JADWAL WAKTU PELAKSANAAN
PEKERJAAN : REHABILITASI 3 UNIT RUMAH DINAS PEGAWAI KEJAKSAAN NEGERI LANGKAT
TAHUN ANGGARAN : TA. 2025
JADWAL WAKTU PELAKSANAAN PEKERJAAN (SELAMA 35 HARI KALENDER)
MASA
NO JENIS PEKERJAAN MINGGU KE-
PEMELIHARAAN
M - 1 M - 2 M - 3 M - 4 M - 5
I. PEKERJAAN PENDAHULUAN 3,426
II. PEKERJAAN PERBAIKAN PLAFOND 11,446 11,446
III. PEKERJAAN PERBAIKAN ATAP DAN DAK KANOPI BETON 2,039 2,039
PHO
IV. PEKERJAAN REHAB PINTU, JENDELA DAN PENGECATAN DINDING 11,342 11,342 11,342
180 Hari Kalender
V. PEKERJAAN KANOPI DAN PAVING BLOCK 17,790 17,790
TOTAL HARGA PEKERJAAN
Progres Rencana Mingguan (%) 14,872 13,485 13,380 29,131 29,131
Progres Rencana Kumulatif (%) 14,872 28,357 41,737 70,869 100,000 100,000| Authority | |||
|---|---|---|---|
| 29 May 2015 | Rehabilitasi Linning Sei Bingei Kel. Pekan Binjai | Rp 391,630,000 | |
| 3 July 2014 | Pembangunan Saluran Drainase Jl. Kl. Yos Sudarso Kel. Cengkeh Turi | LPSE Kota Binjai | Rp 300,000,000 |
| 29 May 2015 | Pembangunan Linning Sei Diski (Kuburan Megawati) Kel. Sumber Karya | Rp 291,630,000 | |
| 18 July 2014 | Pembangunan Parit Beton Jalan Suka Mulia Di Dusun Suka Mulia Sep. 470M Desa Lubuk Kasih Kec. Brandan Barat | Rp 250,000,000 | |
| 2 July 2024 | Pengadaan Calon Induk Dan Ketersediaan Sarana Pembudidayaan Ikan | Kota Binjai | Rp 106,040,000 |