| 0935762401711000 | Rp 900,000,000 | |
| 0940496532711000 | Rp 930,000,000 | |
| 0417216058711000 | Rp 950,000,009 | |
| 0954729521711000 | - | |
| 0729476150711000 | Rp 994,500,000 | |
| 0030626956731000 | - | |
| 0015767080711000 | - | |
| 0028234748731000 | - | |
| 0538078049711000 | - | |
| 0839447471731000 | - | |
| 0024376618711000 | - | |
| 0836201400735000 | - | |
| 0965493554711000 | - | |
| 0942446899711000 | - | |
| 0842968182711000 | - | |
| 0854818507711000 | - | |
| 0842370199711000 | - | |
CV Putera Jaya Perkasa | 0808426019731000 | - |
| 0032299943711000 | - | |
| 0756781670711000 | - | |
| 0530329663732000 | - | |
PT Gempita Cahaya Persada | 04*8**0****11**0 | - |
| 0029783875711000 | - | |
| 0940307606732000 | - | |
| 0710197096711000 | - | |
| 0847817954711000 | - | |
| 0025387887711000 | - | |
| 0942812017711000 | - |
PEMERINTAH KABUPATEN KAPUAS
BADAN KEUANGAN DAN
ASET DAERAH
Jalan Pemuda Km. 5,5 Kode Pos 73515 Kuala Kapuas
URAIAN SINGKAT PEKERJAAN
PEMELIHARAAN BMD (RENOVASI GEDUNG KANTOR)
Lokasi kegiatan pengadaan jasa kontruksi Pemeliharan BMD (Renovasi Gedung Kantor), berada pada
Kabupaten Kapuas Propinsi Kalimantan Tengah
MAKSUD DAN TUJUAN
1) Maksud dari kegiatan pembangunan ini adalah untuk memperbaiki bangunan Gedung kantor
yang rusak.
2) Tujuan dari kegiatan adalah terciptanya bangunan kantor yang representatif.
SUMBER PENDANAAN
Kegiatan ini dibiayai dari sumber pendanaan :
- Sumber Dana berasal dari APBD Kabupaten Kapuas yang terdapat pada DPA Badan Pengelola
Keuangan dan Aset Daerah Kabupaten Kapuas
- Nilai Pagu Anggaran Rp. 1.000.000.000,- ( Satu Milyar Rupiah).
- Nilai HPS Rp. 999.980.000,- ( Sembilan Ratus Sembilan Puluh Sembilan Juta Sembilan Ratus
Delapan Puluh Ribu Rupiah).
NAMA DAN ORGANISASI PEJABAT PEMBUAT KOMITMEN
Pejabat Pembuat Komitmen (PPK) adalah pejabat struktural pada Instansi Badan Pengelola Keuangan dan
Aset Kabupaten Kapuas yang bertanggung jawab terhadap kegiatan, yaitu:
a. Pejabat Pembuat Komitmen : Drs. YAN HENDRI ALE, MT
(PPK)
b. K/L/D/I : Kabupaten Kapuas
c. SKPD : Badan Pengelola Keuangan dan Aset Daerah Kabupaten Kapuas
d. Alamat : Jalan Pemuda Kuala Kapuas
LINGKUP PEKERJAAN
No. Analisa Volume / Sat Harga Satuan Jumlah Harga
I PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan - 1.00 Ls Rp. -
2 SMK3 - 1.00 Ls Rp. Rp. Rp. -
JUMLAH BIAYA PEKERJAAN I Rp. -
II - 1.00 Keg Rp. Rp. -
A GEDUNG KANTOR BKAD
1 PEKERJAAN BONGKARAN
Pekerjaan Bongkaran Atap Gedung BKAD meliputi :
- Bongkaran Seluruh Genteng Metal
- Bongkatran Rangka Atap Dan Kuda Kuda Pelana Tumpang Bagian Atas
- Bongkaran Tawing layar dan Listplank
- Bongkara Seluruh Plafon
- Bongkaran Toilet Umum, Toilet Ruang Kepala Badan Dan Gudang Aset
JUMLAH A Rp. -
B
B.1 RUANG KEPALA BADAN
0.36
1 PEKERJAAN LANTAI DAN DINDING A 4.1.1.4 M3 Rp. Rp. -
2.64
2 Rabat Beton Lantai ex. Toilet Umum A 4.4.3.36.b M2 Rp. Rp. -
6.45
3 Keramik Lantai 40 x 40 Polos ex. Toilet Umum A 4.4.19a M2 Rp. Rp. -
12.90
4 Pas. Dinding Bata Ringan Toilet Umum dan Toilet R. Kepala Badan Plesteran 1 : 4 A 4.4.2.4 M2 Rp. Rp. -
12.90
5 Acian dan benangan dinding - M2 Rp. Rp. -
49.31
6 Pas. Dinding Plywood Lapis HPL + List Aluminium - M2 Rp. Rp. -
8.15
7 Back Drop Dinding Kepala Badan - M2 Rp. Rp. -
20.33
8 Pasang Lapis Lantai Parkeet A.4.4.3.59.a M2 Rp. Rp. -
7.50
9 Kusen Pintu Aluminium KM/WC - M' Rp. Rp. -
10 Pintu Kaca Rayben Rangka Aluminium + Accesoris - 1.00 Bh Rp. Rp. -
11 Kusen Jendela Aluminium ( 45 x 170 ) - 4.30 M' Rp. Rp. -
12 Jendela Kaca Rangka Aluminium ( Uk. 37 x 162)+ Accesoris - 1.00 Bh Rp. Rp. -
JUMLAH B.1 Rp. -
B.2 TOILET RUANG KEPALA BADAN
1 Pasang Closet Duduk setara TOTO -
1.00
S et Rp. Rp. -
2 Handshower sekualitas Toto -
1.00
Set Rp. Rp. -
3 Meja Beton Wastafel Finishing Granit Roman - 1.00 Ls Rp. Rp. -
4 Wastafel sekualitas Toto - 1.00 Set Rp. Rp. -
5 Kran skualitas Toto - 1.00 Set Rp. Rp. -
6 Fitting and supporting + Pemipaan - 1.00 Ls Rp. Rp. -
7 Kaca Cermin Uk. 60 x 120, tebal 3 mm + accesoris - 1.00 Bh Rp. Rp. -
JUMLAH B.2 Rp. -
JUMLAH TOTAL B Rp. -
C RUANG KEPALA BIDANG
A.4.4.3.60 52.11
1 Lapis Wallpaper Ruang Kepala Bidang Aset M2 Rp. Rp. -
A.4.4.3.60 45.23
2 Lapis Wallpaper Ruang Kepala Bidang Anggaran M2 Rp. Rp. -
3 Lapis Wallpaper Ruang Kepala Bidang Perbendaharaan A.4.4.3.60 45.69 M2 Rp. Rp. -
4 Lapis Wallpaper Ruang Kepala Bidang Akuntansi A.4.4.3.60 38.79 M2 Rp. Rp. -
5 Lapis Wallpaper Ruang Keuangan A.4.4.3.60 37.79 M2 Rp. Rp. -
JUMLAH C Rp. -
D RUANG KASI PERBENDAHARAAN
1 Dinding Partisi Jalusi Kayu Banuas 3/10 Finishing Duco + Rangka + Accesoris Di - 15.13 M2 Rp. -
2 Pasang Pintu Kaca Rangka Aluminium ( Geser + Rell ) dan Accesoris - 1.00 Set Rp. Rp. Rp. -
JUMLAH D Rp. -
E REHAB ATAP DAN PLAFON
E.1 RAHAB ATAP GEDUNG BKAD
1 Pas. Rangka Atap Reng Tasso ( Tambahan ) - 256.29 M2 Rp. Rp. -
2 Pasang Genteng Metal Berpasir sekualitas Arista Roof 2 x 4 tebal 0,3 Talang Seng A.4.5.2.32 913.82 M2 Rp. Rp. -
3 Plat 27.00 M' Rp. Rp. -
4 Nok Atap Metal A.4.5.2.36a 94.84 M' Rp. Rp. -
5 Pas. Listplank Kalsieplank - 124.56 M' Rp. Rp. -
JUMLAH E.1 Rp. -
E.2 REHAB PLAFON
1 Rehab Rangka Plafon Dalam dan Luar 10% x Luasan A.4.2.1.21 76.53 M2 Rp. Rp. -
2 Rangka Hollow Drop Ceiling A.4.2.1.21 150.48 M2 Rp. Rp. -
3 Pasang Plafon Gypsum A.4.5.1.7.a 765.25 M2 Rp. Rp. -
4 Drop Ceiling Gypsum -
Teras
A.4.5.1.7.b 24.80 M' Rp. Rp. -
- Ruang Pelayanan A.4.5.1.7.b 30.80 M' Rp. Rp. -
- Ruang Kerja A.4.5.1.7.b 65.16 M' Rp. Rp. -
- Ruang Aset Dan Kabid Aset A.4.5.1.7.b 34.00 M' Rp. Rp. -
- Aula Rapat A.4.5.1.7.b 26.80 M' Rp. Rp. -
- Ruang Kepala Badan A.4.5.1.7.b 12.40 M' Rp. Rp. -
- Ruang Kabid Anggaran A.4.5.1.7.b 9.60 M' Rp. Rp. -
- Ruang Kabid Perbend A.4.5.1.7.b 9.60 M' Rp. Rp. -
- Ruang Kepala Bidang Akuntansi A.4.5.1.7.b 9.60 M' Rp. Rp. -
- Ruang Keuangan A.4.5.1.7.b 9.60 M' Rp. Rp. -
- Ruang Sekretaris A.4.5.1.7.b 9.48 M' Rp. Rp. -
- Pantry A.4.5.1.7.b 17.60 M' Rp. Rp. -
5 List Profil Gypsum - 285.38 M' Rp. Rp. -
JUMLAH E.2 Rp. -
JUMLAH TOTAL E Rp. -
F
PENGECATAN
1 Pengecatan Plafon Luar Dan Dalam A.4.7.1.10 804.17 M2 Rp. Rp. -
2 Pengecatan Listplank A.4.7.1.10 24.91 M2 Rp. Rp. -
3 Pengecatan dinding KM/WC R. Kepala Badan A.4.7.1.10 9.55 M2 Rp. Rp. -
JUMLAH F Rp. -
G
PEKERJAAN KERAMIK LANTAI TERAS
1 Bongkaran Keramik Lantai Teras Samping Kiri Kanan Depan Gedung - 1.00 Ls Rp. Rp. -
2 Rabat Beton Lantai Penebalan Lantai A 4.1.1.4 8.99 M3 Rp. Rp. -
3 Pasang Keramik Roman 60 x 60 ( Permukaan Motif Kasar ) A 4.4.3.36.d 59.95 M2 Rp. Rp. -
JUMLAH G Rp. -
H
PEKERJAAN BATU ALAM DINDING
1 Pasang Batu alam Dinding Depan Ruang Bidang Aset - 14.66 M2 -
2 Coating Batu Alam Seluruh Dinding Depan Gedung BKAD - 36.32 M2 Rp. Rp. Rp. Rp. -
JUMLAH H Rp. -
JUMLAH BIAYA PEKERJAAN II ( A + B + C + D + E + F + G + H ) Rp. -
III PEKERJAAN GUDANG ASET DAN TOILET UMUM
GUDANG ASET DAN TOILET UMUM
A PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pasang Bouwplank A 2.2.1.4 49.00 M' Rp. Rp. -
JUMLAH A Rp. -
B
PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Kali 61.44 M3 Rp. Rp. -
2 Pengadaan Cerucuk Galam Pondasi Uk. 8 - 10 Panjang 2 M' A 2.3.1.1 Ls 480.00 Btg Rp. Rp. -
3 Pemancangan Cerucuk Ls 960.00 M' Rp. Rp. -
4 Urugan Kembali Tanah A 2.3.1.9 20.48 M3 Rp. Rp. -
5 Urugan Pasir Bawah Lantai A 2.3.1.11 13.00 M3 Rp. Rp. -
JUMLAH B Rp. -
C
PEKERJAAN PONDASI BETON DAN PASANGAN
1 Rabat Beton Lantai Kerja tebal 10 Cm
A 4.1.1.4 7.68
M3 Rp. Rp. -
2 Pondasi Batu Kali Camp. 1 : 4
A 3.2 .1.2 33.60
M3 Rp. Rp. -
3 Pondasi Rollag Selasar Pek. Sloof
- 30.00
M' Rp. Rp. -
4 15/25 :
A 4.1.1.17 A 108.21
Pembesian ( tulangan pokok Besi 12 ; cincin Besi 6 ) Kg Rp. Rp. -
4.1.1.5 0.92
Cor Beton K-175 M3 Rp. Rp. -
A. 4.1.1.22 7.32
Bekisting M2 Rp. Rp. -
5 Pek. Kolom 15 x 15 :
A 4.1.1.17 A 141.95
Pembesian ( tula ngan pokok Besi 12 ; cincin Besi 6 )
4.1.1.5 0.62
Kg Rp. Rp. -
Cor Beton K-175
A. 4.1.1.22 16.51
M3 Rp. Rp. -
Bekisting M2 Rp. Rp. -
6 Pek. Ring balk 15/20 :
A 4.1.1.17 A 119.77
Pembesian ( tulangan pokok Besi 10 ; cincin Besi 6 ) Kg Rp. Rp. -
4.1.1.5 0.81
Cor Beton K-175 M3 Rp. Rp. -
Bekisting A. 4.1.1.22
12.15
M2 Rp. Rp. -
7 Cor Beton Lantai K-175 A 4.1.1.5 9.30 M3 Rp. Rp. -
Pembesian Tunggal dia. 10 jarak 20 A 4.1.1.17 381.92 Kg Rp. Rp. -
Bekisting A. 4.1.1.22 A 62.00 M2 Rp. Rp. -
8 Pas. Dinding bata ringan 4.4.19a 159.95 M2 Rp. Rp. -
Plesteran 1 : 4 A 4.4.2.4 319.89 M2 Rp. Rp. -
Acian dan Benangan - 319.89 M2 Rp. Rp. -
JUMLAH C Rp. -
D PEKERJAAN KERAMIK
1 Pas. Keramik lantai 40 x 40 (Gudang Arsip + Selasar Dan Los Toilet Umum + Sel A 4.4.3.36.b 50.00 M2 Rp. Rp. -
2 Pas. Keramik Lantai Dalam Toliet 25 x 25 A 4.4.3.36.a 12.00 M2 Rp. Rp. -
3 Pas. Keramik Dinding Toilet 25 x 40 A 4.4.3.39 50.40 M2 Rp. Rp. -
JUMLAH D Rp. -
E PEK. KUSEN PINTU JENDELA
28.20
1 Kusen Pintu Jendela Kayu Ulin 5/10 Toilet Umum + Pasang - M' Rp. Rp. -
6.00
2 Pintu Panil Kayu Ulin + Pasang - Bh Rp. Rp. -
18.00
3 Engsel Pintu 4" + Pasang - Psg Rp. Rp. -
6.00
4 Kunci Pintu + Handel + Pasang - Set Rp. Rp. -
15.50
5 Kusen Pintu Jendela Aluminium Gudang Arsip - M' Rp. Rp. -
5.00
6 Bouvenlitch Kaca Mati rangka Aluminium Gudang arsip Uk. 185 x 45 - Bh Rp. Rp. -
7 Bouvenlitch Kaca Mati rangka Aluminium Toilet Umum Uk. 65 x 45 - 4.00 Bh Rp. Rp. -
8 Pintu Kaca Doubel Rangka Aluminium Gudang Arsip + Accesoris + Pemasangan - 1.00 unit Rp. Rp. -
9 Pas. Jendela Kaca Rangka Aluminium + Kacamati + Accesoris - 2.00 Bh Rp. Rp. -
JUMLAH E Rp. -
F
1 PEKERJAAN ATAP DAN PLAFON U - 109.91 M2 Rp. Rp. -
2 Rangka Atap + Kuda Baja Ringan Gudang Arsip + Selasar Penghubung + Toilet Pasang A.4.5.2.32
109.91
M2 Rp. Rp. -
3 Genteng Metal Berpasir sekualitas Arista Roof 2 x 4 tebal 0,3 Talang Seng Plat -
7.25
M' Rp. Rp. -
4 Nok Atap Metal A.4.5.2.36a
24.57
M' Rp. Rp. -
5 Pas. Listplank Kalsieplank - 40.08 M' Rp. Rp. -
6 Rangka Plafon Besi Hollow A.4.2.1.21 52.00 M2 Rp. Rp. -
7 Rangka Plafon Besi Hollow Selasar Penghubung Depan Gudang Arsip A.4.2.1.21 11.36 M2 Rp. Rp. -
8 Plafon Gypsum Board A.4.5.1.7.a 63.36 M2 Rp. Rp. -
9 List Gypsum - 83.68 M' Rp. Rp. -
JUMLAH F Rp. -
G PEK. MEKANIKAL ELEKTRIKAL
A GUDANG ARSIP 7.00
1 Instalasi Titik Lampu - 4.00 Ttk Rp. Rp. -
2 Instalalasi saklaar - 7.00 Ttk Rp. Rp. -
3 Fitting Lampu Brocco - 1.00 Bh Rp. Rp. -
4 Saklaar Tunggal Setara Brocco - Bh Rp. Rp. -
3.00
5 Saklaar Ganda Setara Brocco - Bh Rp. Rp. -
2.00
6 Stop Kontak Setara Broco - Bh Rp. Rp. -
7.00
7 Lampu SL setara Phillip's 20 Watt - Bh Rp. Rp. -
B TOILET UMUM
7.00
1 Instalasi Titik Lampu - Ttk Rp. Rp. -
6.00
2 Instalalasi saklaar - Ttk Rp. Rp. -
7.00
3 Fitting Lampu Brocco - Bh Rp. Rp. -
4.00
4 Saklaar Tunggal Setara Brocco - Bh Rp. Rp. -
5 Saklaar Ganda Setara Brocco - 2.00 Bh Rp. Rp. -
6 Stop Kontak Setara Broco - 2.00 Bh Rp. Rp. -
7 Lampu SL setara Phillip's 20 Watt - 7.00 Bh Rp. Rp. -
JUMLAH G Rp. -
H
PEKERJAAN PENGECATAN
Cat Tembok Dinding dan Plafon setara Matex A.4.7.1.10 383.25 M2 -
Cat Kilap Kusen, Pintu Dan Jendela Toilet Umum - 1.00 Pkt Rp. Rp. Rp. Rp. -
JUMLAH H Rp. -
PEKERJAAN SANITASI
I
2.00
Pasang Closet Duduk Standar + Jet Shower
1 - Rp. Rp. -
2.00
Pasang Closet Jongkok Standar
2 - Rp. Rp. -
Pasang Bak Air Fiberglass
2.00
3
Pasang Kran Air 1/2 Inch
-
4.00
Rp. Rp. -
4
Pasang Wastafel + Meja Beton Finishing Keramik Polos
-
2.00
Uni t Rp. Rp. -
5 - Bh Rp. Rp. -
Pemipaan Air Bersih 1/2 Inch + Accesoris 35.00
6 - Bh Rp. Rp. -
Pemipaan Air Kotor 2 Inc + Accesoris 20.00
7 - Bh Rp. Rp. -
Pemipaan Air Kotor 4 Inc + Accesoris 20.00
8 - Unit Rp. Rp. -
9 Pas. Floor Drain - 6.00 M' Rp. Rp. -
10 Pekerjaan Septictank Buis Beton dia. 1 M sebanyak 2 susun lengkap dengan : - galian - 1.00 M' Rp. Rp. -
dan urugan kembali
M'
- Tutup Septictank Bh
- Pipa Hawa Unit
11 Sambungan Baru PDAM - 1.00 Ls Rp. Rp. -
JUMLAH I Rp. -