REKAPITULASI BILL OF QUANTITY (BoQ)
PROGRAM : PENGELOLAAN PENDIDIKAN
KEGIATAN : PENGELOLAAN PENDIDIKAN SEKOLAH MENENGAH PERTAMA
SUB KEGIATAN : PEMBANGUNAN 1 RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU UPTD SMP NEGERI 1 GABUSWETAN
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SMP NEGERI 1 GABUSWETAN
JUMLAH TKDN JUMLAH BIAYA TKDN
NO. URAIAN PEKERJAAN
(RP.) (%) (RP.)
A PEKERJAAN PERSIAPAN 12.012.039,80 3,69% 11.696.432,85
JUMLAH A 12.012.039,80 3,69% 11.696.432,85
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
LANTAI 2
II PEKERJAAN PASANGAN 49.528.867,55 15,47% 49.073.349,43
II PEKERJAAN BETON K. 175 SITE MIX 34.238.657,91 8,64% 27.414.435,56
III PEKERJAAN KUSEN 29.966.179,28 5,48% 17.375.746,56
IV PEKERJAAN PENUTUP ATAP 88.585.982,76 20,29% 64.348.659,39
V PEKERJAAN PLAFOND 49.125.592,02 9,46% 38.617.809,51
VI PEKERJAAN PENUTUP LANTAI DAN DINDING 34.485.415,20 8,36% 26.511.623,58
VII PEKERJAAN PENGECATAN 11.405.352,34 2,18% 6.918.801,08
VIII PEKERJAAN LISTRIK DAN MEKANIKAL 2.841.759,00 0,66% 2.082.559,74
IX PEKERJAAN PERLENGKAPAN DAN ACSESORIES 5.000.000,00 1,47% 4.667.698,71
JUMLAH B 305.177.806,06 72,01% 237.010.683,56
a. JUMLAH TOTAL (A+B) 317.189.845,86 75,70% 2 48.707.116,41
b. PPN 11% (a x 11%) 34.890.883,04 2 7.357.782,80
c. JUMLAH TOTAL (a+b) 352.080.728,90 2 76.064.899,21
b. DIBULATKAN 352.080.000,00 2 76.064.000,00
TERBILANG : Tiga Ratus Lima Puluh Dua Juta Delapan Puluh Ribu Rupiah
Diperiksa, Dibuat,
Pejabat Pelaksana Teknis Kegiatan Penawar
Dinas Pendidikan Dan Kebudayaan PT/CV ….............
Kabupaten Indramayu
AGUS SUMARDJO, S.IP ….......................
NIP. 19770830 200901 1 003 Direktur
Disetujui,
Pejabat Pembuat Komitmen
Dinas Pendidikan Dan Kebudayaan
Bill Of Quantity (BoQ)
PROGRAM : PENGELOLAAN PENDIDIKAN
KEGIATAN : PENGELOLAAN PENDIDIKAN SEKOLAH MENENGAH PERTAMA
SUB KEGIATAN : PEMBANGUNAN 1 RUANG KELAS BARU
PEKERJAAN : PEMBANGUNAN 1 RUANG KELAS BARU UPTD SMP NEGERI 1 GABUSWETAN
SUMBER DANA : DANA ALOKASI UMUM (DAU) TAHUN 2025
LOKASI : UPTD SMP NEGERI 1 GABUSWETAN
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 8 9 10
A PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Kegiatan Digital Printing 1,00 Bh A.5 368.986,00 368.986,00 98,97% 0,12% 365.170,85
2 Pek. Pas. Stegger dengan bambu 12,60 M2 A.7 469.803,00 5.919.517,80 99,44% 1,86% 5.886.625,99
3 Biaya Administrasi Pelaporan & Dokumentasi 1,00 Ls - 2.900.000,00 2.900.000,00 100,00% 0,91% 2.900.000,00
4 Pengadaan Air + Listrik Selama Pekerjaan 1,00 Ls - 500.000,00 500.000,00 100,00% 0,16% 500.000,00
5 Pembersihan dan Perapihan selesai pekerjaan 1,00 Ls - 500.000,00 500.000,00 100,00% 0,16% 500.000,00
6 Biaya Penyelenggaraan Sistem Manajemen Keselamatan
dan kesehatan kerja (SMK3)
a Alat Pelindung Kerja dan pelindungan diri
- Topi Pelindung (Safety Helmet) 10,00 Bh - 7 5.000,00 750.000,00 72,11% 0,17% 540.825,00
- Rompi Keselamatan ( Safety Vest) 10,00 Bh - 2 5.000,00 250.000,00 72,11% 0,06% 180.275,00
b Rambu - rambu
- Rambu Petunjuk 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
- Rambu Larangan 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
- Rambu Peringatan 1,00 Bh - 7 5.000,00 75.000,00 100,00% 0,02% 75.000,00
c BPJS Ketenagakerjaan dan Kesehatan Kerja 1,00 Ls - 598.536,00 598.536,00 100,00% 0,19% 598.536,00
JUMLAH PEKERJAAN A 12.012.039,80 3,69% 11.696.432,85
B PEKERJAAN KONSTRUKSI
PEMBANGUNAN 1 RUANG KELAS BARU (RKB)
LANTAI 2
II PEKERJAAN PASANGAN
1 Pek. Pas. 1/2 bata 1 Pc : 5 Psr 116,61 M2 D.3.2 169.333,00 19.745.921,13 99,26% 6,18% 19.599.707,15
2 Pek. Plesteran 1 Pc : 5 Psr 226,34 M2 E.3.2 80.354,00 18.187.324,36 98,85% 5,67% 17.977.946,16
3 Pek. Acian Dinding 226,34 M2 E.6.2 50.259,00 11.375.622,06 99,12% 3,55% 11.275.696,12
4 Pek. Profil Kolom 4,00 Bh - 55.000,00 220.000,00 100,00% 0,07% 220.000,00
Sub. Total Pekerjaan II 49.528.867,55 15,47% 49.073.349,43
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 8 9 10
II PEKERJAAN BETON K. 175 SITE MIX
1 Pek. Pasang Kolom 20/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 1 ,12 M3 G.2.2 1.318.907,00 1 .477.175,84 98,07% 0,46% 1.448.675,21
- Besi beton terpasang U-24 1 86,67 Kg G.25.2 1 9.597,00 3 .658.171,99 57,66% 0,67% 2.109.348,91
- Begisting Papan Terentang 1 9,60 M2 G.23.2 204.730,00 4 .012.708,00 96,14% 1,22% 3.857.907,64
2 Pek. Pasang Kolom Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,39 M3 G.2.2 1.318.907,00 5 14.373,73 98,07% 0,16% 504.449,40
- Besi beton terpasang U-24 6 5,00 Kg G.25 1 9.597,00 1 .273.805,00 57,66% 0,23% 734.492,31
- Begisting Papan Terentang 9 ,10 M2 G.23 204.730,00 1 .863.043,00 96,14% 0,56% 1.791.171,40
3 Pek. Pasang Kolom Praktis 12/12 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,10 M3 G.2.2 1.318.907,00 1 31.890,70 98,07% 0,04% 129.346,00
- Besi beton terpasang U-24 1 6,80 Kg G.25.2 1 9.597,00 3 29.229,60 57,66% 0,06% 189.838,01
- Begisting Papan Terentang 1 ,68 M2 G.23.2 204.730,00 3 43.946,40 96,14% 0,10% 330.677,80
3 Pek. Pasang Kolom Praktis Pengaman Selasar 12/12 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,08 M3 G.2.2 1.318.907,00 1 05.512,56 98,07% 0,03% 103.476,80
- Besi beton terpasang U-24 1 3,20 Kg G.25.2 1 9.597,00 2 58.680,40 57,66% 0,05% 149.158,44
- Begisting Papan Terentang 1 ,32 M2 G.23.2 204.730,00 2 70.243,60 96,14% 0,08% 259.818,27
4 Pek. Pasang Ring Balok 15/20 (166.67 Kg/m3)
- Beton Site Mix K. 175 0 ,96 M3 G.2.2 1.318.907,00 1 .266.150,72 98,07% 0,39% 1.241.721,61
- Besi beton terpasang U-24 1 60,00 Kg G.25.2 1 9.597,00 3 .135.520,00 57,66% 0,57% 1.807.981,07
- Begisting Papan Terentang 8 ,96 M2 G.23.2 204.730,00 1 .834.380,80 96,14% 0,56% 1.763.614,92
5 Pek. Pasang Balok Liufel 12/15 Cm (216,38 Kg/m3)
- Beton Site Mix K. 175 0 ,32 M3 G.2.2 1.318.907,00 4 22.050,24 98,07% 0,13% 413.907,20
- Besi beton terpasang U-24 7 0,11 Kg G.25.2 1 9.597,00 1 .373.945,67 57,66% 0,25% 792.234,71
- Begisting Papan Terentang 7 ,56 M2 G.23.2 204.730,00 1 .547.758,80 96,14% 0,47% 1.488.050,09
6 Pek. Pasang Balok Selasar 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,41 M3 G.2.2 1.318.907,00 540.751,87 98,07% 0,17% 530.318,60
- Besi beton terpasang U-24 6 7,50 Kg G.25.2 1 9.597,00 1.322.797,50 57,66% 0,24% 762.742,01
- Begisting Papan Terentang 1 0,13 M2 G.23.2 204.730,00 2.073.914,90 96,14% 0,63% 1.993.908,39
7 Pek. Pasang Balok Konsol 15/20 (166.74 Kg/m3)
- Beton Site Mix K. 175 0 ,18 M3 G.2.2 1.318.907,00 237.403,26 98,07% 0,07% 232.822,80
- Besi beton terpasang U-24 3 0,80 Kg G.25.2 1 9.597,00 603.587,60 57,66% 0,11% 348.036,36
- Begisting Papan Terentang 4 ,84 M2 G.23.2 204.730,00 990.893,20 96,14% 0,30% 952.666,99
8 Pek. Pasang Balok pengaman selasar 12/12 Cm (308.25 Kg/m3)
- Beton Site Mix K. 175 0 ,24 M3 G.2.2 1.318.907,00 316.537,68 98,07% 0,10% 310.430,40
- Besi beton terpasang U-24 7 5,46 Kg G.25.2 1 9.597,00 1.478.789,62 57,66% 0,27% 852.689,07
- Begisting Papan Terentang 4 ,08 M2 G.23.2 204.730,00 835.298,40 96,14% 0,25% 803.074,65
9 Pek. Pasang Balok ampig 12/12 Cm (308.25 Kg/m3)
- Beton Site Mix K. 175 0 ,19 M3 G.2.2 1.318.907,00 250.592,33 98,07% 0,08% 245.757,40
- Besi beton terpasang U-24 5 7,70 Kg G.25.2 1 9.597,00 1.130.746,90 57,66% 0,21% 652.003,17
- Begisting Papan Terentang 3 ,12 M2 G.23.2 204.730,00 638.757,60 96,14% 0,19% 614.115,91
Sub. Total Pekerjaan II 34.238.657,91 0,09 27.414.435,56
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 8 9 10
III PEKERJAAN KUSEN
1 Pek. Kusen + Pintu Steel Door Mother and Son + BV dan Acsesoris Type P1
- Pintu Steel Door + Acsesories (Pabrikasi) 1,00 Unit F.27.Rob.1.2 1 0.657.540,00 1 0.657.540,00 50,18% 1,69% 5.347.481,13
2 Pek. Pasang Kusen + Jendela Alumunium type J1 (4 Unit)
- Frame Kusen Alumunium 4" Warna Putih 53,36 M' F.6.2 185.767,00 9 .912.527,12 62,63% 1,96% 6.208.147,25
- Daun Jendela + Engsel Casment + Kaca polos 5 mm 8,00 Unit F.28.2 774.440,00 6 .195.520,00 60,61% 1,18% 3.755.334,01
- Pasang Kaca 5 mm 4,40 M2 L.8.2 202.010,00 8 88.844,00 61,20% 0,17% 543.940,71
3 Pek. Pasang Kusen Alumunium type BV1 (1 Unit)
- Frame Kusen Alumunium 4" Warna Putih 7,48 M' F.6.2 185.767,00 1 .389.537,16 62,63% 0,27% 870.257,52
- Pasang Kaca 5 mm 1,10 M2 L.8.2 202.010,00 2 22.211,00 100,00% 0,07% 222.211,00
4 Pek. Pasang Jalusi Ampig Kayu Kelas Kuat II 2,00 Unit - 350.000,00 7 00.000,00 61,20% 0,14% 428.374,94
Sub. Total Pekerjaan III 29.966.179,28 0,05 17.375.746,56
IV PEKERJAAN PENUTUP ATAP
1 Pek. Kuda-kuda + rangka atap baja ringan (Zincallume) 217,98 M2 H.18.2 219.335,00 4 7.810.643,30 78,02% 11,76% 37.303.261,00
2 Pek. Pasang Atap Genteng Metal Berpasir 217,98 M2 H.30.2 153.112,00 3 3.375.353,76 65,00% 6,84% 21.695.323,70
3 Pek. Pasang Nok Atap Metal Berpasir 17,30 M' H.54.2 129.389,00 2 .238.429,70 73,22% 0,52% 1.638.947,19
4 Pek. Pasang Lisplank GRC Tumpangsari (1/20 + 1/10) Cm 47,20 M' H.64.2 109.355,00 5 .161.556,00 71,90% 1,17% 3.711.127,51
Sub. Total Pekerjaan IV 88.585.982,76 20,29% 64.348.659,39
V PEKERJAAN PLAFOND
1 Pek. Pasang Rangka Plafond galvalume modul 60x60 Cm 111,06 M2 I.23.2 8 9.218,00 9 .908.551,08 69,74% 2,18% 6.910.063,17
2 Pek. Pasang Plafond PVC Motif 111,06 M2 I.16.2 199.724,00 2 2.181.347,44 90,04% 6,30% 19.971.100,40
3 Pek. Pasang List Plafond PVC 71,20 M' I.29.2 4 9.302,00 3 .510.302,40 89,31% 0,99% 3.135.167,33
4 Pek. Pasang Rangka Plafond galvalume Toilet modul 60x60 Cm 69,95 M2 I.23.2 8 9.218,00 6 .240.799,10 69,74% 1,37% 4.352.232,30
5 Pek. Pasang Plafond GRC Toilet + Ruang Kelas Lama 96,50 M2 I.11.2 7 5.488,00 7 .284.592,00 58,33% 1,34% 4.249.246,32
Sub. Total Pekerjaan V 49.125.592,02 9,46% 38.617.809,51
VI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Pasang Lantai Granit 60x60 Cm 90,00 M2 M.14.2 348.114,00 3 1.330.260,00 75,78% 7,48% 23.740.724,98
2 Pek. Pasang Keramik Kolom motif batu alam 20x40 cm t. 1,6 m 9,60 M2 N.3.2 328.662,00 3 .155.155,20 87,82% 0,87% 2.770.898,60
Sub. Total Pekerjaan VI 34.485.415,20 8,36% 26.511.623,58
VII PEKERJAAN PENGECATAN
1 Pek. Cat dinding interior 92,24 M2 P.12.2 4 3.842,00 4 .043.986,08 61,44% 0,78% 2.484.626,45
2 Pek. Cat dinding exterior Weather Shield Dulux 134,09 M2 P.13.2 5 0.290,00 6 .743.386,10 61,44% 1,31% 4.143.138,75
3 Pek. Cat Listplank 9,44 M2 P.4.2 6 5.464,00 6 17.980,16 47,09% 0,09% 291.035,88
Sub. Total Pekerjaan VII 11.405.352,34 2,18% 6.918.801,08
VIII PEKERJAAN LISTRIK DAN MEKANIKAL
1 Pek. Pasang Instalasi Titik Penerangan dan Stop Kontak 7,00 Titik Q.1.2 228.631,00 1 .600.417,00 92,85% 0,47% 1.486.046,97
2 Pek. Pasang Saklar Tunggal 1,00 Bh Q.3.2 3 8.158,00 3 8.158,00 57,07% 0,01% 21.776,37
3 Pek. Pasang Saklar Double 1,00 Bh Q.4.2 4 1.148,00 4 1.148,00 59,40% 0,01% 24.442,52
4 Pek. Pasang Stop Kontak 1,00 Bh Q.2.2 3 9.078,00 3 9.078,00 56,38% 0,01% 22.031,68
5 Pas. Lampu TL 2x18 watt + dudukan Removable Mounting (RM) 4,00 Bh Q.7.2 194.213,00 7 76.852,00 45,35% 0,11% 352.301,63
6 Pas. Lampu Downligt 4" + LED 9 Watt 2,00 Bh Q.8.2 173.053,00 3 46.106,00 50,84% 0,06% 175.960,56
Sub. Total Pekerjaan VIII 2.841.759,00 0,66% 2.082.559,74
HARGA JUMLAH
NILAI JUMLAH BIAYA
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN TOTAL % TKDN
TKDN TKDN (RP)
(Rp.) (3 x 6)
1 2 3 4 5 6 7 8 9 10
IX PEKERJAAN PERLENGKAPAN DAN ACSESORIES
1 Pek. Pasang Pipa Stainless 2" pengaman Selasar 15,50 M' Ls 300.000,00 4 .650.000,00 92,85% 1,36% 4.317.698,71
2 Pek. Pasang Prasasti Granit Uk. P. 40 Cm L. 30 Cm 1,00 Bh - 3 50.000,00 3 50.000,00 100,00% 0,11% 350.000,00
Sub. Total Pekerjaan IX 5 .000.000,00 1,47% 4 .667.698,71
JUMLAH B 305.177.806,06 72,01% 237.010.683,56
JUMLAH TOTAL PEKERJAAN (A+B) 317.189.845,86 75,70% 248.707.116,41
Dibuat,
Konsultan Perencana
PT/CV ….............
….......................
Direktur