URAIAN SINGKAT PEKERJAAN
PROGRAM : PROGRAM PEMERINTAHAN DAN KESEJAHTERAAN RAKYAT
KEGIATAN : ADMINISTRASI TATA PEMERINTAHAN
PEKERJAAN : BELANJA MODAL PEMBANGUNAN GEDUNG KANTOR KECAMATAN TEWANG SANGALANG
GARING
LOKASI : PENDAHARA, KEC. TEWANG SANGALANG GARING
TAHUN ANGGARAN : 2025
HARGA SATUAN JUMLAH
No. ITEM PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
A PEKERJAAN ENDAHULUAN
1 Pembersihan Awal dan Akhir 1,00 keg. Ls 1.394.594,59 1.394.594,59
2 Pengukuran dan Pemasangan Patok 92,00 m' Ls 58.350,00 5.368.200,00
3 Pagar Dinding Seng Keliling 130,00 m' A. 2.2.1.2 423.600,00 55.068.000,00
4 Papan Nama Kegiatan 1,00 bh Ls 500.000,00 500.000,00
5 Bangsal Kerja 24,00 m2 Ls 289.000,00 6.936.000,00
6 Jembatan sementara+ Jalan Masuk 1,00 keg. Ls 3.500.000,00 3.500.000,00
7 Penanganan SMK 1,00 keg. Ls 3.280.000,00 3.280.000,00
SUB TOTAL (A) 76.046.794,59
B PEKERJAAN TANAH
1 Galian Tanah Pondasi Footplate 180,00 m3 A. 2.3.1.2 197.780,00 35.600.400,00
2 Urugan Kembali 56,16 m3 A. 2.3.1.9 117.410,00 6.593.745,60
3 Urugan Pasir Bawah Pondasi 7,20 m3 A. 2.3.1.11 312.820,00 2.252.304,00
4 Cerucuk Galam 2 m 256,00 btg BOW E.13a 83.897,10 21.477.657,60
SUB TOTAL (B) 65.924.107,20
C PEKERJAAN STRUKTUR BETON (BANGUNAN)
1 Lantai Kerja Bawah Pondasi f'c = 7,4 7,20 m3 A. 4.1.1.4 1.808.010,00 13.017.672,00
2 Pondasi Footplate 150x150 Beton Bertulang
a. Bekisting 180,48 m2 A. 4.1.1.20 285.440,00 51.516.211,20
b. Pembesian 1858,11 kg A. 4.1.1.17 36.180,00 67.226.353,23
c. Cor Beton f'c = 24,0 Mpa 30,82 m3 A. 4.1.1.9 2.231.490,00 68.765.595,84
3 Sloof 20x40 Beton Bertulang
a. Bekisting 158,40 m2 A. 4.1.1.21.a 149.040,00 23.607.936,00
b. Pembesian 1585,31 kg A. 4.1.1.17 36.180,00 57.356.400,02
c. Cor Beton f'c = 24,0 Mpa 15,84 m3 A. 4.1.1.9 2.231.490,00 35.346.801,60
4 Pek. Rollag Dinding 1 Bata 56,40 m2 A. 4.4.1.3 570.740,00 32.189.736,00
5 Pekerjaan Plesteran 56,40 m2 A. 4.4.2.4 126.160,00 7.115.424,00
6 Pekerjaan Cor Tumbuk Keliling Tebal 10 cm
a Bekisting 10,05 m2 A. 4.1.1.20 285.440,00 2.868.672,00
b Pembesian 294,03 kg A. 4.1.1.17 36.180,00 10.638.005,40
c Cor Beton f'c = 16,9 Mpa 6,70 m3 A. 4.1.1.6 2.134.640,00 14.302.088,00
7 Balok 30x50 Beton Bertulang
a. Pembesian 4138,40 kg A. 4.1.1.17 36.180,00 149.727.239,64
SUB TOTAL (C) 533.678.134,93