan dibuat drainase yaitupenentuan panjang
                                                                           
       galian, elevasi dan bentuk drainase. Memberi tanda berupa patok yang diberi cat merah pada
       lokasi yang akan digali Penggalian dilakukan dengan alat excavator. Excavator menggali
                                                                           
       berdasarkan tanda yang sudah diberikan berdasarkan hasil kerja dan dipandu dengan pelaksana
       dan didampingi oleh pengawas lapangan untuk mendapatkan hasil yang sempurna. Tanah Galian
                                                                           
       dimuat ke dump truck atau kesamping badan jalan apabila lokasi memungkinkan.
       Tenaga yang digunakan :                                             
                                                                           
         Pekerja                                                          
                                                                           
         Mandor                                                           
                                                                           
       Peralatan yang diperlukan :                                         
                                                                           
         Excavator                                                        
                                                                           
                                                                           
         Dump Truck                                                       
                                                                           
         Alat Bantu                                                       
                                                                           
     2. Pasangan Batu Dengan Mortar                                        
                                                                           
       Pekerjaan Pasangan Batu dengan mortar digunakan sebagai saluran drainase. Pasangan batu
       dengan mortar dibuat berdasarkan bentuk dan dimensi yang disesuaikan dengan lapangan dan
                                                                           
       gambar. Pekerjaan pasangan batu ini dikerjakan oleh tukang batu pekerja.
                                                                           
       Perlengkapan K3 yang harus disiapkan :                              
                                                                           
       1. Safety Helmet                                                    
                                                                           
       2. Masker                                                           
                                                                           
       3. Safety Gloves                                                    
                                                                           
       4. Safety Shoes                                                     
                                                                           
       5. Pembatas Area                                                    
                                                                           
       6. Rambu-rambu                                                      
                                                                           
                                                                           
                                                                           
                                                                           
       Urutan pekerjaan pasangan batu :                                    
                                                                           
        Membuat mix design untuk campuran mortar yang akan digunakan sebagai perekat batu.
        Melakukan survey untuk menentukan tempat, elevasi, dan dimensi untuk pasangan yang akan
                                                                           
         dibuat.                                                           
                                                                           
        Menyiapkan material ( semen, pasir, dan batu kali ) dan alat kerja ( molen, sendok semen,
         kayu profil sebagai acuan pasangan ) untuk pemasangan batu kali   
                                                                           
        Menggali tanah untuk pasangan sesuai dengan ukuran survey yang sudah dipasang.
                                                                           
        Mengaduk mortar dengan menggunakan molen dengan campuran adukan disesuaikan dengan
         mix design yang digunakan.                                        
                                                                           
        Menyusun batu kali dan merekatkannya dengan menggunakan mortar yang sudah disiapkan.
       Tenaga yang digunakan :                                             
                                                                           
         Pekerja                                                          
                                                                           
         Tukang Batu                                                      
                                                                           
         Mandor                                                           
                                                                           
       Bahan yang digunakan :                                              
                                                                           
         Batu                                                             
                                                                           
         Semen (PC)                                                       
                                                                           
         Pasir                                                            
                                                                           
     Peralatan yang diperlukan :                                           
                                                                           
         Concrete Mixer                                                   
                                                                           
         Alat Bantu                                                       
                                                                           
                                                                           
                                                                           
                                                                           
C. DIVISI 3 PEKERJAAN TANAH GEOSINTETIK                                    
  1. Galian Biasa                                                          
     Pekerjaan Galian biasa harus mencakup seluruh galian yang tidak Diklasifikasikan sebagai galian
     batu, galian structur, galian sumber bahan (borrow excavation), Galian perkerasan beraspal, galian
     perkerasan berbutir, dan galian perkerasan beton                      
                                                                           
     Perlengkapan K3 yang harus disiapkan:                                 
                                                                           
     1. Safety Helmet                                                      
                                                                           
     2. Masker                                                             
                                                                           
     3. Safety Gloves                                                      
                                                                           
     4. Safety Shoes                                                       
                                                                           
     5. Pembatas Area                                                      
                                                                           
     6. Rambu-rambu                                                        
                                                                           
     Pelaksanaan galian biasa ini prosedurnya sebagai berikut :            
                                                                           
     Pengukuran dan pemasangan bowplank atau menentukan kedalaman galian. Pengukuran
                                                                           
     dilaksanakan dengan menggunakan alat ukur theodolit dengan mempedomani hasil rekayasa yang
     telah ditentukan oleh konsultan dan pihak proyek.Pemasangan bowplank dilakukan setelah hasil
     dari pengukuran disetujui oleh pihak Konsultan dan direksi Pekerjaan. Penggalian secara Manual,
     Pekerjaan penggalian dilaksanakan setelah pemasangan bowplank dalam hal ini penentuan
     kedalaman galian. Tanah yang digali secara manual dikumpulkan ke tepi galian dan selanjutnya
                                                                           
     dimuat ke Dump Truck, kemudian diangkut keluar lokasi proyek. Penggalian dengan Menggunakan
     Alat Berat, Pekerjaan penggalian dilaksanakan setelah pemasangan bowplank dalam hal ini
     penentuan kedalaman galian.Tanah yang digali oleh Excavator langsung dimuat ke Dump Truck,
     kemudian diangkut keluar lokasi proyek/Disposal Area.                 
                                                                           
     Pekerjaan galian ini adalah penggalian tanah untuk membentuk badan jalan. Penggalian dilakukan
     dengan alat excavator. Hasil galian dimuat pada dump truck dan kemudian dump truck membawa
                                                                           
     hasil galian ketempat yang sudah ditentukan.                          
                                                                           
     Urutan Kerja.                                                         
                                                                           
     Melakukan survey untuk menentukan batas, elevasi dan bentuk dari galian untuk pembuatan badan
     jalan oleh orang survey. Memberi tanda berupa patok kayu yang diberi tanda merah sebagai acuan
     untuk melaksanakan pekerjaan. Excavator menggali berdasarkan tanda yang sudah diberikan oleh
     orang survey. Pada saat penggalian diarahkan oleh pelaksana lapangan yang didampingi oleh
     pengawas lapangan agar mendapatkan hasil kerja yang diinginkan sesuai dengan gambar yang
                                                                           
     digunakan. Hasil galian dimuat pada dump truck dan kemudian dump truck membawa hasil galian
     pada tempat yang sudah ditentukan.                                    
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
     Tenaga yang digunakan :                                               
                                                                           
         Pekerja                                                          
         Mandor                                                           
                                                                           
                                                                           
                                                                           
     Peralatan yang diperlukan :                                           
                                                                           
         Excavator                                                        
         Dump Truck                                                       
                                                                           
         Alat Bantu                                                       
                                                                           
     2. Galian Batu                                                        
                                                                           
       Perlengkapan K3 yang harus disiapkan :                              
       1. Safety Helmet                                                    
                                                                           
       2. Masker                                                           
       3. Safety Gloves                                                    
                                                                           
       4. Safety Shoes                                                     
       5. Pembatas Area                                                    
                                                                           
       6. Rambu-rambu                                                      
                                                                           
       Urutan Kerja:                                                       
                                                                           
       1. Batu yang dipotong umumnya berada disisi jalan                   
                                                                           
       2. Penggalian dilakukan dengan Excavator, Compresor dan Jack Hammer, dimuat ke dlm
          Truk dengan Loader.                                              
                                                                           
       3. Dump Truck membuang material hasil galian keluar                 
                                                                           
                                                                           
       Peralatan-peralatan yang dipergunakan :                             
       1. Compressor                                                       
                                                                           
       2. Jack Hammer                                                      
                                                                           
       3. Wheel Loader                                                     
       4. Excavator                                                        
                                                                           
       5. Dump Truck                                                       
                                                                           
       6. Alat bantu                                                       
                                                                           
                                                                           
       Tenaga Kerja :                                                      
        Pekerja                                                           
                                                                           
        Mandor                                                            
                                                                           
  3. Galian Struktur dengan Kedalaman 0 - 2 meter                          
       Perlengkapan K3 yang harus disiapkan:                               
                                                                           
         1. Safety Helmet                                                  
                                                                           
         2. Masker                                                         
         3. Safety Gloves                                                  
                                                                           
         4. Safety Shoes                                                   
         5. Pembatas Area                                                  
                                                                           
         6. Rambu-rambu                                                    
                                                                           
  Pekerjaan galian ini akan dilaksanakan untuk galian struktur jembatan, adapun Langkah Kerja tersebut
                                                                           
  adalah sebagai berikut:                                                  
                                                                           
      Agar pelaksanaan pekerjaan dapat berjalan dengan baik dan lancar, maka sebelum memulai
       pekerjaan, lokasi pekerjaan harus dibersihkan terlebih dahulu.      
                                                                           
      Pada lokasi pekerjaan galian, suveyor memasang patok – patok batas dan patok elevasi yang
                                                                           
       dicor dan dipagar, patok ini harus dijaga sampai akhir pekerjaan selesai, karena setiap bagian
       dari bangunan jembatan yang akan dibuat akan diukur ketinggian elevasinya dari patok elevasi
                                                                           
       tersebut.                                                           
      Galian dilakukan sesuai gambar rencana pekerjaan atau shop drawing yang disetujui oleh
                                                                           
       direksi lapangan.                                                   
      Peralatan yang dipergunakan untuk pekerjaan galian tanah adalah excavator dan jika memang
                                                                           
       diperlukan dapat juga ditambahkan dengan buldoser untuk mendorong tanah
       dalam jumlah yang cukup besar dan Dump Truk untuk pengangkut material bekas galian.
                                                                           
      Galian tanah dilaksanakan sampai dengan elevasi yang telah direncanakan.
                                                                           
                                                                           
     Bekas galian selanjutnya dibuang keluar lokasi dengan menggunakan mobil dump truk yang
     dilengkapi dengan terpal untuk menutup permukaan atas agar tanah bekas galian yang diangkut
                                                                           
     tidak tercecer di sepanjang perjalana.                                
                                                                           
     Bahan yang dibutuhkan :                                               
                                                                           
       - Urugan pilihan                                                    
       - Bahan pengaman tebing galian                                      
                                                                           
     Alat yang diperlukan :                                                
                                                                           
        - Excavator                                                        
        - Dump truck                                                       
                                                                           
        - Bulldozer                                                        
     Tenaga yang diperlukan :                                              
                                                                           
        - Pekerja                                                          
        - Mandor                                                           
                                                                           
  4. Timbunan Biasa dari Sumber Galian                                     
     A. Lingkup Pekerjaan                                                  
                                                                           
       Pekejaan ini meliputi persiapan lokasi pekerjaan, penghamparan, pemadatan, pengujian dan
       perapihan hasil pekerjaan.                                          
                                                                           
                                                                           
                                                                           
                                                                           
     B. Persiapan Pekerjaan                                                
         Mengirim program kerja (workplan) termasuk metoda kerja, schedule, perlatan,
          personil kerja dan gambar kerja yang akan digunakan, untuk memperoleh persetujuan dari
          Konsultan sebelum pekerjaan dimulai.                             
                                                                           
         Mengajukan permohonan penggunaan material kepada Direksi.        
         Memberitahu Konsultan secara tertulis paling sedikit 24 jam sebelum tanggal
          dilakukannya pelaksanaan pekerjaan.                              
                                                                           
                                                                           
                                                                           
     C. Pelaksanaan Pekerjaan                                              
         Melakukan persiapan lokasi pekerjaan berupa : pengukuran dan pemasangan marking pada
          area pekerjaan, pembersihan lokasi pekerjaan, dimana harus bebas dari material organik dan
                                                                           
          anorganik.                                                       
         Melakukan request material dan pekerjaan kepada direksi, konsultan dan pengawas.
         Memuat material timbunan pilihan dari hasil galian pada lokasi pekerjaan dengan dum truk,
          dan ditumpuk dengan jarak tertentu pada lokasi pekerjaan.        
                                                                           
         Timbunan pilihan dihampar dengan menggunakan Motor Greader.      
         Hasil hamparan timbunan pilihan disiram air dengan menggunakan Water Tanker lalu
          dipadatkan dengan Vibratory Roller sampai mencapai ketabalan dan kepadatan sesuai
          dengan spesifikasi teknik.                                       
                                                                           
         Melakukan pengujian timbunan, pengujian testpit dan cbr untuk menentukan ketebalan dan
          kepadatan dari timbunan.                                         
         Perapihan hasil pekerjaan, setiap material sisa diangkut utuk dibuang pada area yang telah
          ditentukan.                                                      
     Peralatan yang digunakan;                                             
                                                                           
       o  Meteran; untuk mengukur dimensi timbunan                         
       o  Sekop/cangkul, gerobak; sebagai media manual                     
     Peralatan keselamatan;                                                
       o  Rompi safety proyek; agar mudah terlihat, sehingga mudah dikenali dan tidak tertabrak oleh
                                                                           
          pengendara jalan raya                                            
       o  Rambu-rambu peringatan; sebagai pertanda adanya pekerjaan        
       o  Helm safety proyek; sebagai pelindung kepala dari cidera benturan
       o  Sepatu safety proyek;                                            
                                                                           
                                                                           
  3. Timbunan Pilihan Dari Sumber Galian                                   
     Timbunan yang diklasifikasikan sebagai timbunan pilihan harus terdiri dari bahan tanah atau batu
     yang memenuhi semua ketentuan di atas level timbunan biasadan sebagai tambahan harus memiliki
     sifat-sifat tertentu yang tergantung dari maksud penggunaannya, seperti diperintahkan atau distujui
                                                                           
     oleh Direksi pekerjaan.Dalam segala hal, seluruh timbunan pilihan harus, bila di uji sesuai dan
     memiliki CBR paling sedikit 10% setelah 4 hari perendaman bila dipadatkan sampai 100%
     kepadatan kering maksimum.                                            
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                              Penghamparan                                 
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                         Timbunan Pilihan Dari Sumber                      
                                 Galian                                    
                                Pemadatan                                  
     Perlengkapan K3 yang harus disiapkan:                                 
                                                                           
     1. Safety Helmet                                                      
                                                                           
     2. Masker                                                             
                                                                           
     3. Safety Gloves                                                      
                                                                           
     4. Safety Shoes                                                       
                                                                           
     5. Pembatas Area                                                      
                                                                           
     6. Rambu-rambu                                                        
                                                                           
     Pekerjaan Timbunan pilihan dilaksanakan dengan prosedur sebagai berikut :
                                                                           
      Pengangkutan Material                                               
       Pengangkutan Material Urugan pilihan kelokasi pekerjaan menggunakan Dump Truck dan
       loadingnya dilakukan dengan menggunakan Wheel Loader. Pengecekan dan pencatatan volume
       material dilakukan pada saat penghamparan agar tidak terjadi kelebihan material disatu tempat
                                                                           
       dan kekurangan material ditempat lain.                              
                                                                           
      Penghamparan Material                                               
       Penghamparan material dilakukan dengan menggunakan motor grader dalam tahap
       penghamparan ini harus diperhatikan hal-hal berikut :               
                                                                           
      Kondisi cuaca yang memungkinkan                                     
       Panjang hamparan pada saat setiap section yang didapatkan sesuai dengan kondisi lapangan.
                                                                           
       Lebar penghamparan disesuaikan dengan kondisi lapangan dan tebal penghamparan sesuai
       dengan spesifikasi, semua tahapan pekerjaan hamparan dan tebal hamparan berdasarkan
       petunjuk dan persetujuan dari Direksi Pekerjaan. Material yang tidak dipakai dipisahkan dan
       ditempatkan pada lokasi yang ditetapkan.                            
                                                                           
      Pemadatan Material                                                  
       Pemadatan dilakukan dengan menggunakan Vibro Roller, dimulai dari bagian tepi ke bagian
                                                                           
       tengah.Pemadatan dilakukan berulang jika dimungkinkan untuk mendapat hasil yang maksimal
       dengan dibantu alat water tank untuk membasahi material timbunan pilihan dan diselingi dengan
       pemadatan dengan menggunakan Vibro Roller.imbunan pilihan dipadatkan mulai dari tepi luar
       dan bergerak menuju ke arah sumbu jalan sedemikian rupa yang sama. Bilamana
                                                                           
       memungkinkan, lalu lintas alat-alat konstruksi harus terus menerus divariasi agar dapat
       menyebarkan pengaruh usaha pemadatan dari lalu lintas tersebut.     
                                                                           
     Alat yang digunakan:                                                  
     -  Motor Grader                                                       
     -  Tandem                                                             
     -  Water Tanker                                                       
                                                                           
     -  Alat Bantu                                                         
     Bahan yang digunakan :                                                
     -  Bahan Pilihan                                                      
     Tenaga :                                                              
     -  Pekerja                                                            
     -  Mandor                                                             
                                                                           
                                                                           
   D. DIVISI 5 PEKERJAAN BERBUTIR DAN PERKERASAN BETON SEMEN               
     Perlengkapan K3 yang harus disiapkan:                                 
     1. Safety Helmet                                                      
     2. Masker                                                             
                                                                           
     3. Safety Gloves                                                      
     4. Safety Shoes                                                       
     5. Pembatas Area                                                      
     6. Rambu-rambu                                                        
                                                                           
                                                                           
  1. Lapis Pondasi Agregat Kelas A dan Lapis Pondasi Agregat Kelas B       
     A. Persiapan                                                          
         Pembuatan DMF (Design Mix Formula) dilaksanakan Laboratorium atau di UMPKL Dinas
          Pekerjaan Umum setempat, bila dianjurkan oleh Direksi pengawas, contoh semua jenis material
          diambil dari sumber quarry dengan lokasi sketsa terlampir, pengambilan contoh material (batu, abu
          batu, pasir) dilaksanakan bersama-sama dengan Pengawas Lapangan dan konsultan Pengawas.
         Setelah DMF selesai kontraktor akan membuat JMF (Job Mix Formula) di Laboratorium Kontraktor
                                                                           
          itu sendiri, didampingi konsultan dan Direksi teknis.            
         Penyediaan material di stock pile atau lokasi pengadukan khususnya pemecahan batu dilaksanakan
          segera setelah hasil uji kekerasan memenuhi syarat, termasuk penyediaan pasir.
         Percobaan pelaksanaan : menyangkut komposisi masing-masing jenis material (mengacu JMF), tebal
          hamparan gembur sehingga dihasilkan tebal padat yang disyaratkan (diketahui faktor gembur), kadar
          air optimal, jumlah lintasan pemadatan sehingga dihasilkan kepadatan maksimal sesuai spesifikasi
          teknis. Hasil percobaan pelaksanaan dilakukan pengujian : ketebalan (pengukuran manual), uji
                                                                           
          kepadatan (Sand Cone), uji gradasi lapangan (analisa saringan) dan PI lapangan (atterberg) dan uji
          CBR Lapangan (DCP).                                              
         Staking-out, menentukan lebar dan tebal hamparan sebagai gambar rencana.
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
     B. Pelaksanaan                                                        
         Pengadukkan material LPA : dilaksanakan di stock pile (lokasi pengadukan) dengan komposisi
          berdasarkan JMF dan hasil percobaan lapangan, pengadukan dilaksanakan setiap maksimal ≤ 50 m3
          agar menghasilkan campuran yang homogen, digunakan peralatan excavator dan Wheel Loader.
                                                                           
         Material LPA diangkut dengan menggunakan dump truk, pemuatan menggunakan wheel Loader,
          jarak hauling diatur sedemikian rupa (memeprhatikan faktor gembur dari hasil percobaan
          pelaksanaan) sehingga penghamparan dapat dilaksanakan efektif dan efisien.
         Penghamparan menggunakan Motor Grader, tebal hamparan sesuai hasil percobaan pelaksanaan,
          dilaksanakan selebar rencana, perapian hamparan dilaksanakan dengan tenaga manusia dengan
          peralatan sesuai keperluan lapangan. Selama proses penghamparan dilakukan control kadar air,
          sehingga akan dihasilkan kadar air optimal pada saat pemadatan dilaksanakan. Dimensi dan
          kelandaian permukaan dilaksanakan sesuai dengan gambar rencana.  
         Pemadatan menggunakan Vibrator Roller (berat 8-12 ton), dilaksanakan mulai dari bagian yang
          rendah berangsur-angsur menuju bagian yang lebih tinggi, jumlah lintasan sesuai dengan hasil
                                                                           
          percobaan pelaksanaan. Pemadatan dihentikan jika diyakini tercapai kepadatan yang disyaratkan.
     C. Pengujian dan Pengukuran                                           
         Pengujian mutu : uji gradasi dan PI (di laboratorium), uji kepadatan (sand cone di lapangan), uji
          CBR Lapangan (DCP).                                              
         Pengukuran : dimensi (panjang, lebar dan tebal dilaksanakan secara manual), kelandaian
          (menggunakan pesawat waterpass atau theodolit) dan kerataan permukaan (menggunakan mistar
                                                                           
          ukur).                                                           
     D. Peralatan yang digunakan;                                          
       o  Alat berat Motor Grader, Vibratory Roller, Water Tanker          
       o  Meteran; untuk mengukur dimensi hamparan                         
       o  Sekop/cangkul, gerobak; sebagai media manual                     
     E. Perlengkapan K3;                                                   
       o  Rompi safety proyek; agar mudah terlihat, sehingga mudah dikenali dan tidak tertabrak oleh
          pengendara jalan raya                                            
                                                                           
       o  Rambu-rambu peringatan; sebagai pertanda adanya pekerjaan        
       o  Helm safety proyek; sebagai pelindung kepala dari cidera benturan
       o  Sepatu safety proyek;                                            
                                                                           
       Perlengkapan K3 yang harus disiapkan:                               
         1. Safety Helmet                                                  
         2. Masker                                                         
         3. Safety Gloves                                                  
                                                                           
         4. Safety Shoes                                                   
         5. Pembatas Area                                                  
         6. Rambu-rambu                                                    
  2. Perkerasan Beton Semen dengan Anyaman Tulangan Tunggal                
                                                                           
  Prosedur Pelaksanaan Pekerjaan/Urutan Pengerjaan                         
  a. Persiapan                                                             
                                                                           
     - Pastikan Pekerjaan Lapis Pondasi Bawah dan bagian penunjangnya sudah disetujui direksi/
       pengawas, baik dari aspek kekuatan maupun elevasi.                  
                                                                           
     - Pastikan pemasangan Tulangan baja sudah terpasang sesuai gambar dan sudah disetujui Direksi.
     - Persetujuan pelaksanaan Pekerjaan sudah diterima dan dapat dilaksanakan.
                                                                           
     - Formwork sudah terpasang dengan benar dan sudah disetujui direksi.  
                                                                           
     - Datangkan Campuran beton yang sudah disetujui spesifikasinya ke lokasi pekerjaan.
  b. Pengecoran                                                            
                                                                           
     - Beton di-cor ke dalam bekisting.                                    
     - Beton diratakan sesuai ketinggian form work menggunakan tenaga manusia (manual).
                                                                           
     - Lakukan pengetaran menggunakan concrete vibrator                    
                                                                           
     - Setelah setting beton langsung digrooving dengan merata             
                                                                           
  c. Perawatan                                                             
     - Dilakukan Pemeriksaan dan Perawatan terhadap beton menggunakan curing compound
                                                                           
     - Dilakukan Pemeriksaan akhir                                         
                                                                           
     Tenaga yang dibutuhkan :                                              
                                                                           
       -  Pekerja                                                          
       -  Tukang                                                           
                                                                           
       -  Mandor                                                           
     Bahan yang digunakan :                                                
                                                                           
       -  Semen                                                            
                                                                           
       -  Pasir                                                            
       -  Agregat Kasar                                                    
                                                                           
       -  Baja Tulangan Polos                                              
       -  Joint sealent                                                    
                                                                           
       -  Cat anti karat                                                   
                                                                           
       -  Exspansion Cap                                                   
       -  Polytene 125 mikron                                              
                                                                           
       -  Curing Compound                                                  
       -  Formwork plate                                                   
                                                                           
       -  Paku                                                             
                                                                           
       -  Additive                                                         
       -  Crack induser                                                    
                                                                           
                                                                           
     Peralatan yang dibutuhkan :                                           
       -  Wheel Loader                                                     
                                                                           
       -  Concrete Pan Mixer (Batching plan)                               
       -  Truck Mixer                                                      
                                                                           
       -  Concrete Vibrator                                                
                                                                           
       -  Water tank truck                                                 
       -  Split form Paver                                                 
                                                                           
     Concrete Cutter                                                       
  3. Lapis Pondasi bawah Beton Kurus                                       
       Perlengkapan K3 yang harus disiapkan:                               
                                                                           
         7. Safety Helmet                                                  
         8. Masker                                                         
                                                                           
         9. Safety Gloves                                                  
         10. Safety Shoes                                                  
                                                                           
         11. Pembatas Area                                                 
                                                                           
         12. Rambu-rambu                                                   
  Uraian Kerja :                                                           
                                                                           
    Sebelum pengecoran beton dimulai, seluruh acuan, baja tulangan dan benda lain yang harus
     dimasukkan kedalam beton (seperti pipa atau selongsong) harus sudah dipasang dan diikat kuat
                                                                           
     sehingga tidak bergeser pada saat pengecoran. Acuan yang dibuat dapat dari kayu atau baja
     dengan sambungan dari adukan yang kedap dan kaku untuk mempertahankan posisi yang
                                                                           
     diperlukan selama pengecora, pemadatan dan perawatan, dan acuan dibuat sedemikian sehingga
     dapat dibongkar tanpa merusak beton. Segera sebelum beton dimulai, acuan harus dibasahi
                                                                           
     dengan air atau diolesi minyak disisi dalamnya dengan minyak yang tidak meninggalkan bekas.
                                                                           
     Bahan dan material yang telah disetujui dicampur dan diaduk menggunakan Concrete Mixer
     dilokasi pekerjaan, kemudian campuran beton dituang kedalam acuan.    
                                                                           
                                                                           
    Kegiatan pengecoran dilanjutkan tanpa berhenti sampai dengan sambungan konstruksi yang telah
     disetujui sebelumnya atau sampai pekerjaan selesai. Untuk pemadatan campuran digunakan
                                                                           
     concrete vibrator, dengan ketentuan penggunaan mengikuti spesifikasi teknik. Sekelompok pekerja
     dengan menggunkan alat bantu akan merapihkan pengecoran setelah pengecoran dilaksanakan.
                                                                           
                                                                           
    Acuan tidak dibongkar dari bidang vertical, dinding, kolom yang tipis struktur yang sejenis lebih
     awal 30 jam setelah pengecoran beton. Cetakan yang ditopang oleh perancahdibawah pelat, balok,
                                                                           
     gelegar, atau struktur busur, tidak dibongkar hingga pengujian menunjukan bahwa paling sedikit
                                                                           
     85 % dari kekuatan rancangan beton telah dicapai.                     
     Tenaga yang dibutuhkan :                                              
                                                                           
       -  Pekerja                                                          
       -  Tukang                                                           
                                                                           
       -  Mandor                                                           
                                                                           
     Bahan yang digunakan :                                                
                                                                           
       -  Semen                                                            
       -  Pasir                                                            
                                                                           
       -  Agregat Kasar                                                    
                                                                           
       -  Multiplex 12 mm                                                  
       -  Kayu acuan                                                       
                                                                           
       -  Paku                                                             
                                                                           
     Peralatan yang dibutuhkan :                                           
                                                                           
       -  Wheel Loader                                                     
       -  Concrete Pan Mixer (Batching plan)                               
       -  Truck Mixer                                                      
                                                                           
       -  Concrete Vibrator                                                
       -  Water tank truck                                                 
                                                                           
                                                                           
 E. DIVISI 6 PERKERASAN ASPAL                                              
                                                                           
  1. LAPIS RESAP PENGIKAT – ASPAL CAIR/EMULSI                              
                                                                           
     Pekerjaan lapis resap pengikat pelaksanaan di atas lapis pondasi agregat yang telah dipadatkan
     sesuai dengan spesifikasi teknis atau sudah disetujui oleh Direksi Pekerjaan. Kondisi lapis pondasi
     Agregat yang akan dilapisi dengan lapis resap pengikat dalam kondisi kering.
                                                                           
     Tahapan Persiapan :                                                   
                                                                           
     Pemasangan rambu-rambu kerja dan rambu-rambu lalu lintas untuk menjaga keselamatan pekerja
     dan pengguna jalan lainnya. Lokasi yang akan dikerjakan dibersihkan dari kotoran dan sisa-sisa
     material di atas lahan/agregat (Kelas A) yang akan disiram Lapis Resap Pengikat. Buang kotoran
     dan debu dengan dibantu compressor, jika perlu dibantu secara manual dengan sapu/sikat. Pastikan
                                                                           
     kondisi permukaan dalam keadaan bersih dan kering.                    
                                                                           
     Perlengkapan K3 yang harus disiapkan:                                 
                                                                           
     1. Safety Helmet                                                      
                                                                           
     2. Masker                                                             
                                                                           
     3. Safety Gloves                                                      
                                                                           
     4. Safety Shoes                                                       
                                                                           
     5. Pembatas Area                                                      
                                                                           
     6. Rambu-rambu                                                        
                                                                           
     7. Traffic Cone                                                       
                                                                           
                                                                           
     Tahapan Pelaksanaan :                                                 
     Material lapis resap pengikat-aspal cair terdiri dari campuran aspal murni dengan minyak tanah dan
                                                                           
     dicampur dalam tangki asphalt distributor dengan pemanasan sesuai spesifikasi teknis.
     Perbandingan aspal murni dan minyak tanah juga disesuaikan dengan spesifikasi teknis. Lakukan
     penyiraman Lapis Resap Pengikat-Aspal Cair di atas permukaan lahan/agregat. Atur ketinggian
     nozzle dan kecepatan kendaraan agar didapatkan ketebalan sesuai dengan spesifikasi teknis dan
     tidak terjadi genangan. Lakukan pemasangan paper test di atas permukaan lahan untuk mengetahui
                                                                           
     ketebalan lapisan resap pengikat yang terhampar. Pada bekas paper test dilakukan penyiraman
     kembali. Lakukan penyiraman secara terus menerus sampai seluruh permukaan terpasang lapis
     resap pengikat. Selama masa peresapan, permukaan lapis resap pengikat harus dijaga agar tidak
     terkelupas oleh ban kendaraan, hal ini dapat dilakukan dengan melakukan penutupan sementara dari
                                                                           
     lalu lintas. Jika lalu lintas diizinkan lewat maka harus digunakan bahan penyerap (blotter material)
     dari hasil pengayakan kerikil atau batu pecah.                        
     Pengujian yang dilakukan :                                            
     Paper test : untuk menentukan pemakaian lapis resap pengikat per meter persegi.
                                                                           
                                                                           
     Tenaga yang digunakan :                                               
     -  Pekerja                                                            
     -  Mandor                                                             
                                                                           
     Bahan yang digunakan :                                                
                                                                           
     -  Aspal                                                              
     -  Kerosene                                                           
                                                                           
     Alat yang digunakan :                                                 
                                                                           
     -  Compressor (untuk membersihkan lahan dari kotoran)                 
     -  Asphalt Distributor (untuk menghampar/menyemprot aspal cair)       
                                                                           
                                                                           
  2. Laston Lapis AUS AC-WC / Laston Lapis Antara AC-BC                    
                                                                           
    Pekerjaan ini dilaksanakan diatas Lapis Pondasi Agregat Kelas A pada daerah pelebaran dan di atas
    daerah overlay, composisi Aspal Hotmix (AC – BC) Lapis Antara terdiri dari campuran Agregat
    Kasar + Agregat Halus + Filler + Aditif + Aspal minyak. Besarnya composisi campuran sesuai
    dengan JMF yang disetujui oleh pengawas lapangan yang dikeluarkan oleh Laboratorium.
                                                                           
    Keseluruhan material tersebut diaduk menjadi satu kesatuan yang monolit dengan menggunakan alat
    Asphalt Mixing Plant (AMP). Setelah campuran teraduk rata untuk selanjutnya adukan tersebut
    dituang kedalam dump truck dan kemudian dump truck membawa hotmix tersebut kelokasi
    pekerjaan/penghamparan.Untuk suhu hotmix disesuaikan dengan kondisi dan jarak angkut aspal
    kelokasi pekerjaan/lokasi penghamparan.                                
                                                                           
    Perlengkapan K3 yang harus disiapkan:                                  
                                                                           
    1. Safety Helmet                                                       
                                                                           
    2. Masker                                                              
                                                                           
    3. Safety Gloves                                                       
                                                                           
    4. Safety Shoes                                                        
                                                                           
    5. Pembatas Area                                                       
                                                                           
    6. Rambu-rambu                                                         
                                                                           
    7. Traffic Cone                                                        
                                                                           
    Urutan kerja :                                                         
                                                                           
    Prinsip dan urutan kerja untuk penghamparan aspal Laston Lapis AUS AC-WC / Laston Lapis
                                                                           
    Antara AC-BC ini adalah sebagai berikut :                              
                                                                           
    a. Penghamparan                                                        
      Material Aspal Hotmix (AC – BC)                                     
       Composisi adukan untuk hotmix disesuaikan dengan job mix formula yang sudah disepakati
       sesuai dengan speck yang digunakan. Campuran material diaduk dengan menggunakan AMP
       dan kemudian dituang keatas dump truk dan dump truck membawa hotmix kelokasi
                                                                           
       penghamparan. Untuk menjaga kehilangan suhu aspal yang berlebihan dump truck tersebut
       ditutup dengan menggunakan terpal.                                  
                                                                           
    b. Placing / spreading                                                 
       a. Persiapan lahan pengaspalan                                      
       b. Penghamparan                                                     
          Hotmix dibawa dengan dump truck kelokasi penghamparan.          
                                                                           
          Penghamparan hotmix dilakukan dengan menggunakan alat hampar aspal finisher.
          Hotmix dari damp truck dituang ke bak finisher.                 
          Finisher menghampar hotmix sesuai dengan dimensi/gambar yang disetujui oleh
           pengawas lapangan.                                              
                                                                           
       Compacting/Pemadatan                                                
      Setelah aspal terhampar untuk selanjutnya hamparan aspal dipadatkan dengan menggunakan alat
       tandem roller dan kemudian diikuti dengan PTR.                      
      Step pemadatan dilakukan dari sebelah sisi badan jalan.             
                                                                           
      Pemadatan dilakukan berulang – ulang sesuai dengan jumlah lintasan alat yang terdapat dalam
       trial dan spesifikasi teknis pekerjaan.                             
                                                                           
    c. Testing                                                             
                                                                           
      Pengujian untuk pemadatan aspal hotmix ini dilakukan dengan menggunakan Marshall Test.
      Pengetesan dilakukan dilaboratorium. Untuk benda uji diambil dari hotmix yang sudah dihampar
      dan digiling dengan menggunakan alat core drill. Pengambilan sample dilakukan paling sedikit
      harus diambil 2 titik pengujian per penampang melintang per lajur dengan jarak memanjang antar
      penampang melintang yang diperiksa tidak lebih dari 100 meter.       
                                                                           
     Tenaga yang digunakan:                                                
                                                                           
         Pekerja                                                          
                                                                           
                                                                           
         Mandor                                                           
                                                                           
     Bahan yang digunakan:                                                 
                                                                           
         Lolos Screen2 Ukuran (9,5 – 19,0)                                
                                                                           
         Lolos Screen2 Ukuran (0 – 5)                                     
                                                                           
         Filler Added                                                     
                                                                           
         Aspal                                                            
                                                                           
     Peralatan-peralatan yang dipergunakan :                               
                                                                           
      AMP untuk Produksi Hotmix                                           
      Dump truck untuk pengangkutan Hotmix.                               
      Asphalt Finisher untuk Menghampar                                   
                                                                           
      Tandem Roller untuk Pemadatan                                       
      PTR untuk Pemadatan dan Penyiraman                                  
      Genset                                                              
      Wheel Loader                                                        
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
  3. Bahan anti pengelupasan                                               
                                                                           
                                                                           
    Bahan Anti Pengelupasan (Anti Stripping Agent)                         
                                                                           
    Bahan anti pengelupasan hanya digunakan jika stabilitas Marshall sisa campuran beraspal sebelum
    ditambah bahan anti pengelupasan minimum 90%. Bahan anti pengelupasan (anti striping agent)
    harus ditambahkan dalam bentuk cairan di timbangan aspal AMP dengan mengunakan pompa
    penakar (dozing pump) sesaat sebelum dilakukan proses pencampuran basah di pugmil. Kuantitas
                                                                           
    pemakaian aditif anti striping dalam rentang 0,2% - 0,4% terhadap berat aspal. Jenis bahan anti
    pengelupasan yang digunakan haruslah yang disetujui Konsultan Pengawas.Bahan anti striping harus
    sesuai dengan Tabel (6) dan Tabel (7).                                 
                                                                           
                                                                           
                                                                           
    Tabel (6) Ketentuan Bahan Anti Pengelupasan Mengandung Amine           
    Tabel (7) - Kompatibilitas Bahan Anti Pengelupasan dengan Aspal        
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
F. DIVISI 7. STRUKTUR                                                      
                                                                           
     1. Beton Struktur, Fc’ 20 MPa                                         
                                                                           
       Perlengkapan K3 yang harus disiapkan:                               
                                                                           
       1. Safety Helmet                                                    
                                                                           
       2. Masker                                                           
                                                                           
       3. Safety Gloves                                                    
       4. Safety Shoes                                                     
                                                                           
       5. Rambu-rambu                                                      
                                                                           
       Urutan pekerjaan pengecoran beton :                                 
                                                                           
        Menyiapkan semua peralatan kerja yang mendukung pelaksanaan kerja pengecoran beserta
                                                                           
         alat – alat lab yang dibutuhkan.                                  
        Membersihkan bekisting dari sampah yang terdapat didalamnya.      
                                                                           
        Mengecek kembali begisting yang sudah dibuat apakah sudah benar dan kuat dan menutupi
                                                                           
         celah – celah yang masih terdapat pada begisting agar beton tidak bocor.
        Agregat kasar, semen, pasir dan air dengan komposisi dan takaran sesuai JMF diaduk dengan
                                                                           
         alat pengaduk mekanis concrete mixer                              
                                                                           
        Mengambil sample beton segar dari concrete mixer untuk melakukan slump test dan
         pembuatan sample beton untuk benda uji.                           
                                                                           
        Menuangkan beton segar kedalam begisting yang sudah disiapkan.    
                                                                           
        Melakukan getaran pada coran dengan menggunakan alat concrete vibrator untuk mengurangi
         void yang mungkin terdapat pada beton ceron.                      
                                                                           
        Melakukan pengecoran sampai begisting penuh.                      
        Merapikan permukaan hasil coran dengan menggunakan raskam         
        Setelah beton mulai mengeras beton itu harus di curring dengan cara menggunakan goni basi,
                                                                           
         menyirap beton secara rutin atau menggenangi coran dengan air sampai minmal 3 hari. Hal
         ini dilakukan untuk mengantisipasi keretakan beton yang diakibatkan oleh pemuaian beton
                                                                           
         yang tidak serentak.                                              
        Melakukan finishing dan perapian                                  
                                                                           
       Bahan yang digunakan :                                              
                                                                           
        Semen                                                             
                                                                           
        Pasir Beton                                                       
        Agregat Kasar                                                     
                                                                           
        Multiplek 12 mm                                                   
                                                                           
        Kayu Perancah                                                     
        Paku                                                              
                                                                           
       Peralatan yang digunakan :                                          
                                                                           
        Concrete Pan Mixer                                                
                                                                           
        Truck Mixer                                                       
        Water Tank Truck                                                  
                                                                           
        Concrete Vibrator                                                 
                                                                           
        Alat bantu                                                        
                                                                           
       Tenaga yang digunakan :                                             
                                                                           
        Pekerja                                                           
        Tukang                                                            
                                                                           
        Mandor                                                            
                                                                           
  2. Beton Mutu sedang fc’15 Mpa                                           
                                                                           
      Perlengkapan K3 yang harus disiapkan:                                
                                                                           
      1. Safety Helmet                                                     
                                                                           
      2. Masker                                                            
                                                                           
      3. Safety Gloves                                                     
                                                                           
      4. Safety Shoes                                                      
                                                                           
      5. Pembatas Area                                                     
                                                                           
      6. Rambu-rambu                                                       
      7. Traffic Cone                                                      
                                                                           
    a. Tahap pelaksanaan                                                   
                                                                           
       1) Bahan-bahan untuk campuran beton (semen, pasir, aggregat kasar dan air)
       2) Material (pasir, semen, aggregat kasar) pencampuran dilakukan menggunakan concerete pan
          mixer.                                                           
       3) Ratakan dan padatkan lapisan dibawah beton sampai memenuhi spesifikasi umum.
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
       4) Cutting/Potong pinggiran aspal secara merata sampai kedalaman yang disyaratkan.
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
       5) Selanjutnya pasang bekisting (disyaratkan yang kaku/dari besi) dan tutup lapisan dibawah
          beton dan permukaan aspal menggunakan plastik cor.               
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
       6) Adukan beton ready mix dituang ke dalam cetakan.                 
       7) Padatkan adukan beton secara merata menggunakan Concerete Vibrator.
       8) Permukaan beton dibentuk dan diratakan perlahan-lahan menggunakan Towel dan
                                                                           
          dilanjutkan                                         menggunakan  
          mistar  lurus                                           sampai   
          permukaan                                          menjadi rata  
          dan halus.                                                       
       9) Perawatan dilakukan dengan menutupi permukaan beton menggunakan karung basah.
          Setelah minimal 12 jam pada saat pengecoran bekisting dibongkar. 
    b. Tenaga Kerja:                                                       
                                                                           
       1) Pekerja                                                          
       2) Tukang                                                           
       3) Mandor                                                           
    c. Bahan:                                                              
                                                                           
       1) Semen                                                            
       2) Pasir Beton                                                      
       3) Aggregat Kasar (Kerikil)                                         
       4) Multiplek 12 mm                                                  
       5) Kayu Perancah                                                    
                                                                           
       6) Paku                                                             
       7) Plastik cor                                                      
          Peralatan:                                                       
             Concrete Pan Mixer                                           
                                                                           
             Truck Mixer                                                  
             Water Tank Truck                                             
             Concrete Vibrator                                            
                                                                           
             Asphalt Cutter                                               
                                                                           
                                                                           
  3. Beton Siklop, fc’15 Mpa                                               
  Beton siklop (15 Mpa) merupakan beton mutu sedang yang bersifat structural yang digunakan untuk
                                                                           
  beton bertulang seperti bangunan mewah, jembatan, lantai dan berkerasan beton semen.Dalam kegiatan
                                                                           
  ini beton mutu sedang diperuntukan untuk struktur bangunan bawah jembatan (Abutment, Wing Wall
  dan Petak Injak).Pekerjaan ini juga sudah termasuk pembuatan perancah dan bekisting untuk acuan
                                                                           
  pengecoran.                                                              
                                                                           
  Sebelum melakukan pekerjaan, penyedia jasa terlebih dahulu menunjukan semen usulan agregat dan
  zampuran yang memadai berdasarkan hasil pengujian material dan campuran di laboratorium
                                                                           
  berdasarkan kuat beton untuk umur 7 dan 28 hari atau umur yang lain yang telah ditentukan oleh
                                                                           
  Direksi Pekerjaan, yang tertuang secara berurutan sesuai dalam spesifikasi teknik mulai dari pengujian
  DMF hingga persetujuan JMF.                                              
                                                                           
  Proporsi bahan dan berat penakaran hasil perhitungan harus memenuhi kriteria teknis utama, yaitu
  kecelakaan (workability), kekuatan (straight) dan keawetan (durability). Penyedia jasa akan membuat
                                                                           
  gambar detail untuk seluruh perancah uang akan digunakan dan memperoleh persetujuan direksi
                                                                           
  pekerjaan sebelum setiap pekerjaan perancah dimulai.                     
  Pelaksanaan                                                              
                                                                           
  Sebelum pengecoran beton dimulai seluruh acuan baja tulangan dan benda lain harus dimasukan
                                                                           
  kedalam beton (seperti pipa atau selongsong) harus sudah dipasang dan diikat kuat sehingga tidak
  bergeser pada saat pengecoran. Acuan yang dibuat dapat dari kayu atau baja dengan sambungan dari
                                                                           
  adukan kedap dan kaku untuk mempertahankan posisi yang diperlukan selama pengecoran pemadatan
                                                                           
  dan perawatan dan acuan dibuat sedemikian sehingga dapat dibongkar tanpa merusak beton. Segera
  sebelum beton dimulai, acuan harus dibasahi dengan air atau diolesi minyak disisi dalamnya
                                                                           
  dengan minyak yang tidak meninggalkan bekas. Bahan dan material yang telah disetujui
  dicampur dan diaduk menggunakan Concrete Mixer dilokasi pekerjaan, kemudian campuran beton
                                                                           
  dituang kedalam acuan.                                                   
                                                                           
  TenagaKerja:                                                             
                                                                           
  - Pekerja                                                                
                                                                           
  - Tukang                                                                 
  - Mandor                                                                 
                                                                           
                                                                           
  Bahan yang dibutuhkan:                                                   
   - Semen                                                                 
                                                                           
   - Pasir Beton                                                           
   - Aggregat Kasar (Kerikil)                                              
                                                                           
   - Batu                                                                  
                                                                           
   - Multiplex 12 mm                                                       
   - Kayu Perancah                                                         
                                                                           
   - Paku                                                                  
                                                                           
   Alat yang digunakan :                                                   
                                                                           
   - Concrete Pan Mixer                                                    
   - Truck Mixer                                                           
                                                                           
   - Water Tank Truck                                                      
     Conc. Vibrator                                                        
                                                                           
                                                                           
  4. Baja Tulangan Polos BjTP 280 / Baja Tulangan Sirip BjTS 420B          
                                                                           
       Pekerjaan baja tulangan Polos BjTP 280 merupakan pekerjaan penulangan untuk BoxCuilvert.
       Setelah bekisting dipasang dan pasangan bekisting kuat maka pekerjaan perakitan besi tulangan
                                                                           
       dapat dilakukan. Pabrikasi besi tulangan dilakukan di work shop.    
                                                                           
       Perlengkapan K3 yang harus disiapkan :                              
                                                                           
       1. Safety Helmet                                                    
       2. Masker                                                           
                                                                           
       3. Safety Gloves                                                    
       4. Safety Shoes                                                     
                                                                           
       5. Rambu-rambu                                                      
                                                                           
       Uraian pekerjaan pemasangan besi tulangan :                         
                                                                           
       1) Melakukan pabrikasi besi di work shop                            
                                                                           
       2) Pemotongan dan pembentukan besi tulangan dilakukan sesuai dengankondisi lapangan atau
         sesuai dengan gambar kerja atau petunjuk dari konsultan/direksi lapangan.
                                                                           
       3) Besi tulangan yang sudah dipabrikasi dibawa kelokasi pekerjaan.  
       4) Menginstal potongan – potongan besi tulangan sesuai dengan bentuk dari lokasi pemasangan.
                                                                           
       5) Mengikat/menyambung potongan – potongan besi dengan menggunakan kawat ikat (bendrat)
                                                                           
       6) Memastikan ikatan bendrat sudah terpasang semua dengan baik dan kuat.
       7) Memberi dacking beton pada sisi begisting dengan besi tulangan. Hal ini bertujuan untuk
                                                                           
         menjaga selimut beton.                                            
                                                                           
       Tenaga yang diperlukan :                                            
                                                                           
        Pekerja                                                           
                                                                           
        Tukang                                                            
                                                                           
        Mandor                                                            
                                                                           
                                                                           
                                                                           
       Bahan yang digunakan :                                              
                                                                           
        Baja Tulangan Polos BjTP 280                                      
                                                                           
        Baja Tulangan Sirip BjTS 420B                                     
        Kawat Beton                                                       
                                                                           
                                                                           
       Peralatan :                                                         
        Alat Bantu                                                        
                                                                           
                                                                           
  5. Pasangan Batu                                                         
    a. Pekerjaan Pasangan Batu                                             
                                                                           
       Pemasangan pasangan batu digunakan sebagai pondasi plat duiker dan diinding penahan tanah.
                                                                           
       Pasangan batu dibuat berdasarkan bentuk dan dimensi yang disesuaikan dengan lapangan dan
       gambar. Pekerjaan pasangan batu ini dikerjakan oleh tukang batu pekerja.
                                                                           
      Perlengkapan K3 yang harus disiapkan:                                
                                                                           
                                                                           
      1. Safety Helmet                                                     
      2. Masker                                                            
                                                                           
      3. Safety Gloves                                                     
      4. Safety Shoes                                                      
                                                                           
      5. Pembatas Area                                                     
      6. Rambu-rambu                                                       
                                                                           
      7. Traffic Cone                                                      
    b. Urutan pekerjaan pasangan batu :                                    
                                                                           
       1) Membuat mix design untuk campuran mortar yang akan digunakan sebagai perekat batu.
                                                                           
       2) Melakukan survey untuk menentukan tempat, elevasi, dan dimensi untuk pasangan batu
          yang akan dibuat.                                                
                                                                           
       3) Menyiapkan material ( semen, pasir, dan batu kali ) dan alat kerja ( molen, sendok semen,
          kayu profil sebagai acuan pasangan ) untuk pemasangan batu kali Menggali tanah untuk
                                                                           
          pondasi pasangan batu sesuai dengan ukuran survey yang sudah dipasang.
                                                                           
       4) Mengaduk mortar dengan menggunakan molen dengan campuran adukan disesuaikan
          dengan mix design yang digunakan.                                
                                                                           
       5) Menyusun batu kali dan merekatkannya dengan menggunakan mortar yang sudah disiapkan.
       6) Perapihan kepala pasangan batu setelah pemasangan.               
                                                                           
    c. Tenaga yang diperlukan:                                             
                                                                           
           Pekerja                                                        
           Tukang                                                         
                                                                           
           Mandor                                                         
                                                                           
    d. Bahan yang digunakan:                                               
           Batu                                                           
                                                                           
           Semen (PC)                                                     
                                                                           
           Pasir                                                          
    e. Peralatan yang digunakan :                                          
                                                                           
         Concrete Mixer                                                   
         Water Tanker                                                     
                                                                           
         Gerobak                                                          
                                                                           
         Cangkul                                                          
         Sekop                                                            
                                                                           
                                                                           
  6. Bronjong dengan Kawat yang dilapisi Galvanis                          
      Perlengkapan K3 yang harus disiapkan:                                
                                                                           
      1. Safety Helmet                                                     
                                                                           
      2. Masker                                                            
      3. Safety Gloves                                                     
                                                                           
      4. Safety Shoes                                                      
                                                                           
      5. Pembatas Area                                                     
      6. Rambu-rambu                                                       
                                                                           
      Urutan pekerjaan:                                                    
                                                                           
        Keranjang kawat bronjong direntangkana dan dibentuk sesuai dengan konstruksi yang
                                                                           
         diinginkan                                                        
                                                                           
        Batu ditempatkan satu demi satu sehingga rongga sesedikit mungkin 
                                                                           
        Anyaman kawat ditutup dan diikat                                  
                                                                           
     Bahan yang digunakan:                                                 
        Bronjong pabrikasi t = 2,7 mm                                     
                                                                           
        Batu                                                              
                                                                           
     Peralatan yang digunakan :                                            
     Alat Bantu: - Tang                                                    
                                                                           
               - Pemotong kawat                                            
               - Palu pemecah batu                                         
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
                                                                           
     Tenaga yang diperlukan:                                               
                                                                           
         Pekerja                                                          
                                                                           
         Tukang                                                           
         Mandor                                                           
                                                                           
                                                                           
G. DIVISI 9 PEKERJAAN HARIAN DAN PEKERJAAN LAIN LAIN                       
                                                                           
                                                                           
 A. MARKA JALAN TERMOPLASTIK                                               
    Tahap persiapan :                                                      
                                                                           
    Marka jalan dipasang setelah seluruh pekerjaan aspal dan bahu jalan sudah selesai dan kondisi kering
    serta bersih. Untuk mendapatkan hasil marka yang bagus pastikan saat pemasangan, kondisi cuaca
                                                                           
    panas dan hotmix sudah beberapa lama berselang dari waktu penghamparan terakhir.
                                                                           
     Perlengkapan K3 yang harus disiapkan:                                 
                                                                           
      1. Safety Helmet                                                     
                                                                           
      2. Masker                                                            
      3. Safety Gloves                                                     
                                                                           
      4. Safety Shoes                                                      
      5. Rambu-rambu                                                       
                                                                           
                                                                           
    Tahap pelaksanaan :                                                    
                                                                           
    Ukur centerline jalan untuk marka tengah, dan gunakan alat Bantu tali untuk membentuk lurus dan
                                                                           
    lengkung pada tikungan agar didapat hasil yang bagus. Pastikan jumlah glassbead cukup menutupi
    pasta marka, sehingga jika terkena cahaya lampu lalu-lintas marka benar-benar memberikan pantulan
                                                                           
    yang sempurna. Ukur hasil pemasangan dengan meter untuk mendapatkan kuantitas pekerjaan
                                                                           
    terpasang.                                                             
                                                                           
    Bahan yang digunakan :                                                 
                                                                           
    - Glassbead (butiran kaca yang digunakan harus seusai dengan SNI 06-4825-1998)
                                                                           
    - Cat marka thermoplastik (jenis padat sesuai SNI 06-4826-1998)        
    - Thinner                                                              
                                                                           
                                                                           
    Alat yang digunakan :                                                  
                                                                           
    - Comppressor                                                          
                                                                           
    - Alat pembuat marka jalan thermoplastic                               
                                                                           
                                                                           
                                                                           
    - Dump truck                                                           
                                                                           
    - Alat bantu                                                           
                                                                           
                                                                           
     B. REL PENGAMAN                                                       
       Perlengkapan K3 yang harus disiapkan:                               
                                                                           
       1. Safety Helmet                                                    
       2. Masker                                                           
                                                                           
       3. Safety Gloves                                                    
       4. Safety Shoes                                                     
                                                                           
       5. Rambu-rambu                                                      
                                                                           
       Urutan Pekerjaan:                                                   
       -  Kesatuam pondasi, pelat dan tiang rambu disiapkan dan dipasang ditempat yang telah
                                                                           
          ditentukan                                                       
       Tenaga yang dibutuhkan :                                            
                                                                           
       -  Pekerja                                                          
                                                                           
       -  Mandor                                                           
       Bahan yang dibutuhkan :                                             
                                                                           
       -  Cat Galvanis                                                     
       -  Beton Fc 15 MPa                                                  
                                                                           
       -  Baut dan material lain                                           
       Peralatan yang dibutuhkan :                                         
                                                                           
       Alat Bantu; sekop linggis dsb.
Tenders also won by PT Era Bangun Sarana
Authority
16 November 2017Preservasi Rekonstruksi Jalan Weda - Sagea/PnKementerian Pekerjaan Umum dan Perumahan RakyatRp 49,849,725,000
3 February 2022Preservasi Jalan Nimbotong - Bonggo - Betaf - SarmiKementerian Pekerjaan Umum dan Perumahan RakyatRp 40,506,795,000
31 December 2021Preservasi Jalan Ruas Menawi - Saubeba - YobiKementerian Pekerjaan Umum dan Perumahan RakyatRp 40,030,000,000
15 March 2016Peningkatan Jalan Sp. Samboja - Sp. Muara JawaUnit Layanan Pengadaan Pemprov. KaltimRp 39,740,950,000
5 April 2021Penanganan Longsoran Ruas Jalan Waropko - Mindiptana - Tanah MerahKementerian Pekerjaan Umum dan Perumahan RakyatRp 39,536,730,000
20 May 2024Lanjutan Pembangunan Jalan Teluk Sulaiman - Teluk SumbangKab. BerauRp 38,572,290,000
7 June 2025Pembangunan Jalan Jalur Utara Pulau Maratua (Apbd + Bankeu Prov)Kab. BerauRp 37,191,581,650
13 April 2020Rehabilitasi Dan Renovasi Sarana Prasarana Madrasah Sulawesi TenggaraKementerian Pekerjaan Umum dan Perumahan RakyatRp 33,872,240,000
9 November 2016Preservasi Dan Pelebaran Jalan Sanana - ManafKementerian Pekerjaan Umum dan Perumahan RakyatRp 32,870,800,000
11 June 2019Rehabilitasi Dan Renovasi Sarana Prasarana Sekolah Kab. Bombana Dan KolakaKementerian Pekerjaan Umum dan Perumahan RakyatRp 26,077,580,000