| 0017367160202000 | Rp 1,500,000,000 | |
| 0024506685201000 | Rp 1,290,400,000 | |
| 0730500006201000 | Rp 1,532,350,000 | |
| 0965134836201000 | - | |
CV Indopuro Bangun Bersama | 00*6**2****05**0 | - |
| 0625088497205000 | Rp 1,290,400,000 | |
| 0748837366201000 | Rp 1,399,890,447 | |
| 0766300230321000 | Rp 1,290,400,000 | |
| 0026681148201000 | Rp 1,290,400,000 | |
| 0602148769201000 | Rp 1,290,400,000 | |
| 0754660348201000 | Rp 1,349,191,579 | |
| 0311911754124000 | - | |
| 0023817760202000 | Rp 1,290,400,000 | |
| 0719897951201000 | Rp 1,290,400,000 | |
| 0012300786201000 | Rp 1,290,400,000 | |
| 0717865356201000 | Rp 1,290,400,000 | |
CV Nuansa Cipta Mandiri | 09*9**9****01**0 | Rp 1,290,400,000 |
CV Pantai Barat Sumatera | 09*9**9****01**0 | Rp 1,290,016,584 |
| 0210543088443000 | Rp 1,290,400,000 | |
| 0929446540203000 | Rp 1,443,613,798 | |
CV Artha Yola Tama | 09*2**6****05**0 | - |
| 0015212921201000 | - | |
| 0939721262201000 | - | |
CV Lindo Pratama Kontraktor | 10*1**1****48**9 | - |
| 0745604322201000 | - | |
| 0750905267443000 | - | |
| 0743141285205000 | - | |
CV Nusasikerei | 10*1**1****00**1 | - |
CV Vellisa Nusa Graha | 00*9**8****01**0 | - |
CV Perintis Utama Mandiri | 00*1**9****01**0 | - |
| 0625397559205000 | - | |
| 0317509842201000 | - | |
PT Aan Jaya Baru | 0764695649201000 | - |
| 0020500351201000 | - | |
PT Bubuakat Oinan Sibau | 04*4**7****05**0 | - |
| 0626689004205000 | - | |
| 0925272437201000 | - | |
CV Rerari Tri Konstruksi | 10*0**0****19**4 | - |
CV Bima | 08*3**6****12**0 | - |
| 0749782116429000 | - | |
| 0718045784201000 | - | |
CV Tirik Pondonan Jaya | 05*2**2****05**0 | - |
| 0023223282201000 | - | |
CV Aurora Kirana | 02*4**5****05**0 | - |
| 0744879834205000 | - | |
| 0015808652201000 | - | |
| 0900844739201000 | - | |
| 0022437610201000 | - | |
| 0031469018201000 | - | |
| 0028788941201000 | - | |
CV Sopou Surung | 09*6**9****05**0 | - |
| 0016890725201000 | - | |
| 0031192818201000 | - | |
| 0028050946203000 | - | |
CV Muara Gunung | 09*6**3****01**0 | - |
CV Trigatra Aritama Konstruksi Persada | 00*9**4****01**0 | - |
| 0028385946201000 | - | |
| 0951715648201000 | - | |
| 0662994698201000 | - | |
PT Marawa Nantigo Warna | 02*9**6****05**0 | - |
| 0020455580201000 | - | |
CV Bumi Sikerei Sejahtera | 10*0**0****17**2 | - |
RINCIAN MAYOR ITEM PEKERJAAN
Sub Kegiat:anPembangunan Unit Sekolah Baru (USB)
Pekerjaan : Pembangunan Unit Sekolah Baru di SMPN 2 Pagai Utara (Lanjutan TA. 2023)
Lokasi : Guluk-guluk, Sipora Pagai Utara
Tahun : 2025
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
B. LANJUTAN BANGUNAN RUANG GURU/TU
-
PEKERJAAN BETON & DINDING -
Plesteran Semua Dinding 1 Pc : 4 Ps, Tebal 2 Cm M2 5 60,57 73.930,27 41.442.735,44
Acian Semua Dinding M2 5 60,57 37.514,11 21.029.104,47
PEKERJAAN PLAFON -
Pas. Rangka Plafond Dalam, Luar dan Pada Singok MAt3ap, K a y u 4 , 1 5 5 6x. 970 c4m.7,1 u6k,9u6ran 6 0 x 6 208 c.m624.523,04
Pas. Plafond Dalam, Luar dan Pada Singok Atap GRMC2 4 mm , u3 k2u3r,1a2n 12 0 x 2 8480.9 c5m8,, 58 28.744.420,92
-
PEKERJAAN KOZEN, PINTU DAN JENDELA -
Pas. Pintu Panil Ruangan M2 1 2,39 790.948,49 9.799.851,79
Pas. Jendela Kaca Rangka Kayu tebal 5 mm M2 1 2,41 891.538,34 11.066.130,44
Pas. Papan Ventilasi Konzen/Jalusi Kayu M2 3 3,32 406.299,96 13.539.052,16
PEKERJAAN LANTAI & KERAMIK -
Pek. Urugan Tanah di Bawah Lantai (Sisa belum dikMe3rjaka n ) 1 4,71 381.772,44 5.615.391,49
Pek. Urugan Pasir di Bawah Lantai Tbl = 5 cm M3 1 2,50 562.835,79 7.035.908,90
Pek. Cor Lantai 1 : 3 : 5 Tbl = 7 cm M3 1 7,50 1.816.495,32 31.790.753,51
Pas. Lantai Granit Warna Utk Ruangan Uk. 60 x 60M c2m Lic in 1 96,40 461.699,37 90.676.831,98
Pas. Lantai Granit Warna Utk Teras Uk. 60 x 60 cmM K2asar 4 3,50 461.699,37 20.083.922,40
Pas. Dinding Keramik KM/WC 20 x 20 cm Licin M2 3 4,44 262.781,77 9.050.204,07
-
PEKERJAAN PENGECATAN -
Pek. Cat Minyak Kayu Kusen, Pintu Panil, Rangka JMen2dela , L i3 s0t 7P,i3n8ggir P l a f o 6n3,. 6V1e7n,t2i7lasi d a n L i s 1t9 P.5la5n4k.7 D30en,3g0an Cat Minyak Platon Atau Setara Warna Marun
Pek. Cat Dinding Dengan Cat Air Catilac atau SetarMa 2Warn a C 6 r3e0m,64 38.677,47 24.391.452,17
Pek. Cat Plafond Dengan Cat Air Catilac atau SetaraM W2arn a P 3 u2ti3h,12 38.677,47 12.497.518,66
Pek. Cat Residu Kuda - Kuda + Gording M2 4 47,37 14.572,31 6.519.171,29
-
PEKERJAAN PERLENGKAPAN LUAR DAN PERLENGKAPAN DALAM -
PERLENGKAPAN DALAM -
Pekerjaan Instalasi Listrik -
Pas. Instalasi Listrik Ttk 3 0,00 300.000,00 9.000.000,00
PERLENGKAPAN LUAR -
RABAT KELILING -
Pek. Urugan Tanah Bawah Lantai M3 2 2,81 381.772,44 8.708.076,53
Pek. Rabat Beton Keliling Spesi 1 : 3 : 5 Tebal 7 cmM3 4 ,93 1.816.495,32 8.951.688,96
Pas. Hollow Brick Keliling 1 : 4 M2 4 7,87 193.601,18 9.268.075,65
Plesteran Rabat Beton Keliling Spesi 1 : 4 M2 1 19,68 73.930,27 8.847.974,47
Kolom Uk. 20 x 20 M3 0 ,40 16.925.415,79 6.770.166,32
LAIN-LAIN -
Pek. Septic Tank + Resapan Kapasitas 25 Orang UNIT 1 ,00 9.000.000,00 9.000.000,00
-
-
C. LANJUTAN BANGUNAN RUANG KELAS 3 LOKAL -
PEKERJAAN BETON & DINDING -
Plesteran Dinding Hollow Brick 1 Pc : 4 Ps, Tebal 2 MCm2 4 37,18 73.930,27 32.320.686,68
Acian Dinding Holowbrick M2 4 37,18 37.514,11 16.400.343,50
-
PEKERJAAN KUDA -KUDA DAN KAP / ATAP -
Pas. List Plank Ukuran 2 x 2,5 x 20 cm M2 3 7,33 161.804,08 6.039.822,87
-
PEKERJAAN PLAFON -
Pas. Rangka Plafond Dalam, Luar dan Pada Singok MAt3ap, K a y u 5 1 ,x7 73 cm , 6u.9k0u4ra.7n1 660,9 x6 60 c m ( S i 1s1a. 9P4a1d.a5 B97a,g5ia1n Luar)
Pas. Plafond Dalam, Luar dan Pada Singok Atap GRMC2 4 mm , u1 k4u0r,2a7n 12 0 x 2 8480.9 c5m8,, 5(S8isa P a d a B 1a2g.4ia7n8 .L3u9a7r, 9&4 Dalam)
-
PEKERJAAN KOZEN, PINTU DAN JENDELA -
Pas. Pintu Panil Besar dan Kecil M2 3 1,70 790.948,49 25.069.903,35
Pas. Jendela Kaca Rangka Kayu tebal 5 mm M2 1 8,79 891.538,34 16.748.439,17
Pas. Papan Ventilasi Pada Konzen/Jalusi Kayu M2 2 7,12 406.299,96 11.016.904,56
Pas. Engsel Pintu SKK Pintu Panil Bh 1 20,00 56.407,17 6.768.860,01
-
PEKERJAAN LANTAI & KERAMIK -
Pek. Urugan Pasir di Bawah Lantai Tbl = 5 cm M3 1 1,82 562.835,79 6.650.996,76
Pek. Cor Lantai 1 : 3 : 5 Tbl = 7 cm M3 1 6,54 1.816.495,32 30.051.582,76
Pas. Lantai Granit Warna Utk Ruangan Uk. 60 x 60M c2m Lic in 1 82,34 461.699,37 84.185.708,26
Pas. Lantai Granit Warna Utk Teras Uk. 60 x 60 cmM K2asar 5 3,60 461.699,37 24.747.085,99
-
PEKERJAAN PENGECATAN -
Pek. Cat Minyak Kayu Kusen, Pintu Panil, Rangka JMen2dela , L i3 s5t 5P,i3n2ggir P l a f o 6n3,. 6V1e7n,t2i7lasi d a n L i s 2t2 P.6la0n4k.2 D49en,3g8an Cat Minyak Platon Atau Setara Warna Marun
Pek. Cat Dinding Dengan Cat Air Catilac atau SetarMa 2Warn a C 5 r1e4m,46 38.677,47 19.897.934,50
Pek. Cat Plafond Dengan Cat Air Catilac atau SetaraM W2arn a P 3 u1ti7h,14 38.677,47 12.266.126,82
-
PEKERJAAN PERLENGKAPAN LUAR DAN PERLENGKAPAN DALAM -
PERLENGKAPAN DALAM -
PEKERJAAN INSTALASI LISTRIK -
Pas. Instalasi Listrik Ttk 3 0,00 300.000,00 9.000.000,00
-
PERLENGKAPAN LUAR -
RABAT KELILING -
Pek. Urugan Tanah Bawah Lantai M3 2 1,89 381.772,44 8.356.235,06
Pek. Rabat Beton Keliling Spesi 1 : 3 : 5 Tebal 7 cmM3 4 ,79 1.816.495,32 8.697.379,61
Pas. Hollow Brick Keliling 1 : 4 M2 5 1,68 193.601,18 10.005.308,94
Plesteran Rabat Beton Keliling Spesi 1 : 4 M2 1 14,00 73.930,27 8.428.050,55
-
D. BANGUNAN RUANG UKS -
PEKERJAAN TANAH & PONDASI -
Pek. Cerucuk Dolken Kayu Galam/sejenisnya dia 8B ctmg, Pj g 2 1 m80,00 94.499,79 17.009.962,20
Pek. Pondasi Telapak 80/80 Tebal= 20 cm Spesi 1 :M 23 : 3 2 ,56 8.986.297,72 23.004.922,16
Pek. Kolom Pedestal/Kolom Pondasi Tapak UkuranM 230/20 C m S0 p,5e2si 1 1:4 2.8 :7 37 . 339,11 7.736.216,34
-
PEKERJAAN BETON & DINDING -
Pek. Sloof Beton Bertulang Ukuran 15/20 Cm SpesMi 31 : 2 : 3 1 ,75 10.629.657,95 18.591.271,76
Pek. Kolom Utama & Teras Beton Bertulang UkuranM 230/20 C m S1 ,p2e4si 1 1 :2 2.9 :2 35 . 028,36 16.052.885,23
Pek. Kolom Praktis Beton Bertulang Ukuran 12/12M C3m Sp e s i 1 0 :, 620 : 3 2 0.140.361,94 12.006.878,17
Pek. Balok Latei Beton Bertulang Ukuran 12/15 CmM 3 S0 p,5e5si 1 1 :9 2.1 :5 34 . 378,37 10.515.753,73
Pek. Beton Bertulang Ring Balok (RB1) Ukuran 15/M203 Cm 1 , 3 9 S p1e4s.2i 6 14 .:4 20 7: ,30 5 19.877.451,23
Pek. Balok Miring+Datar Pada Sopi-Sopi Teras BetoMn 3Bertu l a n g 0 U,k5u5ra n 1 182.5/6165. 8C1m8, 3S6pes i 1 : 2 : 1 30 . 219.919,50
Pas. Dinding + Pada Sigok Hollow Brick 1 : 4 M2 1 20,01 193.601,18 23.234.851,92
Plesteran Dinding + Pada Singok 1 Pc : 4 Ps, Tebal 2M C2m 2 64,98 73.930,27 19.589.746,68
Acian Dinding M2 2 64,98 37.514,11 9.940.338,76
-
PEKERJAAN KUDA -KUDA DAN KAP / ATAP -
Pek. Kuda-kuda Kayu Sistim Gording M3 1 ,14 6.297.862,74 7.188.027,85
Pas. Atap Seng Gelombang Warna Tebal 0,3 mm M2 1 31,40 123.370,78 16.210.920,56
-
PEKERJAAN PLAFON -
Pas. Rangka Plafond Kayu 5 x 7 cm ukuran 60 x 60M c3m 1 ,20 6.904.716,96 8.285.555,18
Pas. Plafond GRC 4 mm, ukuran 120 x 240 cm, M2 9 3,53 88.958,58 8.320.260,41
-
PEKERJAAN KOZEN, PINTU DAN JENDELA -
Pek. Kozen Pintu, Jendela dan Ventilasi M3 1 ,01 7.598.070,54 7.661.514,42
Pas. Pintu Panil Ruangan M2 8 ,40 790.948,49 6.647.763,87
Pas. Jendela Kaca Rangka Kayu tebal 5 mm M2 1 4,37 891.538,34 12.812.832,34
-
-
PEKERJAAN LANTAI & KERAMIK -
Pek. Urugan Tanah di Bawah Lantai M3 1 4,36 381.772,44 5.481.584,06
Pek. Cor Lantai 1 : 3 : 5 Tbl = 7 cm M3 3 ,78 1.816.495,32 6.866.256,96
Pas. Lantai Granit Warna Utk Ruangan Uk. 60 x 60M c2m Lic in 3 4,56 461.699,37 15.955.591,35
Pas. Lantai Granit Warna Utk Teras Uk. 60 x 60 cmM K2asar 1 6,71 461.699,37 7.715.573,52
-
PEKERJAAN PENGECATAN -
Pek. Cat Minyak Kayu Kusen, Pintu Panil, Rangka JMen2dela , L i1 s4t 7P,i9n1ggir P l a f o 6n3,. 6V1e7n,t2i7lasi d a n L i s t 9 P.4la0n9k.4 D89en,8g3an Cat Minyak Platon Atau Setara Warna Marun
Pek. Cat Dinding Dengan Cat Air Catilac atau SetarMa 2Warn a C 2 r8e5m,12 38.677,47 11.027.875,31
-
PEKERJAAN PERLENGKAPAN LUAR DAN PERLENGKAPAN DALAM -
PERLENGKAPAN DALAM -
Pekerjaan Instalasi Listrik -
Pas. Panel MCB/Skring Box UNIT 1 ,00 9.000.000,00 9.000.000,00
Pekerjaan Perpipaan/Sanitair -
JUMLAH TOTAL 1.146.046.742,50
disusun oleh
Pejabat Pembuat Komitmen
JUMEISRI, ST, M.Ec.Dev
Nip.19810508 201101 1 006