Kec. Maesa – Kota Bitung
Tahun Anggaran 2024
PEMERINTAH KOTA BITUNG
D I N A S P E R D A G A N G A N
Jln. Wolter Monginsidi No. 85 Kel. Wangurer Barat Kec. Madidir Kota Bitung 95541
Telp. 0438-2235536, Email: [email protected]
ENGGINEERING ESTIMATE
Pekerjaan : PEMBANGUANAN SARANA PRODUKSI
(Ruang Area Produksi IKM)
Lokasi : KEC. MAESA, KOTA BITUNG
Tahun : DAK 2024
HARGA SATUAN Pajak Pajak JUMLAH HARGA
NO URAIAN PEKERJAAN VOL. SAT.
( Rp. ) (%) (Rupiah) ( Rp. )
I PEKERJAAN PERSIAPAN
1 Gudang bahan / Direksi Keet 1.00 Ls 8,440,000.00 1 1.00 928,400.00 9,368,400.00
2 Pengukuran, pasang bouwplank 271.00 m1 57,902.50 1 1.00 1,726,073.53 17,417,651.03
3 Pembersihan Lahan dan Perataan 1,468.00 m2 25,875.00 1 1.00 4,178,295.00 42,162,795.00
4 Papan Nama Proyek 1.00 Bh 476,100.00 1 1.00 52,371.00 528,471.00
II SMK3 (Sistem Manajemen Keselamatan Konstruksi)
1 Penyiapan RKK 1.00 Set 1,750,000.00 1 1.00 192,500.00 1,942,500.00
2 Spanduk (Banner) 1.00 Lb 75,000.00 1 1.00 8,250.00 83,250.00
3 Papan Informasi K3 1.00 Bh 75,000.00 1 1.00 8,250.00 83,250.00
4 Topi pelindung (Safety Helmet) 4.00 Bh 32,500.00 1 1.00 14,300.00 144,300.00
5 Pelindung pernafasan dan mulut (Masker) 2.00 Box 50,000.00 1 1.00 11,000.00 111,000.00
6 Rompi keselamatan (Safety Vest) 4 .00 Bh 25,000.00 1 1.00 11,000.00 111,000.00
7 Petugas K3 Konstruksi 3.00 Ls 2,500,000.00 1 1.00 825,000.00 8,325,000.00
8 Peralatan P3K (kotak P3K, obat luka, perban) 1.00 Set 750,000.00 1 1.00 82,500.00 832,500.00
9 Bendera K3 1.00 Bh 75,000.00 1 1.00 8,250.00 83,250.00
III PEKERJAAN TANAH
1 Galian Tanah sedalam 1 m 127.51 m3 123,050.00 1 1.00 1,725,938.68 17,416,290.28
2 Urugan kembali bekas galian 38.25 m3 83,375.00 1 1.00 350,833.33 3,540,227.23
3 Timbunan Tanah 59.40 m3 156,400.00 1 1.00 1,021,917.60 10,312,077.60
IV PEKERJAAN PONDASI
1 Pasangan Batu Kosong 30.13 m3 597,270.90 1 1.00 1,979,666.34 19,976,633.10
2 Pasangan Pondasi Batu Belah 1:5 59.23 m3 1,185,903.00 1 1.00 7,726,187.69 77,964,257.63
3 Pek. Pas. Batu Dinding Penahan Tanah 44.10 m3 1,185,903.00 1 1.00 5,752,815.45 58,051,137.75
V PEKERJAAN STRUKTUR
1 Lantai kerja beton mutu f'c = 7,4 Mpa (K100) 1.01 m3 1,122,701.46 1 1.00 124,670.38 1,258,037.51
2 Pek Beton Sloof S (15/20 cm) -
- Beton K-150 12.11 m3 1,204,941.80 1 1.00 1,605,633.14 16,202,298.08
- Pembesian 1,881.56 kg 21,815.50 1 1.00 4,515,193.61 45,562,408.23
- Bekisting 80.74 m2 126,298.75 1 1.00 1,121,707.08 11,319,044.16
3 Pek Beton Kolom K1 (12/12 cm) -
- Beton K-150 4.84 m3 1,204,941.80 1 1.00 641,298.94 6,471,289.34
- Pembesian 1,565.51 kg 21,815.50 1 1.00 3,756,765.76 37,909,181.77
- Bekisting 80.64 m2 206,396.25 1 1.00 1,830,817.30 18,474,610.90
4 Pek Kolom Praktis 192.00 m1 123,567.50 1 1.00 2,609,745.60 26,334,705.60
5 Pek Balok Latei 174.28 m1 157,458.00 1 1.00 3,018,595.83 30,460,376.07
6 Pek Balok Beton B (12/12 cm) -
- Beton K-150 5.81 m3 1,204,941.80 1 1.00 770,703.91 7,777,103.08
- Pembesian 1,319.24 kg 21,815.50 1 1.00 3,165,785.56 31,945,654.27
- Bekisting 62.74 m2 230,546.25 1 1.00 1,590,990.45 16,054,539.99
7 Pekerjaan Plat Meja Beton 0.99 m3 4,712,404.73 1 1.00 511,625.78 5,162,769.25
VI PEKERJAAN DINDING dan PLESTERAN
1 Pasang bata merah, 1 Pc : 5 Ps 843.33 m2 185,367.58 1 1.00 17,195,884.93 173,522,111.54
2 Plesteran 1 Pc : 5 Ps, tebal 15 mm 1,686.66 m2 94,685.94 1 1.00 17,567,349.46 177,270,526.39
3 Acian 1,686.66 m2 32,119.50 1 1.00 5,959,221.41 60,133,961.52
VII PEKERJAAN PENUTUP DINDING dan LANTAI
1 Pek. Lantai Kerja 32.26 m3 1,122,701.46 1 1.00 3,983,565.92 40,197,801.58
2 Pek. Pas. Keramik Granit China 60x60 cm 134.94 m2 330,588.49 1 1.00 4,906,948.06 49,515,566.80
3 Pek. Pas. Keramik Granit China 60x60 cm (Unpolish) 17.28 m2 330,588.49 1 1.00 628,426.23 6,341,392.00
4 Pek. Pasang Keramik Lantai KM (25x25 cm) Anti Slip 10.07 m2 227,038.41 1 1.00 251,365.57 2,536,507.12
5 Pek. Pasang Keramik Dinding KM (25x40 cm) 117.70 m2 253,939.55 1 1.00 3,287,755.35 33,176,440.39
6 Pek. Pas. Keramik lantai (40x40 cm) ex. Asia Tile 132.41 m2 210,919.58 1 1.00 3,072,097.30 31,000,254.62
7 Pek, Pas. Dinding Roster 20x20 cm 0.48 m2 921,253.50 1 1.00 48,642.18 490,843.86
8 Pek. Pasang Lantai epoxy (Resin) 1500 milimikron 169.81 m2 941,275.00 1 1.00 17,582,252.68 177,420,913.45
9 Pek. Timbunan Pasir dibawah Paving 11.76 m3 166,865.00 1 1.00 215,856.56 2,178,188.96
10 Pek. Pasang Paving 168.00 m2 329,671.08 1 1.00 6,092,321.47 61,477,062.07
VIII PEKERJAAN KUSEN, PINTU,JENDELA, VENTILASI, KACA
Harga satuan pekerjaan sudah termasuk pengadaan dan pemasangan Kusen, Pintu, Jendela dan Kaca dan Assesories
yang diperlukan dan Finishing Cat hingga pekerjaan dinyatakan dapat tercapai dengan baik. Pekerjaan harus dilaksanakan
sesuai gambar dan spesifikasi teknik
Rumah Produksi 1 - 6
1 Pintu Tipe P1 (Pintu Kebaya Besi Hollow Lapis Plat Besi) 6.00 Unit 4,592,574.34 1 1.00 3,031,099.07 30,586,545.12
2 Pintu Tipe P2 (Pintu Solid Engineering Rangka Aluminium)) 6 .00 Unit 3,845,128.21 1 1.00 2,537,784.62 25,608,553.90
3 Pintu Tipe P3 (Pintu Solid Engineering Rangka Aluminium) 1 8.00 Unit 3,805,745.82 1 1.00 7,535,376.71 76,038,801.40
5 Pintu Tipe P4 (Pintu Allumunium Spanrell) 6.00 Unit 1,694,550.00 1 1.00 1,118,403.00 11,285,703.00
7 Partisi + Pintu sekat Curtain ( PVC ) (Rg. Personil Higienis) 6 .00 Unit 2,875,000.00 1 1.00 1,897,500.00 19,147,500.00
8 Pas. Sekat/Partisi Curtain ( PVC ) + Rangka Besi Hollow (Rg. Proses Utama) 3 0.00 Unit 1,437,500.00 1 1.00 4,743,750.00 47,868,750.00
9 Jendela Tipe J1 6.00 Unit 2,746,333.83 1 1.00 1,812,580.33 18,290,583.32
10 Ventilasi Tipe V1 36.00 Unit 643,082.16 1 1.00 2,546,605.34 25,697,562.96
11 Ventilasi Tipe V2 18.00 Unit 419,093.06 1 1.00 829,804.26 8,373,479.39
Rumah Produksi 7
1 Pintu PVJ1 (Pintu Kebaya Aluminium Kaca Bening Rangka Aluminium) 1 .00 Unit 12,035,050.58 1 1.00 1,323,855.56 13,358,906.15
2 Pintu PVJ2 (Pintu Geser Aluminium Kaca Bening Rangka Aluminium) 1 .00 Unit 8,138,331.14 1 1.00 895,216.43 9,033,547.57
3 Pintu PVJ3 (Pintu Aluminium Kaca Bening Rangka Aluminium) 1 .00 Unit 5,061,700.94 1 1.00 556,787.10 5,618,488.05
4 Pintu Tipe P5 (Pintu Besi Hollow Lapis Plat Besi) 1.00 Unit 2,746,333.83 1 1.00 302,096.72 3,048,430.55
5 Pintu Tipe P6 (Pintu Spanrell) (Toilet) 1.00 Unit 1,694,550.00 1 1.00 186,400.50 1,880,950.50
6 Pintu Tipe P7 (Pintu Double Tripleks Lapis) (Rg. Janitor) 1.00 Unit 736,411.40 1 1.00 81,005.25 817,416.66
7 Jendela JV1 (Jendela Aluminium Kaca Polos 5 mm Mati) 1.00 Unit 3,670,951.20 1 1.00 403,804.63 4,074,755.83
8 Ventilasi V1 (Ventilasi aluminium kaca susun silang riben) 1.00 Unit 419,093.06 1 1.00 46,100.24 465,193.30
HARGA SATUAN Pajak Pajak JUMLAH HARGA
NO URAIAN PEKERJAAN VOL. SAT.
( Rp. ) (%) (Rupiah) ( Rp. )
IX PEK. ATAP dan PLAFON
1 Pek. Pas. Atap Spandek, t=0.3 mm 369.47 m2 93,131.66 1 1.00 3,785,041.37 38,194,508.34
2 Pek. Pas. Nok/Bubungan Atap 68.62 m1 89,826.50 1 1.00 678,028.39 6,841,922.82
3 Pek. Pas. Rangka Atap 369.47 m1 225,350.55 1 1.00 9,158,659.19 92,419,197.32
3 Pek. Pas. Rangka Plafon 256.72 m2 139,271.90 1 1.00 3,932,985.25 39,687,396.66
4 Pek. Plafond PVC 169.07 m2 300,006.25 1 1.00 5,579,281.03 56,300,017.69
5 Pek. Plafond Gypsum 207.69 m2 64,201.63 1 1.00 1,466,735.43 14,800,693.88
6 Pek. Plafond Tripleks 6 mm 288.25 m2 69,057.50 1 1.00 2,189,619.41 22,095,250.43
7 Pek. List plafon 674.03 m' 32,257.50 1 1.00 2,391,677.50 24,134,200.22
X PEK. DINDING dan CAT
1 Pek. Cat Dinding 1,519.80 m2 32,770.98 1 1.00 5,478,593.27 55,283,986.62
2 Pek. Cat Plafond 256.72 m2 32,770.98 1 1.00 925,439.82 9,338,529.05
2 Pek. Lapis Dinding epoxy, 1.5 m dari lantai 166.86 m2 69,268.33 1 1.00 1,271,392.55 12,829,506.65
3 Pek. Curving sudut dinding dgn Lantai 144.48 m1 65,000.00 1 1.00 1,033,032.00 10,424,232.00
XI PEK. ELEKTRIKAL
1 Instalasi listrik penerangan 107.00 Ttk 167,969.00 1 1.00 1,976,995.13 19,949,678.13
2 Instalasi listrik daya 63.00 Ttk 217,988.25 1 1.00 1,510,658.57 15,243,918.32
3 Pasang MCB 10-16 A serta Box nya 43.00 Bh 428,779.00 1 1.00 2,028,124.67 20,465,621.67
4 Pasang Listrik Baru PLN Kwh Meter 2200 Watt 7.00 Titik 4,200,000.00 1 1.00 3,234,000.00 32,634,000.00
5 Pasang Lampu LED DownLight 12 Watt 72.00 Bh 252,603.25 1 1.00 2,000,617.74 20,188,051.74
6 Pasang Lampu LED DownLight 8 Watt 59.00 Bh 168,078.25 1 1.00 1,090,827.84 11,007,444.59
7 Pengadaan dan pasang Exhaust Fan 12.00 Bh 850,000.00 1 1.00 1,122,000.00 11,322,000.00
8 Pengadaan dan Pasang Insect Killer 6.00 Bh 1,455,000.00 1 1.00 960,300.00 9,690,300.00
9 Stop kontak ex. PANASONIC 52.00 Bh 66,556.25 1 1.00 380,701.75 3,841,626.75
10 Stop kontak AC ex. PANASONIC 12.00 Bh 303,312.50 1 1.00 400,372.50 4,040,122.50
11 Saklar Tunggal 30.00 Bh 57,741.50 1 1.00 190,546.95 1,922,791.95
12 Saklar Double ex. PANASONIC 21.00 Bh 63,537.50 1 1.00 146,771.63 1,481,059.13
XII PEK. PLUMBING DAN SANITAIR
1 Instalasi kloset pipa pvc 4"AW 56.00 m1 220,294.00 1 1.00 1,357,011.04 13,693,475.04
2 Insatalasi Air Kotor Pipa PVC 3" AW 152.00 m1 140,185.00 1 1.00 2,343,893.20 23,652,013.20
3 Insatalasi Air Kotor Pipa PVC 2" AW 104.00 m1 78,240.25 1 1.00 895,068.46 9,032,054.46
4 Instalasi Air Bersih pipa 1/2" AW 260.00 m1 33,994.00 1 1.00 972,228.40 9,810,668.40
5 Pas. Kloset Jongkok 8.00 Bh 827,586.00 1 1.00 728,275.68 7,348,963.68
6 Pas. Floor Drain 8.00 Bh 103,500.00 1 1.00 91,080.00 919,080.00
7 Kran Dinding 8.00 Bh 220,340.00 1 1.00 193,899.20 1,956,619.20
8 Kitchensink Stainless 2 Bak 6.00 Bh 2,082,075.00 1 1.00 1,374,169.50 13,866,619.50
9 Washtafel + Meja Beton + Assesories 1.00 Bh 2,787,473.50 1 1.00 306,622.09 3,094,095.59
10 Pegadaan AC Wall, 1/2 PK 14.00 Unit 3,750,000.00 1 1.00 5,775,000.00 58,275,000.00
11 Pekerjaan Saluran Terbuka 30x40 cm Keliling Bangunan 462.00 m' 530,984.69 1 1.00 26,984,641.97 272,299,568.98
12 Pekerjaan Bak Kontrol pas bata 30x30 cn tinggi 35 cm 28.00 bh 676,959.00 1 1.00 2,085,033.72 21,039,885.72
13 Pasang bioseptick+lantai,dinding,plat penutup 7.00 Unit 11,841,712.30 1 1.00 9,118,118.47 92,010,104.59
XIII PEK. PARKIRAN dan LAIN-LAIN
1 Pas. Papan Nama SENTRA IKM MAESA Beserta Rangka Besi 1 .00 Ls 15,000,000.00 1 1.00 1,650,000.00 16,650,000.00
Tiang Pipa Huruf bahan Acrylic tebal 4 + Lampu LED
3 Pembersihan Akhir 1 .00 Ls 6,000,000.00 1 1.00 660,000.00 6,660,000.00
4 Laporan dan Dokumentasi 1 .00 Ls 4,500,000.00 1 1.00 495,000.00 4,995,000.00
JUMLAH BIAYA PEKERJAAN 2,729,281,951.64
PEMBULATAN 2,729,280,000.00
Mengetahui/disetujui oleh, dibuat oleh,
KEPALA DINAS PERDAGANGAN KONSULAN PERENCANA
KOTA BITUNG CV. PERSPECTIVE JOINT CONSULTAN
JOHNLI EVANS TAMAKA, SE Hesty A. Samuri, ST
NIP. 19750417 200003 1 004 Direktur