REKAPITULASI BILL OF QUANTITY (BoQ)
KEGIATAN : PENGELOLAAN SARANA PRASARANA BIDANG PEMBINAAN SD
SUB KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
UNTUK UPTD SD NEGERI 1 MAJASARI (DAU 2025)
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SD NEGERI 1 MAJASARI
JUMLAH TKDN JUMLAH BIAYA TKDN
NO. URAIAN PEKERJAAN
(RP.) (%) (RP.)
A PEKERJAAN PERSIAPAN 7.976.818,00 2,42% 7.678.079,26
JUMLAH A 7.976.818,00 2,42% 7.678.079,26
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
I PEKERJAAN TANAH DAN PONDASI 3 1.726.939,06 9,93% 31.500.675,12
II PEKERJAAN PASANGAN 6 5.166.516,09 20,22% 64.151.133,13
III PEKERJAAN BETON K. 175 SITE MIX 4 1.699.331,66 10,22% 32.411.149,87
IV PEKERJAAN KUSEN 2 9.073.417,98 5,31% 16.851.207,90
V PEKERJAAN PENUTUP ATAP 6 6.679.338,48 11,45% 36.317.042,76
VI PEKERJAAN PLAFOND 3 1.257.898,72 8,25% 26.180.298,72
VII PEKERJAAN PENUTUP LANTAI DAN DINDING 2 9.445.798,08 7,14% 22.646.244,70
VIII PEKERJAAN PENGECATAN 9.277.188,79 1,78% 5.641.113,47
IX PEKERJAAN LISTRIK DAN MEKANIKAL 4.136.343,00 0,83% 2.645.007,51
X PEKERJAAN PERLENGKAPAN DAN ACSESORIES 750.000,00 0,24% 750.000,00
JUMLAH B 309.212.771,86 75,38% 239.093.873,18
a. JUMLAH TOTAL (A+B) 317.189.589,86 77,80% 2 46.771.952,44
b. PPN 11% (a x 11%) 34.890.854,88 2 7.144.914,77
c. JUMLAH TOTAL (a+b) 352.080.444,74 2 73.916.867,21
b. DIBULATKAN 352.080.000,00 2 73.916.000,00
TERBILANG :
Diperiksa, Dibuat,
Pejabat Pelaksana Teknis Kegiatan Konsultan Perencana
Dinas Pendidikan Dan Kebudayaan CV. AURA BUANA CAHAYA
Kabupaten Indramayu
TAUFIQULLAH, S.IP., M.AP SUYITNO, ST
NIP. 19770918 200801 1 004 Direktur
Disetujui,
Pejabat Pembuat Komitmen
Dinas Pendidikan Dan Kebudayaan
Kabupaten Indramayu
Bill Of Quantity (BoQ)
KEGIATAN : PENGELOLAAN SARANA PRASARANA BIDANG PEMBINAAN SD
SUB KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
UNTUK UPTD SD NEGERI 1 MAJASARI (DAU 2025)
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SD NEGERI 1 MAJASARI
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 7 7 7
A PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Kegiatan Digital Printing 1,00 Bh A.5 3 68.986,00 3 68.986,00 98,97% 0,12% 3 65.170,85
2 Pek. Pengukuran dan Pemasangan Bowplank 42,00 M' A.1 5 4.388,00 2 .284.296,00 99,30% 0,72% 2 .268.272,41
3 Biaya Administrasi Pelaporan & Dokumentasi 1,00 Ls - 2 .500.000,00 2 .500.000,00 100,00% 0,79% 2 .500.000,00
4 Pengadaan Air + Listrik Selama Pekerjaan 1,00 Ls - 5 00.000,00 5 00.000,00 100,00% 0,16% 5 00.000,00
5 Pembersihan dan Perapihan selesai pekerjaan 1,00 Ls - 5 00.000,00 5 00.000,00 100,00% 0,16% 5 00.000,00
6 Biaya Penyelenggaraan Sistem Manajemen Keselamatan
dan kesehatan kerja (SMK3)
a Alat Pelindung Kerja dan pelindungan diri
- Topi Pelindung (Safety Helmet) 10,00 Bh - 7 5.000,00 7 50.000,00 72,11% 0,17% 5 40.825,00
- Rompi Keselamatan ( Safety Vest) 10,00 Bh - 2 5.000,00 2 50.000,00 72,11% 0,06% 1 80.275,00
b Rambu - rambu
- Rambu Petunjuk 1,00 Bh - 7 5.000,00 7 5.000,00 100,00% 0,02% 7 5.000,00
- Rambu Larangan 1,00 Bh - 7 5.000,00 7 5.000,00 100,00% 0,02% 7 5.000,00
- Rambu Peringatan 1,00 Bh - 7 5.000,00 7 5.000,00 100,00% 0,02% 7 5.000,00
c BPJS Ketenagakerjaan dan Kesehatan Kerja 1,00 Ls - 5 98.536,00 5 98.536,00 100,00% 0,19% 5 98.536,00
JUMLAH PEKERJAAN A 7 .976.818,00 2,42% 7 .678.079,26
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah pondasi Menerus 30,24 M3 B.1 9 8.756,00 2 .986.381,44 100,00% 0,94% 2 .986.381,44
2 Pek. Galian tanah pondasi Tapak 8,45 M3 B.1 9 8.756,00 8 34.488,20 100,00% 0,26% 8 34.488,20
3 Pek. Urugan tanah bekas galian 10,29 M3 B.9 7 1.012,00 7 30.713,48 100,00% 0,23% 7 30.713,48
4 Pek. Urugan sirtu peninggian lantai t. 28 cm 21,11 M2 B.14 2 72.866,00 5 .760.201,26 100,00% 1,82% 5 .760.201,26
5 Pek. Lapisan pasir bawah pondasi menerus t. 5 cm 1,68 M3 B.12 3 16.192,00 5 31.202,56 100,00% 0,17% 5 31.202,56
6 Pek. Lapisan pasir bawah pondasi tapak t. 5 cm 0,22 M3 B.12 3 16.192,00 6 9.562,24 100,00% 0,02% 6 9.562,24
7 Pek. Lapisan pasir bawah lantai t. 5 cm 3,60 M3 B.12 3 16.192,00 1 .138.291,20 100,00% 0,36% 1 .138.291,20
8 Pek. Aanstamping batu kali 6,72 M3 C.7 6 68.482,00 4 .492.199,04 100,00% 1,42% 4 .492.199,04
9 Pek. Pasang Pondasi Batu Kali 1 Pc : 5 Psr 13,23 M3 C.4 1 .098.068,00 1 4.527.439,64 98,44% 4,51% 1 4.301.175,70
10 Pek. Curucuk bambu ampel dia. 7 - 10 cm p = 1.50 m 84,00 Ttk A.10 7 .815,00 6 56.460,00 100,00% 0,21% 6 56.460,00
Sub. Total Pekerjaan I 3 1.726.939,06 9,93% 3 1.500.675,12
II PEKERJAAN PASANGAN
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 Pek. Pas. 1/2 bata 1 Pc : 5 Psr 100,09 M2 D.3 164.391,00 1 6.453.895,19 99,26% 5,15% 1 6.332.057,90
2 Pek. Plesteran 1 Pc : 5 Psr 185,34 M2 E.3 75.501,00 1 3.993.355,34 98,85% 4,36% 1 3.832.259,43
3 Pek. Acian Dinding 185,34 M2 E.6 46.526,00 8 .623.128,84 99,12% 2,69% 8 .547.381,40
4 Pek. Profil Kolom 4,00 Bh - 5 5.000,00 2 20.000,00 100,00% 0,07% 2 20.000,00
5 Pek. Pas. Rabat Alas Lantai t. 5 cm 1Pc : 3Pc : 5Kr 3,60 M3 G.1 1.080.199,00 3 .888.716,40 97,46% 1,19% 3 .790.025,89
6 Pek. Pas. Rabat Alas Pondasi Tapak t. 5 cm 1Pc : 3Pc : 5Kr 0,22 M3 G.1 1.080.199,00 2 37.643,78 97,46% 0,07% 2 31.612,69
7 Pek. Pas. Rabat Beton keliling bangunan t. 7 cm 1Pc : 3Pc : 5Kr 2,94 M3 G.1 1.080.199,00 3 .175.785,06 97,46% 0,98% 3 .095.187,81
8 Pek. Pas. tangga landai (Ramp) Beton t. 10 cm 1Pc : 3Pc : 5Kr 0,52 M3 G.1 1.080.199,00 5 61.703,48 97,46% 0,17% 5 47.448,18
9 Pek. Pas. Gravel 1/2 Dia. 20 Cm berikut pasangan 42,00 M' J.28 4 28.864,00 1 8.012.288,00 97,46% 5,53% 1 7.555.159,82
Sub. Total Pekerjaan II 6 5.166.516,09 20,22% 6 4.151.133,13
III PEKERJAAN BETON K. 175 SITE MIX
1 Pek. Pasang Pondasi Tapak 60x60 Cm T. 20 Cm (155.61 Kg/m3)
- Beton Site Mix K. 175 0 ,86 M3 G.2 1 .294.719,00 1 .113.458,34 98,07% 0,34% 1 .091.975,28
- Besi beton terpasang U-24 1 34,45 Kg G.25 1 9.419,00 2 .610.884,55 57,66% 0,47% 1 .505.469,54
2 Pek. Pasang Sloof 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 1 ,26 M3 G.2 1 .294.719,00 1 .631.345,94 98,07% 0,50% 1 .599.870,75
- Besi beton terpasang U-24 2 10,00 Kg G.25 1 9.419,00 4 .077.990,00 57,66% 0,74% 2 .351.421,37
- Begisting Papan Terentang 1 6,80 M2 G.23 1 78.115,00 2 .992.332,00 95,72% 0,90% 2 .864.143,64
3 Pek. Pasang Kolom 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 1 ,26 M3 G.2 1 .294.719,00 1 .631.345,94 98,07% 0,50% 1 .599.870,75
- Besi beton terpasang U-24 2 10,00 Kg G.25 1 9.419,00 4 .077.990,00 57,66% 0,74% 2 .351.421,37
- Begisting Papan Terentang 1 6,80 M2 G.23 1 78.115,00 2 .992.332,00 95,72% 0,90% 2 .864.143,64
4 Pek. Pasang Kolom Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,43 M3 G.2 1 .294.719,00 5 56.729,17 98,07% 0,17% 5 45.987,64
- Besi beton terpasang U-24 7 2,00 Kg G.25 1 9.419,00 1 .398.168,00 57,66% 0,25% 8 06.201,61
- Begisting Papan Terentang 1 0,08 M2 G.23 1 78.115,00 1 .795.399,20 95,72% 0,54% 1 .718.486,18
5 Pek. Pasang Kolom Praktis 12/12 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,15 M3 G.2 1 .294.719,00 1 94.207,85 98,07% 0,06% 1 90.460,80
- Besi beton terpasang U-24 2 5,20 Kg G.25 1 9.419,00 4 89.358,80 57,66% 0,09% 2 82.170,56
- Begisting Papan Terentang 2 ,52 M2 G.23 1 78.115,00 4 48.849,80 95,72% 0,14% 4 29.621,55
6 Pek. Pasang Ring Balok 15/20 (166.67 Kg/m3)
- Beton Site Mix K. 175 0 ,90 M3 G.2 1 .294.719,00 1 .165.247,10 98,07% 0,36% 1 .142.764,82
- Besi beton terpasang U-24 1 50,00 Kg G.25 1 9.419,00 2 .912.850,00 57,66% 0,53% 1 .679.586,69
- Begisting Papan Terentang 8 ,40 M2 G.23 1 78.115,00 1 .496.166,00 95,72% 0,45% 1 .432.071,82
7 Pek. Pasang Balok Liufel 12/15 Cm (216,38 Kg/m3)
- Beton Site Mix K. 175 0 ,29 M3 G.2 1 .294.719,00 3 75.468,51 98,07% 0,12% 3 68.224,22
- Besi beton terpasang U-24 6 2,32 Kg G.25 1 9.419,00 1 .210.192,08 57,66% 0,22% 6 97.812,28
- Begisting Papan Terentang 6 ,72 M2 G.23 1 78.115,00 1 .196.932,80 95,72% 0,36% 1 .145.657,46
8 Pek. Pasang Balok Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,24 M3 G.2 1 .294.719,00 3 10.732,56 98,07% 0,10% 3 04.737,29
- Besi beton terpasang U-24 4 0,00 Kg G.25 1 9.419,00 7 76.760,00 57,66% 0,14% 4 47.889,78
- Begisting Papan Terentang 6 ,00 M2 G.23 1 78.115,00 1 .068.690,00 95,72% 0,32% 1 .022.908,44
9 Pek. Pasang Balok Konsol 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,18 M3 G.2 1 .294.719,00 2 33.049,42 98,07% 0,07% 2 28.552,96
- Besi beton terpasang U-24 3 0,80 Kg G.25 1 9.419,00 5 98.105,20 57,66% 0,11% 3 44.875,13
- Begisting Papan Terentang 4 ,84 M2 G.23 1 78.115,00 8 62.076,60 95,72% 0,26% 8 25.146,14
10 Pek. Pasang Balok ampig 12/12 Cm (308.25 Kg/m3)
- Beton Site Mix K. 175 0 ,34 M3 G.2 1 .294.719,00 4 40.204,46 98,07% 0,14% 4 31.711,16
- Besi beton terpasang U-24 1 04,76 Kg G.25 1 9.419,00 2 .034.334,44 57,66% 0,37% 1 .173.023,34
- Begisting Papan Terentang 5 ,66 M2 G.23 1 78.115,00 1 .008.130,90 95,72% 0,30% 9 64.943,63
Sub. Total Pekerjaan III 4 1.699.331,66 0 ,10 3 2.411.149,87
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
IV PEKERJAAN KUSEN
1 Pek. Kusen + Pintu Steel Door Mother and Son + BV dan Acsesoris Type P1
- Pintu Steel Door + Acsesories (Pabrikasi) 1,00 Unit F.27.Rob.1 1 0.420.387,00 1 0.420.387,00 50,09% 1,65% 5 .219.140,56
2 Pek. Pasang Kusen + Jendela Alumunium type J1 (4 Unit)
- Frame Kusen Alumunium 4" Warna Putih 53,36 M' F.6 1 92.272,00 1 0.259.633,92 62,53% 2,02% 6 .414.848,58
- Daun Jendela + Engsel Casment + Kaca polos 5 mm 8,00 Unit F.28 6 44.555,00 5 .156.440,00 60,74% 0,99% 3 .131.935,77
- Pasang Kaca 5 mm 4,40 M2 L.8 1 99.775,00 8 79.010,00 61,20% 0,17% 5 37.922,65
3 Pek. Pasang Kusen Alumunium type BV1 (1 Unit)
- Frame Kusen Alumunium 4" Warna Putih 7,48 M' F.6 1 92.272,00 1 .438.194,56 62,53% 0,28% 8 99.232,90
- Pasang Kaca 5 mm 1,10 M2 L.8 1 99.775,00 2 19.752,50 100,00% 0,07% 2 19.752,50
4 Pek. Pasang Jalusi Ampig Kayu Kelas Kuat II 2,00 Unit - 3 50.000,00 7 00.000,00 61,20% 0,14% 4 28.374,94
Sub. Total Pekerjaan IV 2 9.073.417,98 0 ,05 1 6.851.207,90
V PEKERJAAN PENUTUP ATAP
1 Pek. Kuda-kuda + rangka atap baja ringan (Zincallume) 120,96 M2 H.18 1 96.978,00 2 3.826.458,88 79,17% 5,95% 1 8.863.849,92
2 Pek. Pasang Atap Onduvilla t. 3 mm 120,96 M2 H.43 3 10.490,00 3 7.556.870,40 37,51% 4,44% 1 4.089.116,80
3 Pek. Pasang Nok Atap Onduvilla t. 3 mm 9,60 M' H.55 2 02.497,00 1 .943.971,20 49,07% 0,30% 9 53.981,01
4 Pek. Pasang Lisplank GRC Tumpangsari (1/20 + 1/10) Cm 31,80 M' H.64 1 05.410,00 3 .352.038,00 71,90% 0,76% 2 .410.095,03
Sub. Total Pekerjaan V 6 6.679.338,48 11,45% 3 6.317.042,76
VI PEKERJAAN PLAFOND
1 Pek. Pasang Rangka Plafond galvalume modul 60x60 Cm 100,96 M2 I.23 9 2.501,00 9 .338.900,96 69,20% 2,04% 6 .462.859,13
2 Pek. Pasang Plafond PVC Motif 100,96 M2 I.16 1 93.171,00 1 9.502.544,16 90,04% 5,54% 1 7.559.224,86
3 Pek. Pasang List Plafond PVC 50,60 M' I.29 4 7.756,00 2 .416.453,60 89,31% 0,68% 2 .158.214,74
Sub. Total Pekerjaan VI 3 1.257.898,72 8,25% 2 6.180.298,72
VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Pasang Lantai Granit 60x60 Cm 72,00 M2 M.14 3 35.048,00 2 4.123.456,00 75,78% 5,76% 1 8.279.718,53
2 Pek. Pasang Plint Granit Ukuran 10x60 Cm 38,00 M' M.31 9 1.924,00 3 .493.112,00 79,01% 0,87% 2 .760.072,36
3 Pek. Pasang Keramik Kolom motif batu alam 20x40 cm t. 1,6 m 7,68 M2 N.3 2 38.181,00 1 .829.230,08 87,82% 0,51% 1 .606.453,80
Sub. Total Pekerjaan VII 2 9.445.798,08 7,14% 2 2.646.244,70
VIII PEKERJAAN PENGECATAN
1 Pek. Cat dinding interior 85,25 M2 P.12 4 2.743,00 3 .643.840,75 61,44% 0,71% 2 .238.777,02
2 Pek. Cat dinding Exterior 100,09 M2 P.13 5 2.188,00 5 .223.496,92 61,44% 1,01% 3 .209.318,32
3 Pek. Cat Listplank 6,36 M2 P.4 6 4.442,00 4 09.851,12 47,09% 0,06% 1 93.018,14
Sub. Total Pekerjaan VIII 9 .277.188,79 1,78% 5 .641.113,47
IX PEKERJAAN LISTRIK DAN MEKANIKAL
1 Pek. Pasang Instalasi Titik Penerangan dan Stop Kontak 7,00 Titik Q.1 2 21.409,00 1 .549.863,00 92,85% 0,45% 1 .439.105,69
2 Pek. Pasang Saklar Tunggal 1,00 Bh Q.3 3 6.840,00 3 6.840,00 57,07% 0,01% 2 1.024,20
3 Pek. Pasang Saklar Double 1,00 Bh Q.4 3 9.830,00 3 9.830,00 59,40% 0,01% 2 3.659,61
4 Pek. Pasang Stop Kontak 1,00 Bh Q.2 3 7.760,00 3 7.760,00 56,38% 0,01% 2 1.288,61
5 Pas. Lampu TL 2x18 watt + dudukan Removable Mounting (RM) 4,00 Bh Q.7 5 32.145,00 2 .128.580,00 45,35% 0,30% 9 65.308,98
6 Pas. Lampu Downligt 4" + LED 9 Watt 2,00 Bh Q.8 1 71.735,00 3 43.470,00 50,84% 0,06% 1 74.620,42
Sub. Total Pekerjaan IX 4 .136.343,00 0,83% 2 .645.007,51
X PEKERJAAN PERLENGKAPAN DAN ACSESORIES
1 Pek. Pasang Prasasti Granit Uk. P. 30 Cm L. 20 Cm 1,00 Bh - 7 50.000,00 7 50.000,00 100,00% 0,24% 7 50.000,00
Sub. Total Pekerjaan X 7 50.000,00 0,24% 7 50.000,00
JUMLAH B 3 09.212.771,86 75,38% 2 39.093.873,18
JUMLAH TOTAL PEKERJAAN (A+B) 317.189.589,86 77,80% 246.771.952,44