BIL OF QUANTITY
KEGIATAN : PEMBANGUNAN JALAN PEDESAAN
PEKERJAAN : PEMBANGUNAN JALAN SETAPAK KECAMATAN NAMROLE
LOKASI : KEC. NAMROLE
TAHUN ANGGARAN : 2024
NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH HARGA TKDN JUMLAH
PEK. ( Rp ) ( Rp ) (%) ( Rp )
1 2 3 4 5 6 7 8
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi Awal dan Akhir Ls 1 .00 2 ,000,000.00 2 ,000,000.00 1 00.00 2,000,000.00
2 Papan Nama Proyek LS 1 .00 5 00,000.00 5 00,000.00 1 00.00 500,000.00
3 Pnerapan K3 LS 1 .00 1 ,000,000.00 1 ,000,000.00 1 00.00 1,000,000.00
4 Dokumentasi Dan Laporan Ls 1 .00 5 ,000,000.00 5 ,000,000.00 1 00.00 5,000,000.00
SUB TOTAL I 8,500,000.00 100.00 8,500,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi M3 6 .92 8 7,333.24 6 04,629.82 1 00.00 604,629.82
2 Pas. Pondasi Batu Kali Cam. 1PC : 4PP M3 1 3.85 1 ,358,330.55 1 8,808,123.96 9 8.54 18,533,808.98
3 Pas. Batu Kosong M3 2 7.69 9 60,638.70 2 6,602,967.52 1 00.00 26,602,967.52
SUB TOTAL II 46,015,721.30 99.40 45,741,406.33
III PEKERJAAN BETON DAN PLESTERAN
1 Pek. Rabat Beton camp. 1PC : 2PP : 3KR , t = 6 cm M3 1 6.15 1 ,367,820.45 2 2,096,113.54 9 6.58 21,341,161.21
2 Pek. Plesteran M2 6 7.69 9 0,244.41 6 ,109,005.09 9 8.83 6,037,480.00
SUB TOTAL III 28,205,118.63 97.07 27,378,641.21