| Reason | |||
|---|---|---|---|
| 0418257556126000 | Rp 430,400,000 | - | |
| 0022952774121000 | Rp 439,575,282 | - | |
Eben Ezer | 0210027009127000 | Rp 448,332,650 | Tidak hadir pada waktu Pembuktian Kualifikasi |
| 0313489775124000 | - | - | |
| 0417307196127000 | Rp 475,709,371 | - | |
| 0532867041121000 | - | - | |
| 0812335545124000 | - | - | |
| 0405951682128000 | Rp 484,200,000 | - | |
| 0939846853128000 | Rp 529,730,000 | - | |
CV Dyandra Mitra Persada | 08*0**8****28**0 | - | - |
| 0415217223121000 | - | - | |
| 0917409021116000 | - | - | |
| 0311826366113000 | - | - | |
| 0614642783118000 | - | - | |
| 0535488480127000 | - | - | |
| 0631580149127000 | - | - | |
| 0708351598127000 | - | - | |
| 0021068242127000 | - | - | |
CV Yusha Putra Mandiri | 12*1**0****10**4 | - | - |
| 0029318334128000 | - | - | |
| 0823235593128000 | - | - | |
| 0024949315128000 | - | - | |
| 0312320161127000 | - | - | |
| 0314009697121000 | - | - | |
| 0014720445128000 | - | - | |
| 0903548824121000 | - | - | |
| 0857649214128000 | - | - | |
| 0824698211124000 | - | - | |
| 0629595844121000 | - | - | |
| 0315604280122000 | - | - | |
CV Solusi Inti Pembangunan | 08*2**3****06**0 | - | - |
DAFTAR KUANTITAS DAN HARGA
Pekerjaan : Pembangunan Ruang Kelas Baru SMP Negeri 5 Sumbul
SUMBER DANA: APBD Kab. DAIRI Tahun Anggaran 2023
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
ANALISA
(Rp.) (Rp.)
a b c d e f g = (d x f)
I. PEKERJAAN PERSIAPAN
1 Pek. Patok-patok profil, Pengukuran dan Pemasangan bowplank Ls 1 .00 Ls -
2 Pekerjaan Pembersihan dan Perataan Lokasi Ls 1 .00 Ls -
3 Biaya Kesehatan dan Keselamatan Kerja Ls 1 .00 Ls -
4 Papan proyek Ls 1 .00 Ls -
5 Membuat/ Sewa gudang dan Direksikeet Ls 1 .00 Ls -
JUMLAH BIAYA PEKERJAAN PERSIAPAN -
II. PEKERJAAN PONDASI
1 Pek. Galian tanah
- Galian Tanah Pondasi A.1.5.1.1 38.76 M3 -
2 Pek. Timbunan Pasir Urug
- Timbunan Pasir urug t=5cm A.1.5.1.10 10.14 M3 -
3 Pek. Timbunan Tanah dipadatkan (bekas galian tanah)
- Timbunan kembali Pondasi (Bekas galian tanah) A.1.5.1.7 21.80 M3 -
- Timbunan Di bawah Lantai Keramik A.1.5.1.10A 23.62 M3 -
4 Pek. Pasangan Batu Kosong
- Pasangan Batu Kosong t=10cm A.3.1.1.9. 4.56 M3 -
5 Pekerjaan Pondasi Menerus
- Pek. Pasangan batu belah/ gunung untuk pondasi camp 1 : 4 A.3.1.1.2 16.96 M3 -
6 Pekerjaan Pondasi Kolom Selasar
- Timbunan Pasir urug t=5cm A.1.5.1.10 0.09 M3 -
- Pek. 'Beton Cor K- 125 untuk Lantai Kerja A.4.1.1.2 0.09 M3 -
- Beton Cor K- 225 untuk Pondasi Kolom Selasar A.4.1.1.7 0.36 M3 -
- Bekisting A.4.1.1.18 0.52 M² -
7 Pek. Soof uk. 15/20 cm
- Beton Cor K- 225 A.4.1.1.7 2.27 M3 -
- Besi Tulangan A.4.1.1.15 415.22 Kg. -
- Bekisting A.4.1.1.19 15.15 M² -
JUMLAH BIAYA PEKERJAAN PONDASI -
III. PEKERJAAN STRUKTUR BETON
1 Pek. Kolom (P1) uk. 20/20 cm
- Beton Cor K- 225 A.4.1.1.7 0.76 M3 -
- Besi Tulangan A.4.1.1.15 98.39 Kg. -
- Bekisting A.4.1.1.20 7.64 M² -
2 Pek. Kolom (P2) uk. 20/20 cm
- Beton Cor K- 225 A.4.1.1.7 0.87 M3 -
- Besi Tulangan A.4.1.1.15 111.55 Kg. -
- Bekisting A.4.1.1.20 8.69 M² -
3 Pek. Kolom (Kp) uk. 13/13 cm
- Beton Cor K- 225 A.4.1.1.7 0.67 M3 -
- Besi Tulangan A.4.1.1.15 174.49 Kg. -
- Bekisting A.4.1.1.20 10.35 M² -
4 Pek. Ring Balok uk. 13/15 cm
- Beton Cor K- 225 A.4.1.1.7 1.46 M3 -
- Besi Tulangan A.4.1.1.15 361.44 Kg. -
- Bekisting A.4.1.1.21 32.25 M² -
JUMLAH BIAYA PEKERJAAN STRUKTUR BETON -
IV. PEKERJAAN DINDING DAN PLESTERAN
1 Pek. Pasangan dinding 1/2 batu bata camp. 1 : 4 A.4.4.1.9 166.91 M² -
2 Pek. Plesteran camp. 1 : 4 + acian A.4.4.2.4 333.82 M² -
JUMLAH BIAYA PEKERJAAN DINDING DAN PLESTERAN -
V. PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pek. Keramik Lantai Uk. 60 x 60 cm A.4.4.3.36.C 157.87 M² -
2 Pek. 'Beton Cor K- 125 untuk Lantai Kerja A.4.1.1.2 7.89 M3 -
3 Pek. Keramik Dinding Corak Batu Kacang Uk. 40 x 40 cm A.4.4.3.36.B2 18.53 M² -
JUMLAH BIAYA PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING -
VI. PEKERJAAN LANGIT-LANGIT (PLAFOND) DAN PENUTUP ATAP
1 Pek. Rangka Plafon (baja ringan) Dihitung 200.35 M² -
2 Pek. Plafond PVC 6 mm Dihitung 200.35 M² -
Pek. Atap spandeck warna 0,30 mm (model Spanrib) + rangka Baja
3 Dihitung 232.00 M² -
ringan + Rabung + Talang dalam
4 Pek. Listplank GRC uk 1 x 20 cm Dihitung 63.20 M -
JUMLAH BIAYA PEKERJAAN LANGIT-LANGIT (PLAFOND) -
VII. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu, Jendela dan Ventilasi (Kayu Sembarang Keras) A.4.6.1.2.A 0.91 M3 -
2 Pek. Jendela Kaca (Kayu Sembarang Keras) A.4.6.1.6. A 13.86 M2 -
3 Pek. Pintu Panil (Kayu Sembarang Keras) A.4.6.1.5. A 5.04 M2 -
JUMLAH BIAYA PEKERJAAN PINTU DAN JENDELA -
VIII. PEKERJAAN ALAT-ALAT PENGGANTUNG DAN KUNCI
1 Biaya pembelian dan pemasangan kunci tanam biasa Ls 2.00 Psg. -
2 Biaya pembelian dan pemasangan engsel besar untuk pintu Ls 12.00 Psg. -
3 Biaya pembelian dan pemasangan grendel untuk pintu Ls 4.00 Psg. -
4 Biaya pembelian dan pemasangan engsel kecil untuk jendela Ls 68.00 Psg. -
5 Biaya pembelian dan pemasangan grendel Kodok untuk jendela Ls 34.00 Bh. -
6 Biaya pembelian dan pemasangan hak angin untuk jendela Ls 68.00 Psg. -
7 Biaya pembelian dan pemasangan handle untuk jendela Ls 34.00 Bh. -
JUMLAH BIAYA PEKERJAAN ALAT-ALAT PENGGANTUNG DAN KUNCI -
IX. PEKERJAAN PENGECATAN
1 Pek. Cat minyak kilat untuk Kozen, Pintu, Jendela dan Ventilasi A.4.7.1.4. 21.63 M2 -
2 Pek. Mengecat dinding (Cat tembok) A.4.7.1.10 333.82 M2 -
3 Pek. Cat minyak kilat untuk Listplank A.4.7.1.4. 12.64 M2 -
JUMLAH BIAYA PEKERJAAN PENGECATAN -
X. PEKERJAAN ELEKTRIKAL
1 Pemasangan 1 Buah Titik Lampu ( Saklar Ganda) - 4.00 Unit -
2 Pemasangan 1 Buah Titik Lampu ( Stop Kontak) - 4.00 Unit -
3 Lampu SL 18 Watt - 14.00 Unit -
4 Instalasi listrik titik api lampu (NYM 3x2.5mm) - 14.00 Titik -
JUMLAH BIAYA PEKERJAAN ELEKTRIKAL -
XI. PEKERJAAN SALURAN
1 Pekerjaan Galian Tanah A.1.5.1.1 24.18 M3 -
2 Pekerjaan Dinding Pas Batu Bata A.4.4.1.9 80.60 M2 -
3 Pekerjaan Cor Rabat Untuk Lantai A.4.1.1.2 1.86 M3 -
4 Pek. Plesteran camp. 1 : 4 + acian A.4.4.2.4 68.20 M2 -
JUMLAH BIAYA PEKERJAAN SALURAN -
XII. PEKERJAAN MEUBILER
1 Pek. Pengadaan Kursi siswa Anl -2 94.00 Unit -
2 Pek. Pengadaan Kursi kerja/ guru Anl -4 2.00 Unit -
3 Pek. Pengadaan Meja siswa Anl -1 94.00 Unit -
4 Pek. Pengadaan Meja kerja/ guru Anl -3 2.00 Unit -
5 Pek. Pengadaan Lemari Simpan Anl -5 2.00 Unit -
6 Pek. Pengadaan Papan tulis gantung Anl -6 2.00 Unit -
7 Pek. Pengadaan Papan Absen Anl -7 2.00 Unit -
JUMLAH BIAYA PEKERJAAN MEUBILER -
R E K A P I T U L A S I
I. PEKERJAAN PERSIAPAN Rp. -
II. PEKERJAAN PONDASI Rp. -
III. PEKERJAAN STRUKTUR BETON Rp. -
IV. PEKERJAAN DINDING DAN PLESTERAN Rp. -
V. PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp. -
VI. PEKERJAAN LANGIT-LANGIT (PLAFOND) DAN PENUTUP ATAP Rp. -
VII. PEKERJAAN PINTU DAN JENDELA Rp. -
VIII. PEKERJAAN ALAT-ALAT PENGGANTUNG DAN KUNCI Rp. -
IX. PEKERJAAN PENGECATAN Rp. -
X. PEKERJAAN ELEKTRIKAL Rp. -
XI. PEKERJAAN SALURAN Rp. -
XII. PEKERJAAN MEUBILER Rp. -
J U M L A H Rp. -
Ppn 11% Rp. -
JUMLAH TOTAL Rp. -