BILL OF QUANTITY (BoQ)
KEGIATAN : PENGELOLAAN SARANA PRASARANA BIDANG PEMBINAAN SD
SUB KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
UNTUK UPTD SD NEGERI 2 TANJUNGKERTA (DAU 2025)
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SD NEGERI 2 TANJUNGKERTA
JUMLAH TKDN JUMLAH BIAYA TKDN
NO. URAIAN PEKERJAAN
(RP.) (%) (RP.)
A PEKERJAAN PERSIAPAN 7.976.818,00 2,42% 7 .678.079,26
JUMLAH A 7.976.818,00 2,42% 7 .678.079,26
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
I PEKERJAAN TANAH DAN PONDASI 3 1.726.939,06 9,93% 3 1.500.675,12
II PEKERJAAN PASANGAN 6 5.166.516,09 20,22% 6 4.151.133,13
III PEKERJAAN BETON K. 175 SITE MIX 4 1.699.331,66 10,22% 3 2.411.149,87
IV PEKERJAAN KUSEN 2 9.073.417,98 5,31% 1 6.851.207,90
V PEKERJAAN PENUTUP ATAP 6 6.679.338,48 11,45% 3 6.317.042,76
VI PEKERJAAN PLAFOND 3 1.257.898,72 8,25% 2 6.180.298,72
VII PEKERJAAN PENUTUP LANTAI DAN DINDING 2 9.445.798,08 7,14% 2 2.646.244,70
VIII PEKERJAAN PENGECATAN 9.277.188,79 1,78% 5 .641.113,47
IX PEKERJAAN LISTRIK DAN MEKANIKAL 4.136.343,00 0,83% 2 .645.007,51
X PEKERJAAN PERLENGKAPAN DAN ACSESORIES 750.000,00 0,24% 7 50.000,00
JUMLAH B 309.212.771,86 75,38% 2 39.093.873,18
a. JUMLAH TOTAL (A+B) 317.189.589,86 77,80% 246.771.952,44
b. PPN 11% (a x 11%) 34.890.854,88 27.144.914,77
c. JUMLAH TOTAL (a+b) 352.080.444,74 273.916.867,21
b. DIBULATKAN 352.080.000,00 273.916.000,00
TERBILANG : Tiga Ratus Lima Puluh Dua Juta Delapan Puluh Ribu Rupiah
Diperiksa, Dibuat,
Pejabat Pelaksana Teknis Kegiatan Konsultan Perencana
Dinas Pendidikan Dan Kebudayaan CV. AURA BUANA CAHAYA
Kabupaten Indramayu
TAUFIQULLAH, S.IP., M.AP SUYITNO, ST
NIP. 19770918 200801 1 004 Direktur
Disetujui,
Pejabat Pembuat Komitmen
Dinas Pendidikan Dan Kebudayaan
Kabupaten Indramayu
Bill Of Quantity (BoQ)
KEGIATAN : PENGELOLAAN SARANA PRASARANA BIDANG PEMBINAAN SD
SUB KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
UNTUK UPTD SD NEGERI 2 TANJUNGKERTA (DAU 2025)
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SD NEGERI 2 TANJUNGKERTA
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 7 7 7
A PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Kegiatan Digital Printing 1,00 Bh A.5 3 68.986,00 368.986,00 98,97% 0,12% 365.170,85
2 Pek. Pengukuran dan Pemasangan Bowplank 42,00 M' A.1 5 4.388,00 2.284.296,00 99,30% 0,72% 2.268.272,41
3 Biaya Administrasi Pelaporan & Dokumentasi 1,00 Ls - 2 .500.000,00 2.500.000,00 100,00% 0,79% 2.500.000,00
4 Pengadaan Air + Listrik Selama Pekerjaan 1,00 Ls - 5 00.000,00 500.000,00 100,00% 0,16% 500.000,00
5 Pembersihan dan Perapihan selesai pekerjaan 1,00 Ls - 5 00.000,00 500.000,00 100,00% 0,16% 500.000,00
6 Biaya Penyelenggaraan Sistem Manajemen Keselamatan
dan kesehatan kerja (SMK3)
a Alat Pelindung Kerja dan pelindungan diri
- Topi Pelindung (Safety Helmet) 10,00 Bh - 7 5.000,00 750.000,00 72,11% 0,17% 540.825,00
- Rompi Keselamatan ( Safety Vest) 10,00 Bh - 2 5.000,00 250.000,00 72,11% 0,06% 180.275,00
b Rambu - rambu
- Rambu Petunjuk 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
- Rambu Larangan 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
- Rambu Peringatan 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
c BPJS Ketenagakerjaan dan Kesehatan Kerja 1,00 Ls - 5 98.536,00 598.536,00 100,00% 0,19% 598.536,00
JUMLAH PEKERJAAN A 7.976.818,00 2,42% 7.678.079,26
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah pondasi Menerus 30,24 M3 B.1 9 8.756,00 2.986.381,44 100,00% 0,94% 2.986.381,44
2 Pek. Galian tanah pondasi Tapak 8,45 M3 B.1 9 8.756,00 834.488,20 100,00% 0,26% 834.488,20
3 Pek. Urugan tanah bekas galian 10,29 M3 B.9 7 1.012,00 730.713,48 100,00% 0,23% 730.713,48
4 Pek. Urugan sirtu peninggian lantai t. 28 cm 21,11 M2 B.14 2 72.866,00 5.760.201,26 100,00% 1,82% 5.760.201,26
5 Pek. Lapisan pasir bawah pondasi menerus t. 5 cm 1,68 M3 B.12 3 16.192,00 531.202,56 100,00% 0,17% 531.202,56
6 Pek. Lapisan pasir bawah pondasi tapak t. 5 cm 0,22 M3 B.12 3 16.192,00 69.562,24 100,00% 0,02% 69.562,24
7 Pek. Lapisan pasir bawah lantai t. 5 cm 3,60 M3 B.12 3 16.192,00 1.138.291,20 100,00% 0,36% 1.138.291,20
8 Pek. Aanstamping batu kali 6,72 M3 C.7 6 68.482,00 4.492.199,04 100,00% 1,42% 4.492.199,04
9 Pek. Pasang Pondasi Batu Kali 1 Pc : 5 Psr 13,23 M3 C.4 1 .098.068,00 14.527.439,64 98,44% 4,51% 14.301.175,70
10 Pek. Curucuk bambu ampel dia. 7 - 10 cm p = 1.50 m 84,00 Ttk A.10 7 .815,00 656.460,00 100,00% 0,21% 656.460,00
Sub. Total Pekerjaan I 31.726.939,06 9,93% 31.500.675,12
II PEKERJAAN PASANGAN
1 Pek. Pas. 1/2 bata 1 Pc : 5 Psr 100,09 M2 D.3 1 64.391,00 16.453.895,19 99,26% 5,15% 16.332.057,90
2 Pek. Plesteran 1 Pc : 5 Psr 185,34 M2 E.3 7 5.501,00 13.993.355,34 98,85% 4,36% 13.832.259,43
3 Pek. Acian Dinding 185,34 M2 E.6 4 6.526,00 8.623.128,84 99,12% 2,69% 8.547.381,40
4 Pek. Profil Kolom 4,00 Bh - 5 5.000,00 220.000,00 100,00% 0,07% 220.000,00
5 Pek. Pas. Rabat Alas Lantai t. 5 cm 1Pc : 3Pc : 5Kr 3,60 M3 G.1 1 .080.199,00 3.888.716,40 97,46% 1,19% 3.790.025,89
6 Pek. Pas. Rabat Alas Pondasi Tapak t. 5 cm 1Pc : 3Pc : 5Kr 0,22 M3 G.1 1 .080.199,00 237.643,78 97,46% 0,07% 231.612,69
7 Pek. Pas. Rabat Beton keliling bangunan t. 7 cm 1Pc : 3Pc : 5Kr 2,94 M3 G.1 1 .080.199,00 3.175.785,06 97,46% 0,98% 3.095.187,81
8 Pek. Pas. tangga landai (Ramp) Beton t. 10 cm 1Pc : 3Pc : 5Kr 0,52 M3 G.1 1 .080.199,00 561.703,48 97,46% 0,17% 547.448,18
9 Pek. Pas. Gravel 1/2 Dia. 20 Cm berikut pasangan 42,00 M' J.28 4 28.864,00 18.012.288,00 97,46% 5,53% 17.555.159,82
Sub. Total Pekerjaan II 65.166.516,09 20,22% 64.151.133,13
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
III PEKERJAAN BETON K. 175 SITE MIX
1 Pek. Pasang Pondasi Tapak 60x60 Cm T. 20 Cm (155.61 Kg/m3)
- Beton Site Mix K. 175 0 ,86 M3 G.2 1 .294.719,00 1 .113.458,34 98,07% 0,34% 1.091.975,28
- Besi beton terpasang U-24 1 34,45 Kg G.25 1 9.419,00 2 .610.884,55 57,66% 0,47% 1.505.469,54
2 Pek. Pasang Sloof 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 1 ,26 M3 G.2 1 .294.719,00 1 .631.345,94 98,07% 0,50% 1.599.870,75
- Besi beton terpasang U-24 2 10,00 Kg G.25 1 9.419,00 4 .077.990,00 57,66% 0,74% 2.351.421,37
- Begisting Papan Terentang 1 6,80 M2 G.23 1 78.115,00 2 .992.332,00 95,72% 0,90% 2.864.143,64
3 Pek. Pasang Kolom 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 1 ,26 M3 G.2 1 .294.719,00 1 .631.345,94 98,07% 0,50% 1.599.870,75
- Besi beton terpasang U-24 2 10,00 Kg G.25 1 9.419,00 4 .077.990,00 57,66% 0,74% 2.351.421,37
- Begisting Papan Terentang 1 6,80 M2 G.23 1 78.115,00 2 .992.332,00 95,72% 0,90% 2.864.143,64
4 Pek. Pasang Kolom Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,43 M3 G.2 1 .294.719,00 5 56.729,17 98,07% 0,17% 545.987,64
- Besi beton terpasang U-24 7 2,00 Kg G.25 1 9.419,00 1 .398.168,00 57,66% 0,25% 806.201,61
- Begisting Papan Terentang 1 0,08 M2 G.23 1 78.115,00 1 .795.399,20 95,72% 0,54% 1.718.486,18
5 Pek. Pasang Kolom Praktis 12/12 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,15 M3 G.2 1 .294.719,00 1 94.207,85 98,07% 0,06% 190.460,80
- Besi beton terpasang U-24 2 5,20 Kg G.25 1 9.419,00 4 89.358,80 57,66% 0,09% 282.170,56
- Begisting Papan Terentang 2 ,52 M2 G.23 1 78.115,00 4 48.849,80 95,72% 0,14% 429.621,55
6 Pek. Pasang Ring Balok 15/20 (166.67 Kg/m3)
- Beton Site Mix K. 175 0 ,90 M3 G.2 1 .294.719,00 1 .165.247,10 98,07% 0,36% 1.142.764,82
- Besi beton terpasang U-24 1 50,00 Kg G.25 1 9.419,00 2 .912.850,00 57,66% 0,53% 1.679.586,69
- Begisting Papan Terentang 8 ,40 M2 G.23 1 78.115,00 1 .496.166,00 95,72% 0,45% 1.432.071,82
7 Pek. Pasang Balok Liufel 12/15 Cm (216,38 Kg/m3)
- Beton Site Mix K. 175 0 ,29 M3 G.2 1 .294.719,00 3 75.468,51 98,07% 0,12% 368.224,22
- Besi beton terpasang U-24 6 2,32 Kg G.25 1 9.419,00 1 .210.192,08 57,66% 0,22% 697.812,28
- Begisting Papan Terentang 6 ,72 M2 G.23 1 78.115,00 1 .196.932,80 95,72% 0,36% 1.145.657,46
8 Pek. Pasang Balok Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,24 M3 G.2 1 .294.719,00 310.732,56 98,07% 0,10% 304.737,29
- Besi beton terpasang U-24 4 0,00 Kg G.25 1 9.419,00 776.760,00 57,66% 0,14% 447.889,78
- Begisting Papan Terentang 6 ,00 M2 G.23 1 78.115,00 1.068.690,00 95,72% 0,32% 1.022.908,44
9 Pek. Pasang Balok Konsol 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,18 M3 G.2 1 .294.719,00 233.049,42 98,07% 0,07% 228.552,96
- Besi beton terpasang U-24 3 0,80 Kg G.25 1 9.419,00 598.105,20 57,66% 0,11% 344.875,13
- Begisting Papan Terentang 4 ,84 M2 G.23 1 78.115,00 862.076,60 95,72% 0,26% 825.146,14
10 Pek. Pasang Balok ampig 12/12 Cm (308.25 Kg/m3)
- Beton Site Mix K. 175 0 ,34 M3 G.2 1 .294.719,00 440.204,46 98,07% 0,14% 431.711,16
- Besi beton terpasang U-24 1 04,76 Kg G.25 1 9.419,00 2.034.334,44 57,66% 0,37% 1.173.023,34
- Begisting Papan Terentang 5 ,66 M2 G.23 1 78.115,00 1.008.130,90 95,72% 0,30% 964.943,63
Sub. Total Pekerjaan III 41.699.331,66 0,10 32.411.149,87
IV PEKERJAAN KUSEN
1 Pek. Kusen + Pintu Steel Door Mother and Son + BV dan Acsesoris Type P1
- Pintu Steel Door + Acsesories (Pabrikasi) 1,00 Unit F.27.Rob.1 1 0.420.387,00 1 0.420.387,00 50,09% 1,65% 5.219.140,56
2 Pek. Pasang Kusen + Jendela Alumunium type J1 (4 Unit)
- Frame Kusen Alumunium 4" Warna Putih 53,36 M' F.6 1 92.272,00 1 0.259.633,92 62,53% 2,02% 6.414.848,58
- Daun Jendela + Engsel Casment + Kaca polos 5 mm 8,00 Unit F.28 6 44.555,00 5 .156.440,00 60,74% 0,99% 3.131.935,77
- Pasang Kaca 5 mm 4,40 M2 L.8 1 99.775,00 8 79.010,00 61,20% 0,17% 537.922,65
3 Pek. Pasang Kusen Alumunium type BV1 (1 Unit)
- Frame Kusen Alumunium 4" Warna Putih 7,48 M' F.6 1 92.272,00 1 .438.194,56 62,53% 0,28% 899.232,90
- Pasang Kaca 5 mm 1,10 M2 L.8 1 99.775,00 2 19.752,50 100,00% 0,07% 219.752,50
4 Pek. Pasang Jalusi Ampig Kayu Kelas Kuat II 2,00 Unit - 3 50.000,00 7 00.000,00 61,20% 0,14% 428.374,94
Sub. Total Pekerjaan IV 29.073.417,98 0,05 16.851.207,90
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
V PEKERJAAN PENUTUP ATAP
1 Pek. Kuda-kuda + rangka atap baja ringan (Zincallume) 120,96 M2 H.18 1 96.978,00 2 3.826.458,88 79,17% 5,95% 18.863.849,92
2 Pek. Pasang Atap Onduvilla t. 3 mm 120,96 M2 H.43 3 10.490,00 3 7.556.870,40 37,51% 4,44% 14.089.116,80
3 Pek. Pasang Nok Atap Onduvilla t. 3 mm 9,60 M' H.55 2 02.497,00 1 .943.971,20 49,07% 0,30% 953.981,01
4 Pek. Pasang Lisplank GRC Tumpangsari (1/20 + 1/10) Cm 31,80 M' H.64 1 05.410,00 3 .352.038,00 71,90% 0,76% 2.410.095,03
Sub. Total Pekerjaan V 66.679.338,48 11,45% 36.317.042,76
VI PEKERJAAN PLAFOND
1 Pek. Pasang Rangka Plafond galvalume modul 60x60 Cm 100,96 M2 I.23 9 2.501,00 9 .338.900,96 69,20% 2,04% 6.462.859,13
2 Pek. Pasang Plafond PVC Motif 100,96 M2 I.16 1 93.171,00 1 9.502.544,16 90,04% 5,54% 17.559.224,86
3 Pek. Pasang List Plafond PVC 50,60 M' I.29 4 7.756,00 2 .416.453,60 89,31% 0,68% 2.158.214,74
Sub. Total Pekerjaan VI 31.257.898,72 8,25% 26.180.298,72
VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Pasang Lantai Granit 60x60 Cm 72,00 M2 M.14 3 35.048,00 2 4.123.456,00 75,78% 5,76% 18.279.718,53
2 Pek. Pasang Plint Granit Ukuran 10x60 Cm 38,00 M' M.31 9 1.924,00 3 .493.112,00 79,01% 0,87% 2.760.072,36
3 Pek. Pasang Keramik Kolom motif batu alam 20x40 cm t. 1,6 m 7,68 M2 N.3 2 38.181,00 1 .829.230,08 87,82% 0,51% 1.606.453,80
Sub. Total Pekerjaan VII 29.445.798,08 7,14% 22.646.244,70
VIII PEKERJAAN PENGECATAN
1 Pek. Cat dinding interior 85,25 M2 P.12 4 2.743,00 3 .643.840,75 61,44% 0,71% 2.238.777,02
2 Pek. Cat dinding Exterior 100,09 M2 P.13 5 2.188,00 5 .223.496,92 61,44% 1,01% 3.209.318,32
3 Pek. Cat Listplank 6,36 M2 P.4 6 4.442,00 4 09.851,12 47,09% 0,06% 193.018,14
Sub. Total Pekerjaan VIII 9.277.188,79 1,78% 5.641.113,47
IX PEKERJAAN LISTRIK DAN MEKANIKAL
1 Pek. Pasang Instalasi Titik Penerangan dan Stop Kontak 7,00 Titik Q.1 2 21.409,00 1 .549.863,00 92,85% 0,45% 1.439.105,69
2 Pek. Pasang Saklar Tunggal 1,00 Bh Q.3 3 6.840,00 3 6.840,00 57,07% 0,01% 21.024,20
3 Pek. Pasang Saklar Double 1,00 Bh Q.4 3 9.830,00 3 9.830,00 59,40% 0,01% 23.659,61
4 Pek. Pasang Stop Kontak 1,00 Bh Q.2 3 7.760,00 3 7.760,00 56,38% 0,01% 21.288,61
5 Pas. Lampu TL 2x18 watt + dudukan Removable Mounting (RM ) 4,00 Bh Q.7 5 32.145,00 2 .128.580,00 45,35% 0,30% 965.308,98
6 Pas. Lampu Downligt 4" + LED 9 Watt 2,00 Bh Q.8 1 71.735,00 3 43.470,00 50,84% 0,06% 174.620,42
Sub. Total Pekerjaan IX 4.136.343,00 0,83% 2.645.007,51
X PEKERJAAN PERLENGKAPAN DAN ACSESORIES
1 Pek. Pasang Prasasti Granit Uk. P. 30 Cm L. 20 Cm 1,00 Bh - 7 50.000,00 7 50.000,00 100,00% 0,24% 750.000,00
Sub. Total Pekerjaan X 7 50.000,00 0,24% 7 50.000,00
JUMLAH B 309.212.771,86 75,38% 239.093.873,18
JUMLAH TOTAL PEKERJAAN (A+B) 317.189.589,86 77,80% 246.771.952,44