PEMERINTAH KABUPATEN ACEH BESAR
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan Prof. A. Madjid Ibrahim Telp. (0651) 92141 Fax. (0651) 92579
Kota Jantho - 23918
OWNER'S ESTIMATE (OE) / HPS
BIDANG BINA MARGA
RENCANA ANGGARAN BIAYA
( RAB )
SUB KEGIATAN :
PEMBANGUNAN JALAN
PEKERJAAN :
REHAB JALAN GAMPONG JEUMPET AJUEN-GAROT, KEC. DARUL
IMARAH
SUMBER DANA : DAU
TAHUN 2025
OWNER'S ESTIMATE (OE) / HPS
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
LOKASI : Kecamatan Darul Imarah
T.A : 2025
HARGA J U M L A H
NO. URAIAN PEKERJAAN VOLUME ANALISA SATUAN H A R G A
( Rp. ) ( Rp. )
I. PEKERJAAN PERSIAPAN
1 Pengukuran/ Pemasangan Profil 1 ,00 Pkt Ls - -
2 Mobilisasi 1 ,00 Pkt Ls - -
3 Administrasi Proyek 1 ,00 Pkt Ls - -
4 Papan Nama Proyek 1 ,00 Pkt Ls - -
5 Sistem Manajemen Keselamatan Konstruksi 1 ,00 Pkt Ls - -
SUB TOTAL -
II. PEKERJAAN JALAN
1 Galian Perkerasan Beraspal tanpa Cold Milling Machine 14,00 M3 Analisa EI-318 - -
2 Lapis Fondasi Agregat Kelas A 35,15 M3 Analisa EI-511 - -
3 Lapis Resap Pengikat - Aspal Cair/Emulsi 210,00 Ltr Analisa EI-611 - -
4 Laston Lapis Aus (AC-WC) 23,73 Ton Analisa EI-635a - -
SUB TOTAL -
MASTER ANALISA
MASTER ANALISA
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
LOKASI : Kecamatan Darul Imarah
T.A : 2025
JUMLAH HARGA
NO. URAIAN
( Rp. )
I. PEKERJAAN PERSIAPAN -
II. PEKERJAAN JALAN -
(A) JUMLAH -
(B) PPN = 11 % x (A) -
(C) TOTAL = (A) + (B) -
(D) DIBULATKAN -
Terbilang : Sembilan Puluh Tiga Juta Tiga ratus Lima Puluh Tujuh Rupiah
....................K..o...t.a.. .J..a..n...t.h,.o..,. . . . .. . . . . .J..u..n..i. .22002255
PKEoNnAsWulAtaRn Perencna
CV/PT........................................
CV. LAGUNA ENGINEERING
FA(HNRAMIZAA J ZELUALSF) AN, S.T, M.T
JABATDANirektur
HARGA DASAR SATUAN UPAH
HARGA HARGA
No. U R A I A N KODE SATUAN YG DIGUNAKAN SATUAN
( Rp.) ( Rp.)
1 Pekerja (L01) Jam - -
2 Tukang (L02) Jam - -
3 M a n d o r (L03) Jam - -
4 Operator (L04) Jam - -
5 Pembantu Operator (L05) Jam - -
6 Sopir / Driver (L06) Jam - -
7 Pembantu Sopir / Driver (L07) Jam - -
8 Mekanik (L08) Jam - -
9 Pembantu Mekanik (L09) Jam - -
10 Kepala Tukang (L10) Jam - -
11
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. U R A I A N KODE SATUAN SATUAN KETERANGAN
( Rp.)
1 Pasir Pasang (Sedang) M01b M3 - Base Camp
2 Pasir Kasar (Beton, Lapis Drainase) M01a M3 - Base Camp
3 Pasir Halus (untuk HRS) M01c M3 - Base Camp
4 Pasir Urug (ada unsur lempung) M01d M3 - Base Camp
5 Batu Kali M02 M3 - Lokasi Pekerjaan
6 Batu Belah/Batu Gunung M06 M4 - Lokasi Pekerjaan
7 Agregat Pecah Kasar M03 M3 - Base Camp
8 Agg. Halus LP A M04 M3 - Base Camp
10 Lolos screen1 ukuran ( 0 - 5) M89a M3 - Base Camp
F i l l e r (non semen) (limestone dust, kapur padam, dolomit,
M05 Kg Proses/Base Camp
14 fly ash) -
15 Batu Belah M06 M3 - Lokasi Pekerjaan
16 G r a v e l / Kerakal / Koral M07 M3 - Base Camp
17 Bahan Tanah Timbunan M08 M3 - Lokasi Pekerjaan
18 Bahan Pilihan M09 M3 - Base Camp
19 Aspal 60/70 M10 Kg - Base Camp
20 Aspal Modifikasi PG 76 M45 Kg. - Base Camp
21 Kerosen / Minyak Tanah (Non Subsidi) M11 LITER - Base Camp
22 Semen / PC (50kg) - Zak -
23 Semen / PC (kg) M12 Kg -
24 Silica Fume (Powder) M13 Kg - Lokasi Pekerjaan
25 Kawat Beton M14 Kg - Lokasi Pekerjaan
26 Batu Bronjong (untuk Bronjong) M15 Kg - Lokasi Pekerjaan
27 Bronjong dengan kawat dilapisi galvanis M15a Kg -
28 Bronjong dengan kawat dilapisi PVC M15b Kg -
29 S i r t u (4 ≤ PI ≤10 ; LL ≤ 35 %) M16 M3 - Lokasi Pekerjaan
30 S i r t u (4 ≤ PI ≤15 ; LL ≤ 35 %) M16 M3 -
31 Cat Marka (Non Thermoplas) M17a Kg - Lokasi Pekerjaan
32 Cat Marka (Thermoplastic) M17b Kg - Lokasi Pekerjaan
33 P a k u M18 Kg - Lokasi Pekerjaan
34 Kayu Perancah M19 M3 - Lokasi Pekerjaan
35 Pertamak M20 LITER - Pertamina
36 S o l a r Non Subsidi M21 LITER - Pertamina
37 Minyak Pelumas / Oli M22 LITER - Pertamina
38 Pipa Galvanis Dia.1.6'' M24 Batang - Lokasi Pekerjaan
39 Pipa Galvanis Dia. 3'' M24 M' - Lokasi Pekerjaan
40 F i l l e r (semen) M05 Kg - Proses/Base Camp
41 Agr. Kelas A (analisis) M26 M3 - Base Camp
42 Agr. Kelas B (analisis) M27 M3 - Base Camp
43 Arg. Kelas S (analisis) M29 M3 - Base Camp
44 Pipa HDPE (PN 10) Dia 150 mm 6 inchi M28 M' -
HARGA
No. U R A I A N KODE SATUAN SATUAN KETERANGAN
( Rp.)
45 Pipa HDPE (PN 10) Dia 200 mm 8 inchi M28 M' -
46 Pipa HDPE (PN 10) Dia 12 inchi M28 M' -
47 Lapis Drainase (analisis) M3 - Base Camp
48 Geotextile Filter Kelas 2 M23 M2 - Lokasi Pekerjaan
49 Geotextile Separator Kelas 1 M30a M2 - Lokasi Pekerjaan
50 Geotextile Separator Kelas 2 M30b M2 - Lokasi Pekerjaan
51 Geotextile Stabilisator M30c M2 - Lokasi Pekerjaan
52 Geomembrane (Waterproof) 1 mm M30d M2 - Lokasi Pekerjaan
53 Aspal Emulsi Modifikasi Polimer 1h M30 Liter - Base Camp
54 Aspal Emulsi M31 Kg - Base Camp
55 Gebalan Rumput M32 M2 - Lokasi Pekerjaan
56 Thinner M33 LITER - Lokasi Pekerjaan
57 Glass Bead M34 Kg - Lokasi Pekerjaan
58 Pelat Rambu (Eng. Grade) M35a BH - Lokasi Pekerjaan
59 Pelat Rambu (High I. Grade) M35b BH - Lokasi Pekerjaan
60 Rel Pengaman + Baut M36 M' - Lokasi Pekerjaan
61 Baja Tulangan BJTP 280 M39a Kg - Lokasi Pekerjaan
62 Baja Tulangan BJTS 420A M39b Kg - Lokasi Pekerjaan
63 Baja Tulangan BJTS 420B M39c Kg - Lokasi Pekerjaan
64 Baja Tulangan BJTS 520 M39d Kg - Lokasi Pekerjaan
65 Kapur M40 M3 - Hasil Proses
66 Chipping M41 M3 - Base Camp
67 Chipping (kg) M41kg Kg - Base Camp
68 Cat Besi M42 Kg - Base Camp
69 Pemantul Cahaya (Reflector) M43 Bh. - Base Camp
70 Arbocell M45 Kg. - Base Camp
71 Baja Bergelombang M46 Kg - Lokasi Pekerjaan
72 Baja Struktur (Rangka) M48 Kg - Lokasi Pekerjaan
73 Tiang Pancang Baja M49 M' - Lokasi Pekerjaan
74 Tiang Pancang Beton Pratekan M50 M' - Pelabuhan terdekat
75 Kawat Las M51 Kg - Lokasi Pekerjaan
76 Pipa Baja M52 Kg - Pelabuhan terdekat
77 Minyak Fluks M53 Liter - Base Camp
78 Bunker Oil M54 Liter - Base Camp
79 Asbuton Halus M55 Ton - Base Camp
80 Baja Prategang M56 Kg - Base Camp
87 Beton fc' 10 MPa M47 M3 - Lokasi Pekerjaan
88 Beton Struktur fc' 15 MPa M60 M3 - Lokasi Pekerjaan
89 Beton Struktur fc' 20 MPa M186 M4 - Lokasi Pekerjaan
90 Beton Struktur fc' 25 Mpa M37 M3 - Lokasi Pekerjaan
91 Beton Struktur fc' 30 MPa M59 M3 - Lokasi Pekerjaan
92 Beton Struktur fc' 30 Mpa M59 M3 - Lokasi Pekerjaan
93 Beton Struktur fc' 35 MPa M72 M3 - Lokasi Pekerjaan
94 Beton Struktur fc' 40 MPa M69 M3 - Lokasi Pekerjaan
95 Beton Struktur fc' 45 MPa M185 M3 - Lokasi Pekerjaan
96 Beton Struktur fc' 50 MPa M68 M3 - Lokasi Pekerjaan
97 Cerucuk M61 M -
98 Bahan pengawet: kreosot M63 liter -
99 Mata Kucing M64 buah -
101 Anti strpping agent M66 Kg -
102 Bahan Modifikasi M67 Kg -
105 Multipleks 12 mm M73 Lbr -
106 Elastomer jenis 1 ukuran 350 x 300 x 36 mm (Karet Sintesis) M74a buah - Base Camp
107 Elastomer jenis 2 ukuran 400 x 350 x 39 mm (Karet Sintesis) M74b buah - Base Camp
108 Elastomer jenis 3 ukuran 400 x 450 x 40 mm (Karet Sintesis) M74c buah - Base Camp
109 Elastomer jenis 3 ukuran 400 x 700 x 73 mm (Karet Sintesis) M74c buah - Base Camp
110 Expansion Tipe Joint Asphaltic Plug M75d M - Base Camp
111 Expansion Join Tipe Rubber M75e M - Base Camp
112 Expansion Join Baja Siku M75f M - Base Camp
113 Marmer M76 Buah - Base Camp
114 Kerb Type A M77 Buah - Base Camp
115 Paving Block M78 M2 - Lokasi Pekerjaan
116 Mini Timber Pile M79 Buah - Lokasi Pekerjaan
117 Expansion Joint Tipe Torma M80 M1 - Lokasi Pekerjaan
118 Strip Bearing M81 Buah - Lokasi Pekerjaan
119 Joint Socket Pile 35x35 M82 Set - Lokasi Pekerjaan
HARGA
No. U R A I A N KODE SATUAN SATUAN KETERANGAN
( Rp.)
120 Joint Socket Pile 16x16x16 M83 Set - Lokasi Pekerjaan
121 Mikro Pile 16x16x16 M84 M1 - Lokasi Pekerjaan
122 Matras Concrete M85 Buah - Lokasi Pekerjaan
123 Assetilline M86 Botol - Lokasi Pekerjaan
124 Oxygen M87 Botol - Lokasi Pekerjaan
125 Batu Bara M88 Kg - Lokasi Pekerjaan
126 Pipa Galvanis Dia 3" M24a M -
127 Pipa Galvanis Dia 1,5" M24b M -
128 Pipa Galvanis Dia 4" M132 M -
129 Agregat Pecah Mesin 0-5 mm M91 M3 -
130 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 -
131 Agregat Pecah Mesin 20-30 mm M93 M3 -
132 Joint Sealent M94 Kg -
133 Cat Anti Karat M95 Kg -
134 Expansion Cap M96 Kg -
135 Polytene 125 mikron M97 Kg -
136 Curing Compound M98 Ltr -
137 Additive M67a Kg -
138 Casing M100 Kg -
139 Pasir Tailing M101 M3 - Base Camp
140 Polimer M102 - Base Camp
144 Bahan Modifikasi M107 Kg -
145 Aditif anti pengelupasan M108 Liter -
146 Bahan Pengisi (Filler) Tambahan M109 Kg -
147 Asbuton yang diproses M110 Kg -
148 Elastomer Alam M111 Kg - 4700000/buah
149 Elastomer Sintesis M112 Kg - 1815000/buah
150 Anchorage M113 Buah -
151 - hidup M114 bh -
152 - mati M115 bh -
153 Kabel Prategang M116 Kg -
154 - Selongsong M117 M' -
155 - Baja Prategang M118 Kg -
156 - Grouting M119 M2 -
159 Baja Profil M122 Kg -
161 Epoxy coated M124 Kg -
162 Cairan Perekat (Epoxy Resin) M125 Kg -
163 Epoxy Bahan Penutup (sealant) M126 Kg -
164 Alat Penyuntik Anti Gravitasi M127 Kg - alat penyuntik epoxy
165 Polymer Mortar M128 Kg -
166 Anti Korosif Baja M129 Kg -
167 Acuan/multipleks M130 M3 -
169 Pelat Baja M133 Kg -
170 Pipa Baja Galvanis M133a Kg -
171 Baut Angkur M134 Kg -
173 Cat Galvanis M136 Kg -
174 Baut Mutu Tinggi M137 Buah -
178 Bahan Grouting M141 Kg -
179 Bahan Grouting M141 M3 -
180 Kayu Kelas 1 M142 Kg -
182 Timbunan/urugan Porous M144 M3 -
185 Gelagar baja M147 Kg -
188 Bahan Baja Profil M150 Kg -
189 Bahan Baja Profil, Mutu BJ 32 M151 Kg -
190 Bahan Baja Profil, Mutu BJ 41 M152 Kg -
196 Aspal Emulsi CSS-1 atau SS-1 M31a Liter - Base Camp
197 Aspal Emulsi CRS-1 atau RS-1 M31b Liter - Base Camp
198 Aspal Emulsi Modifikasi Polimer 1h M31c Liter - Base Camp
206 Pasir Kasar M164 M3 -
207 Pipa PVC diameter 2" M25 M' - Lokasi Pekerjaan
208 Pipa Porus diameter 4" M25 M' - Lokasi Pekerjaan
209 Pipa Porus diameter 5" M25a M' -
210 Pipa Porus diameter 6" M25b M' -
211 Pipa Porus diameter 8" M25c M' -
212 Backer rod 3/8 inci M165 Kg -
HARGA
No. U R A I A N KODE SATUAN SATUAN KETERANGAN
( Rp.)
213 Cairan Perekat (Epoxy Resin) 2 komponen M166 Ltr -
217 Air M170 Liter - 18100/kubik
218 Super plastiziser, maks 0,3 % Sm M171 Kg -
229 Plastizier' M182 Kg -
230 Perkerasan beton fast track <8 jam M226 Kg -
231 Rapid Setting Material (Beton Semen Fast Track < 24 jam) M183 M3 -
232 Thermocouple M184 Buah -
233 Baja Struktur Grade 240 (Kuat Leleh 240 MPa) M220 Kg -
234 Baja Struktur Grade 345 (Kuat Leleh 345 MPa) M187 Kg -
235 Baja Struktur Grade 485 (Kuat Leleh 485 MPa) M188 Kg -
236 Baja Struktur Grade 690 (Kuat Leleh 690 Mpa untuk Tebal Pelat ≤ 2,5M i1n8c9h) Kg -
237 Baja Struktur Grade 690 (Kuat Leleh 620 Mpa untuk Tebal Pelat > 2,5M -1 49,00 inch) Kg -
238 Casing, diameter 800 mm M191 Rp/M' -
242 Perancah/ formwoks M195 -
243 Bahan Turap Kayu dengan pengawetan M196 M3/M' -
244 Kreosot M197 Kg -
245 Bonding Agent M198 Ltr -
246 Cat dasar beton M199 Kg -
247 Cat akhir protektif beton M200 Kg -
248 Cat akhir dekoratif beton M201 Kg -
249 Cat dasar baja M202 Kg -
250 Cat akhir protektif baja M203 M2 -
251 Cat baja anti koresif 240 mikron Kg. -
257 Baja untuk pelat buhul dan pelat ganjal M209 Buah -
258 Baut mutu tinggi A325 Tipe 1 diameter M25 M210 Buah -
259 Baut Mutu Tinggi A490 Tipe 1 diameter M25 M211 Buah -
260 Baut Biasa Grade A diameter M25 M212 Buah -
261 Baut Biasa Grade B diameter M25 M213 Buah -
262 Baut Biasa Grade C untuk anchor bolts diameter M25 M214 Buah -
263 Elektroda Las SMAW M215 Kg -
264 Elektroda Las SAW M216 Kg -
272 Baut dan Mur M223 Buah -
273 Cat dasar kayu M224 Kg -
274 Cat akhir protektif kayu M225 Kg -
276 Karet Pengisi Sambungan Strip Seal M228 M' -
277 Karet Pengisi Sambungan Compression Seal M229 M' -
278 Sambungan siar muai tipe modular M230 M' -
279 Sambungan siar muai tipe finger plate M231 M' -
282 Landasan logam berongga (Pot Bearing) M234 Buah -
283 Landasan logam jenis Spherical M235 Buah -
285 Lem PVC M237 Kg -
286 Tiang sandaran baja M238 M' -
287 Deck Drain M239 Buah -
288 Pipa PVC M240 M' -
289 Pipa Baja drainase 100 mm M241 Batang -
290 Pipa Baja Dia. 150 mm M241 M' -
291 Sambungan Pipa PVC M242 Buah -
292 Sambungan Pipa Baja M243 Buah -
293 Baja Tulangan (Furnished) M57b Kg -
294 Turap Beton M244 Kg -
295 Tiang Pancang Kayu M245 M3 -
296 Plat sepatu tiang pancang / plat sambung M246 Kg -
297 Beton strukut bervolume besar, fc’20 MPa M249 M3 -
298 Beton strukut memadat sendiri, fc’20 MPa M252 M3 -
299 Beton struktur bervolume besar, fc’25 Mpa M248 M3 -
300 Beton struktur memadat sendiri, fc’25 Mpa M251 M3 -
301 Beton strukutr bervolome besar, fc'30 MPa M247 M3 -
302 Beton strukutr memadat sendiri, fc'30 MPa M250 M3 -
303 Beton Fc' 35 MPa M253 M3 -
304 BjTS 280 M254 Kg -
305 Asphaltic plug M255 Kg -
306 Asphaltic plug Moveable M256 Kg -
309 Anyaman Kawat Baja Dilas M258 Kg -
311 Sambungan siar muai tipe Karet (Preformed T-shape) M260 Kg -
312 Bridging Plate PL 125 x 6 M261 Kg -
HARGA
No. U R A I A N KODE SATUAN SATUAN KETERANGAN
( Rp.)
313 Perletakan logam tipe fixed 150 Ton M262 Buah -
314 Perletakan logam tipe movable 150 Ton M263 Buah -
315 Elastomer bearing pad; (450x400x45) mm3 M264 Buah -
316 Beton c 10 MPa M265 M3 -
317 Marmer M266 M2 -
318 Baja Tulangan Angkur M267 Kg -
320 Grauting berbahan dasar semen M269 Kg -
321 Graut berbahan dasar Cellular Plastic M270 Kg -
322 Pipa Galvanis Dia. 6" (L 11 m) M1 -
323 Pipa Galvanis Dia. 4" (T = 4,0 mm) M1 -
324 Plat Baja 12mm M2 -
325 Kerawang GRC M2 -
326 Base Plat (T = 22 mm) M2 -
327 Bahan penutup retak beton dengan sealent m3 -
328 Lampu Jalan LED (Cover Lengkap) 40 Watt 32 Volt berikut kabel Unit - Base Camp
329 Controller 12/24 - 20A + MCB 16 A Unit - Base Camp
330 Bracket + Mur / Baut Unit - Base Camp
331 Pohon Buah -
332 Wiremesh Lembar - dia 6-150/150
333 Sheet Pile Type W-400-B t = 12 cm p = 6 s/d 15 m M1 - tebal = 12 cm
334 Sheet Pile Type FPC-220 F-500 m1 -
335 Anyaman Kawat Baja Dilas Kg -
336 Spun Pile Dia.. 50 cm t = 9 cm M1 -
337 Spun Pile Dia.. 40 Cm t = 9 cm M1 -
338 Steel Shape M1 -
339 Matras Perkuatan Tipe III M2 -
340 Biji Vegetasi Teknik Mulsa (mulching) M2 -
341 Multipleks 9 mm M132 Lbr -
-
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA
No. URAIAN KO HP KAP. HARGA SEWA KET.
DE ALAT ALAT/JAM
(di luar PPN)
1 ASPHALT MIXING PLANT E01 294,0 60,0 T/Jam 5.500.000.000
2 ASPHALT FINISHER E02 49,4 200,0 Ton 2.090.000.000
3 POWER BROOM E03 12,0 4.000,0 M2/Jam 34.452.000
4 BULLDOZER 100-150 HP E04 155,0 - - 2.500.000.000
5 COMPRESSOR 4000-6500 L\M E05 75,0 5.000,0 CPM/(L/m) 400.500.000
6 CONCRETE MIXER 0.3-0.6 M3 E06 20,0 500,0 Liter 35.000.000
7 CRANE 10-15 TON E07 260,0 15,0 Ton 1.519.500.000
8 DUMP TRUCK 3 - 4 M3 E08 100,0 4,0 M3 423.000.000
9 DUMP TRUCK 6 - 8 M3 E09 190,0 8,0 M3 996.712.500
10 EXCAVATOR 80-140 HP E10 123,0 0,9 M3 1.300.000.000
11 FLAT BED TRUCK 3-4 TON E11 100,0 4,0 ton 466.666.667
12 GENERATOR SET E12 180,0 135,0 KVA 207.000.000
13 MOTOR GRADER >100 HP E13 145,0 3,7 - 2.250.000.000
14 TRACK LOADER 75-100 HP E14 70,0 0,8 M3 1.210.000.000
15 WHEEL LOADER 1.0-1.6 M3 E15 96,0 1,5 M3 1.700.000.000
16 THREE WHEEL ROLLER 6-8 T E16 55,0 8,0 Ton 840.000.000
17 TANDEM ROLLER 6-8 T. E17 74,3 6,9 Ton 1.560.000.000
18 TIRE ROLLER 8-10 T. E18 135,0 10,9 Ton 1.710.000.000
19 VIBRATORY ROLLER 5-8 T. E19 131,4 11,0 Ton 1.000.000.000
20 CONCRETE VIBRATOR E20 5,5 0,0 - 8.855.000
21 STONE CRUSHER E21 220,0 60,0 T/Jam 3.500.000.000
22 WATER PUMP 70-100 mm E22 5,5 - - 10.000.000
23 WATER TANKER 3000-4500 L. E23 135,0 4.000,0 Liter 660.000.000
24 PEDESTRIAN ROLLER E24 8,3 0,75 Ton 667.380.560
25 TAMPER E25 4,7 121,00 Kg 102.900.000
26 JACK HAMMER E26 1,0 12,00 M2/JAM 126.000.000
27 FULVI MIXER E27 35,0 55,50 M3/Menit 900.000.000
28 CONCRETE PUMP E28 150,0 100,00 M3/jam 880.000.000
29 TRAILER 20 TON E29 320,0 20,00 Ton 1.428.000.000
30 PILE DRIVER + HAMMER E30 25,0 2,50 Ton 400.000.000
31 CRANE ON TRACK 35 TON E31 220,0 35,0 Ton 5.970.000.000
32 WELDING SET E32 5,0 300,0 Amp 42.663.600
33 BORE PILE MACHINE 160/2200 kw/rpm; Torque 160E k3N3.m 150,0 200,0 cm 3.375.000.000
34 ASPHALT LIQUID MIXER E34 5,0 1.000,0 Liter 165.000.000
35 TRONTON 15 TON E35 150,0 15,0 Ton 814.437.173
36 COLD MILLING E36 240,0 1.000,0 m 5.300.000.000
37 BREAKER E37 2,7 0,7 M3 111.732.000
38 COLD RECYCLER E38 600,0 2,2 M 8.000.000.000
39 HOT RECYCLER E39 295,0 3,0 M 16.000.000.000
40 AGGREGAT (CHIP) SPREADER E40 115,0 4,5 M 395.000.000
41 ASPHALT DISTRIBUTOR E41 115,0 100,0 Liter 434.500.000
42 SLIP FORM PAVER E42 174,0 7,0 M 13.769.105.700
43 CONCRETE PAN MIXER E43 15,0 25,0 m3/jam 1.455.035.800
44 CONCRETE BREAKER E44 290,0 20,0 m3/jam 4.370.311.457
45 ASPAHLT TANKER E45 190,0 4.000,0 liter 657.316.152
46 CEMENT TANKER E46 190,0 4.000,0 liter 657.296.685
47 CONCRETE MIXER (350) E47 20,0 350,0 liter 45.934.000
48 VIBRATING RAMMER E48 6,4 9,5 KG 81.300.000
49 TRUK MIXER (AGITATOR) E49 280,0 5,0 M3 1.425.000.000
50 BORE PILE MACHINE E50 125,0 60,0 CM 1.462.500.000
51 CRANE ON TRACK 75-100 TON E51 190,0 75,0 Ton 10.540.500.000
52 BLENDING EQUIPMENT E52 50,0 30,0 Ton 500.000.000
53 ASPHALT LIQUID MIXER E34a 40,0 20.000,0 Liter 165.000.000
54 BAR BENDER E53 3,0 0,0 0 82.500.000
55 BAR CUTTER E54 3,0 0,0 0 82.500.000
56 ROCK DRILL BREAKER E55 148,0 1,8 m3/jam 1.950.000.000
57 GROUTING PUMP E56 100,0 0,0 Ton 24.000.000
58 JACK HIDROLIC E57 10,0 - - 12.000.000
59 MESIN LAS E58 3,0 0,2 Ton 42.663.600
60 PILE DRIVER LEADER, 75 kw E59 70,0 75,0 kw 784.514.971
61 PILE HAMMER PW 300 E60 10,0 0,0 0 511.500.000
62 PILE HAMMER, 2,5 Ton E61 1,0 2,5 Ton 1.454.314.616
63 STRESSING JACK E62 89,0 15,0 Ton 587.412.267
64 WELDING MACHINE, 300 A E63 5,0 0,0 0 127.662.944
65 ASPHALT MIXING PLANT (WARM MIX) E01a 294,0 60,0 T/Jam 5.500.000.000
66 ASPHALT MIXING PLANT (MODIFIKASI, ASBUTONE)01b 294,0 60,0 T/Jam 5.500.000.000
67 TANDEM ROLLER 8-10 T. E17a 100,0 10,0 Ton 1.560.000.000
68 Trailer Tronton 30 T; 200 HP E35a 200,0 30,0 Ton 1.035.000.000
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA
No. URAIAN KO HP KAP. HARGA SEWA KET.
DE ALAT ALAT/JAM
(di luar PPN)
69 MINI EXCAVATOR 40-60 HP E10a 5 4,50 0,2 M3 558.250.000
70 BABY VIBRATORY ROLLER 1-2 T. E19a 7 ,60 1,5 Ton 120.000.000
71 WATER JET BLASTING E64 6 ,50 100,0 Liter 16.000.000
72 MESIN POTONG RUMPUT E65 2 8,80 150,0 M2
73 Ponton + Tug Boat; 40 Ton; 80 HP E66
74 Silicon Seal pump E67
75 Pompa (+Mixer) pengisi bahan perekat epoxy, 600 WEat6t8
76 Gerinda tangan GWS 750-100 4"; 1 HP E69
77 Hand Mixer E70
78 Mesin Bor E71
79 Mesin Amplas kayu E73
80 KUNCI TORSI 200-1000N.M E74 - 1,0 buah baut 20.000.000
81 POMPA + MIXER EPOXY, 810 Watt E75 1 ,08 0,8 l/mnt 7.000.000
82 CONCRETE CUTTER E76 2 2,00 39,6 m/menit 146.055.000
83 SAND BLASTING E77 7 5,00 10,0 m2/jam 7.909.000
84 MOBILE CRANE 1 TON E78 1 90,00 1,0 Ton 900.000.000
85 DRUM MIXER E79 2 0,00 4,0 Ton/jam 600.000.000
86 CONCRETE MIXING PLANT E80 6 0,00 90,0 m3/Jam 2.175.000.000
87 STAMPER E81 2 2,00 60,0 m2/jam 30.000.000
88 JACK HIDROLIK JEMBATAN E82 2 2,00 50,0 Ton 75.000.000
89 HYDROLIC PUMP E83 2 2,00 30,0 Mpa 16.000.000
90 MANIFOLD E84 - 1,0 0,00 5.000.000
91 THERMOPLASTIC SPREADING MACHINE E85 5 ,50 1.300,0 m/jam 120.000.000
92 COLD PAINT SRAY MACHINE E86 5 ,50 1.300,0 m/jam 70.000.000
93 TRAILER 30- 100 T 2 76,00 100,0 Ton 1.347.000.000
94 CONCRETE MIXING PLANT E80 6 0,00 90,0 m3/Jam 2.175.000.000
95 SHOT MACHINE (Shotcrete Machine 13.26 HP) E87 1 3,26 8,0 M3/jam 289.800.000
96 DRILLING MACHINE E88 2 2,00 80,0 M' 277.178.625
97 EXCAVATOR PC300 (capit) E89 2 46,00 1,6 M3 1.550.000.000
98 SKYLIFT-CRANE TRUCK 1 Ton E90 1 90,00 16,0 M' 723.076.875
99 TRAILLER TRONTON 40 TON E91 2 30,00 40,0 Ton 1.265.000.000
100 ALAT BAHAN GROUTING (CONTRIFUGAL) E92 2 ,00 50,0 Liter 55.000.000
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI
% TERHADAP TOTAL BIAYA PROYEK = 0,0000 %
Lembar 1.2-1
HARGA JUMLAH
No. U R A I A N SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)
A. Sewa Tanah M2 - - -
B. PERALATAN
Periksa lembar 1.2-2 -
C. Kantor Lapangan dan Fasilitas - - -
1 Base Camp M2 - 100.000 -
2 Kantor M2 - 150.000 -
3 Barak M2 - 75.000 -
4 Bengkel M2 -
5 Gudang, dan lain-lain M2 - 50.000 -
6 . . . . . . . . . . . . . . . . . . . . . . . . . .
D. MOBILISASI FASILITAS LABORATORIUM set - - -
1 Ruang Laboratorium (sesuai Gambar)
2 Soil & Aggregate Testing
Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Methode
Moisture Content
Abrasion of Aggregate by Los Angeles Machine
3 Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Method
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Viod Content (Accurate Method)
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor
4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine
5 Pendukung (Periksa Fasilitas Laboratorium)
6 Operasional (Periksa Fasilitas Laboratorium)
E. Metoda Kontruksi LS 1 - -
F. MOBILISASI PERSONIL
F.I. Personil Sesuai Struktur Organisasi LS - - -
1 GS
2 Tenaga Ahli Jalan - 1.000.000 -
3 Tenaga Ahli Jembatan . . . .
4 . . . . . . . . . . . . . . . . . . . . . . . . . .
F.II. Lain-Lainnya Set - - -
1 Koordinator Manajemen dan Keselamatan Lalu Lintas . . . .
2 Manajer Kendal Mutu . . . . - 1.000.000 -
3 Sewa Kendaraan Roda 4 UB - 10.000.000 -
4 . . . . . . . . . . . . . . . . . . . . . . . . . .
G. Manajemen dan Keselamatan lalu lintas LS -
H. DEMOBILISASI LS 1 - -
Total Biaya Mobilisasi -
Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : M O B ILISASI
Lembar 1.2-2
KODE HARGA JUMLAH
No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)
B. PERALATAN
1 ASPHALT MIXING PLANT E01 Unit - 200.000.000 -
2 ASPHALT FINISHER E02 Unit 1,00 - -
3 POWER BROOM E03 Unit - - -
5 COMPRESSOR 4000-6500 L\M E05 Unit 1,00 - -
6 CONCRETE MIXER 0.3-0.6 M3 E06 Unit - - -
7 CRANE 10-15 TON E07 Unit - - -
8 DUMP TRUCK 4 TON (2 - 3 M3) E08 Unit - - -
9 DUMP TRUCK 10 TON (6-8 M3) E09 Unit - - -
10 EXCAVATOR 80-140 HP E10 Unit - - -
11 FLAT BED TRUCK 3-4 TON E11 Unit - - -
12 GENERATOR SET E12 Unit - - -
13 MOTOR GRADER >100 HP E13 Unit 1,00 - -
15 WHEEL LOADER 1.0-1.6 M3 E15 Unit - - -
17 TANDEM ROLLER 6-8 T. E17 Unit 1,00 - -
18 TIRE ROLLER 8-10 T. E18 Unit 1,00 - -
19 VIBRATORY ROLLER 5-8 T. E19 Unit 1,00 - -
20 CONCRETE VIBRATOR E20 Unit - - -
22 WATER PUMP 70-100 mm E22 Unit - - -
23 WATER TANKER 3000-4500 L. E23 Unit 1,00 - -
25 TAMPER E25 Unit - - -
26 JACK HAMMER E26 Unit - - -
28 CONCRETE PUMP E28 Unit - - -
32 WELDING SET E32 Unit - - -
49 TRUK MIXER (AGITATOR) E49 Unit - - -
52 SURVEY EQUIPMENT E52 Unit - - -
64 MINI EXCAVATOR 40-60 HP E10a Unit - 0 0
Total untuk Item B pada Lembar 1 0
II RENCANA KESELAMATAN DAN KESEHATAN KERJA KONTRAK (RK3K)
1 Sosialisasi, Promosi dan Pelatihan
a Papan Informasi K3 0,00 Buah Taksir Rp - Rp -
3 Alat Pelindung Kerja dan Alat Pelindung Diri
a Topi Pelindung (Safety Helmet) 0,00 Buah Taksir Rp - Rp -
b Rompi Keselamatan (Safety Vest) 5,00 Buah Taksir Rp - Rp -
c Sepatu Keselamatan (Safety Shoes) 5,00 Psg Taksir Rp - Rp -
d Sarung Tangan (Safety Gloves) 5,00 Psg Taksir Rp - Rp -
e Pelindung Mata (Goggles, Spectacles) 0,00 Psg Taksir Rp - Rp -
f Pelindung Pernapasan dan Mulut (Masker) 0,00 Buah Taksir Rp - Rp -
4 Asuransi dan Perizinan
a BPJS Ketenagakerjaan 0,00 Ls Taksir Rp - Rp -
5 Fasilitas Sarana Kesehatan
a Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) 1,00 Ls Taksir Rp - Rp -
SUB TOTAL Rp -
Analisa EI-318
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
: 2025
PROP / KAB / KODYA : Aceh Besar
ITEM PEMBAYARAN NO. : 3.1.(8) PERKIRAAN VOL. PEK. : 0,00
JENIS PEKERJAAN : Galian Perkerasan Beraspal tanpa Cold Milling Machine TOTAL HARGA (Rp.) : 0,00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0,00
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 1,6024 0,00 0,00
2. Mandor (L03) Jam 0,2671 0,00 0,00
JUMLAH HARGA TENAGA 0,00
B. BAHAN
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
1. Concrete Cutter E76 Jam 0,1785 - 0,00
2. Jack Hammer E26 Jam 0,2671 - 0,00
3. Compresor E05 Jam 0,2671 - 0,00
4. Dump Truck E09 Jam 0,3122 - 0,00
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 0,00
E. OVERHEAD & PROFIT 10,0 % x D 0,00
F. HARGA SATUAN PEKERJAAN ( D + E ) 0,00
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-511
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
: 2025
PROP / KAB / KODYA : Aceh Besar
ITEM PEMBAYARAN NO. : 5.1.(1) PERKIRAAN VOL. PEK. : 45,00
JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas A TOTAL HARGA : 28.118.863,39
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 24,83
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) jam 0,0779 0,00 0,00
2. Mandor (L03) jam 0,0097 0,00 0,00
JUMLAH HARGA TENAGA 0,00
B. BAHAN
1. Agregat A M26 M3 1,2890 0,00 0,00
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
1. Wheel Loader (E15) jam 0,0087 0,00 0,00
2. Dump Truck (E09) jam 0,1963 0,00 0,00
3. Motor Grader (E13) jam 0,0010 0,00 0,00
4. Vibratory Roller (E19a) jam 0,0097 0,00 0,00
5 Alat Bantu Ls 1,0000 0,00 0,00
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 0,00
E. OVERHEAD & PROFIT 10,0 % x D 0,00
F. HARGA SATUAN PEKERJAAN ( D + E ) 0,00
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-611
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
: 2025
PROP / KAB / KODYA : Aceh Besar
ITEM PEMBAYARAN NO. : 6.1 (1) PERKIRAAN VOL. PEK. : 240,00
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair/Emulsi TOTAL HARGA (Rp.) : 7.898.657,20
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK : 6,98
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 0,0071 0,00 0,00
2. Mandor (L03) Jam 0,0018 0,00 0,00
JUMLAH HARGA TENAGA 0,00
B. BAHAN
1. Aspal Emulsi CSS-1 (M31a) Liter 1,7895 0,00 0,00
atau SS-1
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
1. Asp. Distributor E41 Jam 0,00177 - 0,00
2. Compressor E05 Jam 0,00177 - 0,00
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 0,00
E. OVERHEAD & PROFIT 10,0 % x D 0,00
F. HARGA SATUAN PEKERJAAN ( D + E ) 0,00
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-635a
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Rehab Jalan Gampong jeumpet Ajuen-Garot, Kec. Darul Imarah
: 2025
PROP / KAB / KODYA : Aceh Besar
ITEM PEMBAYARAN NO. : 6.3.(5a) PERKIRAAN VOL. PEK. : 28,20
JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) TOTAL HARGA (Rp.) : 53.532.573,53
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 47,28
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 0,2410 0,00 -
2. Mandor (L03) Jam 0,0402 0,00 -
JUMLAH HARGA TENAGA -
B. BAHAN
1. Agr Pch Mesin 5-10 & 10-15 (M92) M3 0,3460 0,00 -
2. Agr Pch Mesin 0 - 5 (M91) M3 0,4404 0,00 -
3 Semen (M12) Kg 9,6820 0,00 -
4 Aspal (M10) Kg 63,3450 0,00 -
JUMLAH HARGA BAHAN -
C. PERALATAN
1. Wheel Loader E15 Jam 0,0727 - -
2. AMP E01 Jam 0,0201 - -
3. Genset E12 Jam 0,0201 - -
4. Dump Truck E09 Jam 0,1657 - -
5. Asp. Finisher E02 Jam 0,0156 - -
6. Tandem Roller E17a Jam 0,0169 - -
7 P. Tyre Roller E18 Jam 0,0122 - -
8 Alat Bantu Ls 1,0000 0,00 -
JUMLAH HARGA PERALATAN -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10,0 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.