TIME SCHEDULE
NAMA PEKERJAAN = PEMASANGAN PAVING BLOK HALAMAN KANTOR DINAS PERHUBUNGAN KABUPATEN LANGKAT
TAHUN ANGGARAN = 2025
BULAN 1 BULAN 2 KET
1 2 3 4 5 6 7 8 9
NO RINCIAN KEGIATAN DAN PEKERJAAN
1 Oct 2025 8 Oct 2025 15 Oct 2025 22 Oct 2025 29 Oct 2025 5 Nov 2025 12 Nov 2025 19 Nov 2025 26 Nov 2025
7 HK 14 HK 21 HK 28 HK 35 HK 42 HK 49 HK 56 HK 60 HK
A PEKERJAAN PENDAHULUAN 1 ,430 1 ,430 - - - - - - -
B PEKERJAAN PEMASANGAN PAVING BLOCK 6 ,889 1 3,779 1 3,779 1 3,779 1 3,779 1 3,779 1 3,779 6 ,889
C PEKERJAAN LAIN-LAIN 0 ,076 0 ,076 0 ,076 0 ,076 0 ,076 0 ,076 0 ,076 0 ,076 0 ,076
RENCANA KEMAJUAN PEKERJAAN (%) 1,507 8,396 13,855 13,855 13,855 13,855 13,855 13,855 6,966
RENCANA KOMULATIF KEMAJUAN PEKERJAAN (%) 1,507 9,903 23,758 37,613 51,469 65,324 79,179 93,034 100,000