REKAPITULASI
BILL OF QUANTITY (BOQ)
Instansi : RSUD OKU TIMUR
Pekerjaan : Pembangunan Baru Gedung IGD RSUD OKU Timur
Sumber Dana : DAK
Thn. Angg. : 2025
JUMLAH HARGA
NOMOR URAIAN PEKERJAAN KET.
(Rp)
(1) (2) (3) (4)
A PEKERJAAN PENDAHULUAN 164.453.140,84
I PEKERJAAN PERSIAPAN 151.703.140,84
PEKERJAAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI
II 12.750.000,00
BANGUNAN GEDUNG
B GEDUNG IGD 1 1.217.564.173,67
1 PEKERJAAN PENDAHULUAN
I PEKERJAAN GALIAN TANAH PASIR DAN PONDASI 3 .467.494.686,90
2 LANTAI I ELV. ± 0.00
I PEKERJAAN BETON BERTULANG 3 .750.561.069,60
II PEKERJAAN KUSEN PINTU DAN JENDELA 1 .076.617.335,80
III PEKERJAAN DINDING DAN PLESTERAN 2 69.286.153,16
IV PEKERJAAN PENUTUP LANTAI 4 65.741.939,36
V PEKERJAAN PLUMBING DAN SANITASI 3 68.434.684,96
VI PEKERJAAN ELEKTRIKAL 68.163.802,98
VII PEKERJAAN PLAFOND 3 08.474.727,67
VIII PEKERJAAN FINISHING 44.428.948,77
IX PEKERJAAN TANGGA 66.520.799,21
X PEKERJAAN SISTEM SENTRAL GAS MEDIS 5 28.734.777,31
3 LANTAI II ELV. + 4.60
I PEKERJAAN BETON BERTULANG 8 03.105.247,94
(A). JUMLAH HARGA PEKERJAAN 11.382.017.314,51
(B). PAJAK PERTAMBAHAN NILAI (PPN) = 11/100 x (A) 1 .252.021.904,60
(C). TOTAL HARGA (A + B) 1 2.634.039.219,10
(D). DIBULATKAN 1 2.634.039.000,00
TERBILANG : Duabelas Milyar Enam Ratus Tiga Puluh Empat Juta Tiga Puluh Sembilan Ribu Rupiah
Tulus Ayu, Maret 2025
Pejabat Pembuat Komitmen (PPK)
Memeriksa/Menyetujui
PLT MAN I PAK
FANDY NUARY
dr. Sugihartono, M.Sc
NIP. 19760630 200501 1 003
BILL OF QUANTITY (BOQ)
Instansi : RSUD OKU TIMUR
Pekerjaan : Pembangunan Baru Gedung IGD RSUD OKU Timur
Sumber Dana : DAK
Thn. Angg. : 2025
KODE HARGA SATUAN JUMLAH HARGA
NOMOR URAIAN PEKERJAAN QUANTITY SAT.
ANALISA
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)
A PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pek. Pembuatan Papan Nama Proyek Ls 1,00 Ls 250.000,00 2 50.000,00
2 Pek. Pembersihan Awal Lapangan Ls 1,00 Ls 3.000.000,00 3.000.000,00
3 Pek. Pagar Pengaman Proyek Sementara dari Seng Gelombang A.1.1.1.2 160,00 m1 684.159,21 109.465.473,60
5 Pek. Pas. Bouwplank A.1.1.1.4 138,00 m1 91.214,98 12.587.667,24
4 Pek. Pek. Pembuatan Direksi Keet/Gudang Material & Peralatan Ls 1,00 Ls 7.500.000,00 7.500.000,00
5 Pek. Pembuatan Laporan Progres dan Dokumentasi Proyek Ls 1,00 Ls 3.000.000,00 3.000.000,00
6 Pek. Pembuatan Gambar Asbuild Drawing Ls 1,00 Ls 2.400.000,00 2.400.000,00
7 Pek. Air Kerja Ls 1,00 Ls 6.000.000,00 6.000.000,00
8 Pek. Listrik Kerja Ls 1,00 Ls 6.000.000,00 6.000.000,00
9 Pek. Mobilisasi & Demobilisasi Ls 1,00 Ls 1.000.000,00 1.000.000,00
10 Pek. Pembersihan Akhir Lapangan Ls 1,00 Ls 500.000,00 5 00.000,00
151.703.140,84
II PEKERJAAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI BANGUNAN GEDUNG
12.750.000,00
B GEDUNG IGD
1 PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
I PEKERJAAN GALIAN TANAH PASIR DAN PONDASI
1 Pek. Timbunan Tanah Tebal 60cm A.1.5.1.19 616,93 m3 262.831,25 162.148.483,06
2 Pek. Pondasi Borepile Diameter 40cm (Kedalaman 8m) A.3.2.1.14 1.600,00 m1 1.257.879,08 2.012.606.528,00
3 Pek. Pondasi Menerus Batu Belah Ad. 1:4 Type 1
- Pek. Galian Tanah A.1.5.1.1 166,66 m3 83.861,25 13.976.315,93
- Pek. Urug Pasir Tebal 5cm A.1.5.1.10 10,42 m3 339.771,30 3.540.416,95
- Pek. Cor Lantai Kerja Tebal 5cm A.4.1.1.4 10,42 m3 1.415.096,01 14.745.300,42
- Pek. Pondasi Rollag Bata Ad. 1:4 A.3.2.1.12 78,77 m3 2.189.484,24 172.465.673,58
4 Pek. Pondasi Tapakan Type P1 Uk. 220x220m Tebal 70cm (Pilecap)
- Pek. Galian Tanah A.1.5.1.1 259,20 m3 83.861,25 21.736.836,00
- Pek. Urug Pasir Tebal 10cm A.1.5.1.10 28,80 m3 339.771,30 9.785.413,44
- Pek. Cor Lantai Kerja Tebal 10cm A.4.1.1.4 28,80 m3 1.415.096,01 40.754.765,09
5 Pek. Pondasi Tapakan Type P1 Uk. 220x220m Tebal 70cm (Pilecap)
- Bekisting Pondasi A.4.1.1.18 308,00 m2 247.019,63 76.082.046,04
- Besi A.4.1.1.15a 19.950,30 Kg 31.867,88 635.773.766,36
- Beton Mutu K250 A.4.1.1.8a 169,40 m3 1.793.855,62 303.879.142,03
3 .467.494.686,90
2 LANTAI I ELV. + 0.60
I PEKERJAAN BETON BERTULANG
1 Pek. Sloof Beton Bertulang Type S1 Uk. 35x70cm
a. Bekisting Sloof A.4.1.1.19 455,84 m2 263.924,38 120.307.289,38
b. Besi A.4.1.1.15a 19.750,80 Kg 31.867,88 629.416.124,30
c. Beton Mutu K250 A.4.1.1.8a 68,38 m3 1.793.855,62 122.663.847,30
2 Pek. Sloof Beton Bertulang Type S2 Uk. 30x60cm
a. Bekisting Sloof A.4.1.1.19 55,44 m2 263.924,38 14.631.967,63
b. Besi A.4.1.1.15a 1.440,34 Kg 31.867,88 45.900.582,28
c. Beton Mutu K250 A.4.1.1.8a 6,93 m3 1.793.855,62 12.431.419,45
3 Pek. Sloof Beton Bertulang Type S4 Uk. 15x30cm
a. Bekisting Sloof A.4.1.1.19 17,10 m2 263.924,38 4.513.106,90
b. Besi A.4.1.1.15a 212,37 Kg 31.867,88 6.767.781,68
c. Beton Mutu K250 A.4.1.1.8a 0,86 m3 1.793.855,62 1.542.715,83
4 Pek. Rabat Teras Beton Bertulang Tebal 10cm Elv. +4.60
a. Besi Wiremesh M8 A.4.1.1.17a 170,30 Kg 13.592,06 2.314.727,82
b. Beton Mutu K225 A.4.1.1.7a 2,60 m3 1.770.606,88 4.603.577,89
5 Pek. Kolom Beton Bertulang Type K1 Uk. 60x60cm
a. Bekisting Kolom A.4.1.1.20a 483,60 m2 438.530,90 212.073.543,24
b. Besi A.4.1.1.15a 13.196,20 Kg 31.867,88 420.534.918,06
c. Beton Mutu K250 A.4.1.1.8a 70,20 m3 1.793.855,62 125.928.664,52
6 Pek. Kolom Beton Bertulang Type K2 Uk. 40x40cm
a. Bekisting Kolom A.4.1.1.20a 13,10 m2 438.530,90 5.744.754,79
b. Besi A.4.1.1.15a 121,45 Kg 31.867,88 3.870.354,03
c. Beton Mutu K250 A.4.1.1.8a 1,25 m3 1.793.855,62 2.242.319,53
7 Pek. Kolom Praktis Beton Bertulang A.4.1.1.26a 124,00 m1 159.159,07 19.735.724,68
8 Pek. Balok Beton Bertulang Type B1 Uk. 35x70cm Elv. +4.60
a. Bekisting Balok A.4.1.1.21a 577,50 m2 468.942,34 270.814.201,35
b. Besi A.4.1.1.15a 7.383,93 Kg 31.867,88 235.310.195,17
c. Beton Mutu K250 A.4.1.1.8a 66,99 m3 1.793.855,62 120.170.387,98
9 Pek. Balok Beton Bertulang Type B2 Uk. 30x60cm Elv. +4.60
a. Bekisting Balok A.4.1.1.21a 51,00 m2 468.942,34 23.916.059,34
b. Besi A.4.1.1.15a 1.128,01 Kg 31.867,88 35.947.287,32
c. Beton Mutu K250 A.4.1.1.8a 4,90 m3 1.793.855,62 8.789.892,54
10 Pek. Balok Beton Bertulang Type B4 Uk. 15x30cm Elv. +4.60
a. Bekisting Balok A.4.1.1.21a 96,19 m2 468.942,34 45.107.563,68
b. Besi A.4.1.1.15a 1.071,72 Kg 31.867,88 34.153.444,35
c. Beton Mutu K250 A.4.1.1.8a 3,46 m3 1.793.855,62 6.206.740,45
11 Pek. Balok Beton Bertulang Type BT Uk. 15x30cm Elv. +4.60
a. Bekisting Balok A.4.1.1.21a 4,02 m2 468.942,34 1.885.148,21
b. Besi A.4.1.1.15a 47,78 Kg 31.867,88 1.522.647,31
c. Beton Mutu K250 A.4.1.1.8a 0,14 m3 1.793.855,62 2 51.139,79
12 Pek. Balok Beton Bertulang Type BK Uk. 25x40cm Elv. +4.60
KODE HARGA SATUAN JUMLAH HARGA
NOMOR URAIAN PEKERJAAN QUANTITY SAT.
ANALISA
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)
a. Bekisting Balok A.4.1.1.21a 16,38 m2 468.942,34 7.681.275,53
b. Besi A.4.1.1.15a 264,98 Kg 31.867,88 8.444.350,84
c. Beton Mutu K250 A.4.1.1.8a 1,09 m3 1.793.855,62 1.955.302,63
13 Pek. Plat Lantai Beton Bertulang Tebal 12cm
a. Bekisting Plat A.4.1.1.22a 912,40 m2 514.916,66 469.809.960,58
b. Besi A.4.1.1.15a 15.256,00 Kg 31.867,88 486.176.377,28
c. Beton Mutu K250 A.4.1.1.8a 109,49 m3 1.793.855,62 196.409.251,83
14 Pek. Waterproofing Acian Plat Lantai A.4.4.2.27a 912,40 m2 44.702,35 40.786.424,14
3 .750.561.069,60
II PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. Pintu Tempered Type D1 Uk. 200x220cm (1 Lubang Pintu) A.11.1.40 3,00 Unit 17.332.951,99 51.998.855,97
2 Pek. Pintu Hermetic Type D3 Uk. 130x210cm (1 Lubang Pintu) A.11.1.42 8,00 Unit 98.447.250,00 787.578.000,00
3 Pek. Pintu Hermetic Type D4 Uk. 100x210cm (1 Lubang Pintu) A.11.1.43 3,00 Unit 52.384.200,00 157.152.600,00
Pek. Pintu Jendela Aluminium Type D6 Uk. 250x300cm (1 Lubang Pintu, 6
4 A.11.1.45 2,00 Unit 13.084.325,81 26.168.651,62
Lubang Jendela Sedang, 1 Lubang Jendela Besar)
5 Pek. Pintu Kayu Kelas I Type D8 Uk. 100x210cm (1 Lubang Pintu) A.11.1.46 2,00 Unit 4.049.424,54 8.098.849,08
6 Pek. Pintu KM/WC Aluminium Type D9 Uk. 80x200cm (1 Lubang Pintu) A.11.1.47 3,00 Unit 2.754.647,50 8.263.942,50
7 Pek. Pintu Multiplek Type D11 Uk. 160x210cm (1 Lubang Pintu) A.11.1.49 1,00 Unit 5.133.158,55 5.133.158,55
8 Pek. Jendela Aluminium Type W2 Uk. 190x60cm (2 Lubang Bouvenly) A.11.1.52 14,00 Unit 1.816.134,80 25.425.887,20
9 Pek. Jendela Aluminium Type W3 Uk. 85x50cm (1 Lubang Bouvenly) A.11.1.53 7,00 Unit 971.055,84 6.797.390,88
1 .076.617.335,80
III PEKERJAAN DINDING DAN PLESTERAN
1 Pek. Pas. Dinding 1/2 Bata Ad. 1:4 A.4.4.1.9a 709,84 m2 228.587,00 162.260.196,08
2 Pek. Plesteran Tebal 15mm Ad. 1:4 A.4.4.2.4a 1.419,69 m2 75.386,85 107.025.957,08
269.286.153,16
IV PEKERJAAN PENUTUP LANTAI
1 Pek. Pas. Keramik Dinding WC Uk. 20x25cm (UnPolished) A.4.4.3.70a 60,13 m2 341.646,98 20.543.232,91
2 Pek. Pas. Keramik Lantai Uk. 20x20cm (UnPolished) A.4.4.3.71a 42,50 m2 266.558,16 11.328.721,80
3 Pek. Pas. Homogenus Tile Polished Uk. 60x60cm A.4.4.3.68.1a 754,10 m2 508.936,43 383.788.961,86
4 Pek. Pas. Homogenus Tile UnPolished Uk. 60x60cm A.4.4.3.68.2a 59,40 m2 430.826,03 25.591.066,18
5 Pek. Pas. Plint Homogenus Tile Uk. 10x60cm A.4.4.3.69a 457,48 m1 53.532,30 24.489.956,60
465.741.939,36
V PEKERJAAN SANITASI
1 Pek. Jet Shower Spray Ex. Toto THX20NB A.5.1.1.42a 3,00 Unit 591.739,50 1.775.218,50
2 Pek. Closet Duduk Kelas I A.5.1.1.1a 5,00 Unit 4.782.283,00 23.911.415,00
3 Pek. Wastafel Meja A.5.1.1.5a 6,00 Unit 2.251.291,02 13.507.746,12
4 Pek. Wastafel A.5.1.1.5a 1,00 Unit 2.251.291,02 2.251.291,02
5 Pek. Wastafel Spoel Hoek A.5.1.1.5a 3,00 Unit 2.251.291,02 6.753.873,06
6 Pek. Wastafel Dokter dan Perawat A.5.1.1.5a 2,00 Unit 2.251.291,02 4.502.582,04
7 Pek. Urinoir Ex. Toto A.5.1.1.4a 1,00 Unit 7.181.881,52 7.181.881,52
8 Pek. Kran Dinding Ex. Toto T23BQ A.5.1.1.35a 5,00 Unit 612.891,13 3.064.455,65
9 Pek. Floor Drain A.5.1.1.36a 5,00 Unit 68.219,25 3 41.096,25
10 Pek. Head Shower Ex. Toto TX465SL A.5.1.1.41a 2,00 Unit 3.026.837,00 6.053.674,00
11 Pek. Kran Shower A.5.1.1.45a 2,00 Unit 330.191,13 6 60.382,26
12 Pek. Handrailling Pipa Stainless 1.25" A.11.2.16 5,00 Unit 272.748,85 1.363.744,25
13 Pek. Pipa PVC Dia. 1 Inch (Air Bersih) A.5.1.1.27a 32,00 m1 48.764,10 1.560.451,20
14 Pek. Pipa PVC Dia. 3/4 Inch (Air Bersih) A.5.1.1.26a 17,00 m1 41.517,85 7 05.803,45
15 Pek. Pipa PVC Dia, 2 Inch (Air Bekas) A.5.1.1.29 22,00 m1 113.639,90 2.500.077,80
16 Pek. Pipa PVC Dia, 4 Inch (Air Kotor) A.5.1.1.32a 76,00 m1 303.586,25 23.072.555,00
17 Pek. Pas Tanki Air FRP Kap. 20 m3 A.11.2.6 1,00 Unit 1 32.603.854,17 132.603.854,17
18 Pek. Bio Tank Kap. 20 m3 A.11.2.20 1,00 Unit 1 30.095.389,29 130.095.389,29
19 Pek. Mesin Pompa Air Jet Pump A.11.2.12a 2,00 Buah 3.264.597,19 6.529.194,38
368.434.684,96
VI PEKERJAAN ELEKTRIKAL
1 Pek. Titik Sprinkler A.5.1.1.51 24,00 Unit 159.218,13 3.821.235,12
2 Pek. Instalasi Titik Nyala Lampu A.6.2.1.1a 50,00 Titik 326.255,22 16.312.761,00
3 Pek. Instalasi Stop Kontak AC A.6.1.1.2a 19,00 Titik 298.162,15 5.665.080,85
4 Pek. Indoor Hydrant Box Ex. Hooseki Type B A.6.1.1.20 1,00 Unit 6.571.090,63 6.571.090,63
5 Pek. Lampu LED Downlight Inbow Bulat 16 Watt A.6.2.1.3a 16,00 Buah 271.968,13 4.351.490,08
6 Pek. Lampu TL 14W + Kap A.6.2.1.4a 34,00 Buah 254.834,25 8.664.364,50
7 Pek. Exhaust Fan 8 Inch A.6.1.1.15 8,00 Buah 734.690,00 5.877.520,00
8 Pek. Saklar Tunggal A.6.1.1.6a 1,00 Buah 82.075,95 8 2.075,95
9 Pek. Saklar Ganda A.6.1.1.7a 10,00 Buah 86.475,95 8 64.759,50
10 Pek. Saklar Triple A.6.1.1.8a 3,00 Buah 143.675,95 4 31.027,85
11 Pek. Smoke Detektor A.6.1.1.16 22,00 Buah 432.836,25 9.522.397,50
12 Pek. Penarikan Kabel untuk Pasang Meteran Ls 1,00 Ls 6.000.000,00 6.000.000,00
68.163.802,98
VII PEKERJAAN PLAFOND
1 Pek. Rangka Hollow Plafond A.4.2.1.21a 843,50 m2 152.554,60 128.679.805,10
2 Pek. Plafond PVC Ex. Shunda Plafond A.4.5.1.16a 843,50 m2 195.060,86 164.533.835,41
3 Pek. List Profil PVC A.4.5.1.17a 404,94 m1 37.687,28 15.261.087,16
308.474.727,67
VIII PEKERJAAN FINISHING
1 Pek. Cat Tembok Eksterior A.4.7.1.23a 304,54 m2 47.625,67 14.503.921,54
2 Pek. Cat Tembok Interior A.4.7.1.10a 1.115,14 m2 26.835,22 29.925.027,23
44.428.948,77
IX PEKERJAAN TANGGA
1 Pek. Pondasi Tapakan Uk. 70x250m Tebal 20cm
- Pek. Galian Tanah A.1.5.1.1 0,81 m3 83.861,25 6 7.927,61
- Pek. Urug Pasir Tebal 5cm A.1.5.1.10 0,04 m3 339.771,30 1 3.590,85
- Pek. Cor Lantai Kerja Tebal 5cm A.4.1.1.4 0,04 m3 1.415.096,01 5 6.603,84
- Pek. Cerucuk Gelam Dia. 10/12cm A.11.2.7 25,00 Btg 19.548,38 4 88.709,50
Pek. Pondasi Tapakan Uk. 70x250m Tebal 20cm
a. Bekisting Pondasi A.4.1.1.18 0,56 m2 247.019,63 1 38.330,99
b. Besi A.4.1.1.15a 7,58 kg 31.867,88 2 41.558,53
c. Beton Mutu K250 A.4.1.1.8a 0,10 m3 1.793.855,62 1 79.385,56
2 Pek. Kolom Pedestal Beton Bertulang Uk. 30x250cm
a. Bekisting Kolom A.4.1.1.20a 5,68 m2 438.530,90 2.490.855,51
b. Besi A.4.1.1.15a 30,74 kg 31.867,88 9 79.618,63
c. Beton Mutu K250 A.4.1.1.8a 0,75 m3 1.793.855,62 1.345.391,72
3 Pek. Cor Plat Bordes Tebal 15cm
KODE HARGA SATUAN JUMLAH HARGA
NOMOR URAIAN PEKERJAAN QUANTITY SAT.
ANALISA
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)
a. Bekisting Plat A.4.1.1.22a 3,00 m2 514.916,66 1.544.749,98
b. Besi A.4.1.1.15a 71,76 kg 31.867,88 2.286.839,07
c. Beton Mutu K250 A.4.1.1.8a 0,45 m3 1.793.855,62 8 07.235,03
4 Pek. Cor Plat Tangga Tebal 15cm
a. Bekisting Plat A.4.1.1.22a 10,40 m2 514.916,66 5.355.133,26
b. Besi A.4.1.1.15a 257,36 kg 31.867,88 8.201.517,60
c. Beton Mutu K250 A.4.1.1.8a 1,56 m3 1.793.855,62 2.798.414,77
5 Pek. Anak Tangga Beton Bertulang
a. Bekisting Tangga A.4.1.1.25a 4,73 m2 426.247,64 2.016.151,34
b. Besi A.4.1.1.15a 111,45 kg 31.867,88 3.551.675,23
c. Beton Mutu K250 A.4.1.1.8a 0,71 m3 1.793.855,62 1.273.637,49
6 Pek. Pas. Homogeneous Tile Polished Uk. 60x60cm A.4.4.3.72a 15,73 m2 508.936,43 8.005.570,04
7 Pek. Railing Tangga Hollow Steinless 40.40.2 A.11.2.21 7,00 m1 1.461.888,34 10.233.218,38
8 Pek. Atap Area Void Tangga
- Pek. Rangka Atap Baja Ringan C 75.75 A.11.2.1 36,00 m2 243.547,75 8.767.719,00
- Pek. Penutup Atap Spandek Berpasir A.4.5.2.48b 36,00 m2 157.693,48 5.676.965,28
66.520.799,21
X PEKERJAAN SISTEM SENTRAL GAS MEDIS
1 RUANG IGD
a Pek. Pipa tembaga ASTM B819 Tipe L/Medical Grade
- Uk Pipa Tembaga 3/8 " A.11.4.12 34,80 m1 162.417,67 5.652.134,92
- Uk. Pipa Tembaga 1/2 " A.11.4.13 94,80 m1 221.296,77 20.978.933,80
- Uk. Pipa tembaga 5/8 " A.11.4.14 135,00 m1 298.544,20 40.303.467,00
- Uk. Pipa tembaga 3/4 " A.11.4.15 87,00 m1 349.561,57 30.411.856,59
- Uk. Pipa tembaga 3/4 " A.11.4.15 112,00 m1 349.561,57 39.150.895,84
- Uk Pipa Tembaga 1'' A.11.4.16 40,00 m1 530.732,20 21.229.288,00
- Uk. Pipa tembaga 1-1/8'' A.11.4.17 40,00 m1 589.075,80 23.563.032,00
- Uk. Pipa tembaga 1-5/8'' A.11.4.18 40,00 m1 1.114.535,90 44.581.436,00
b Pek. Zona Valve 2 Gas (OAV) Valcon, Ex. Cakratech A.11.4.6 1,00 Set 18.548.750,00 18.548.750,00
c Pek. Zona Alarm 2 Gas (OAV) Valcon, Ex. Cakratech A.11.4.7 1,00 Set 19.228.000,00 19.228.000,00
d Pek. Cooper Fitting, Material Support & Consumable Ls 1,00 Ls 31.752.000,00 31.752.000,00
e Pek. Bedhead (1200 mm, Lampu Baca, Saklar, Stop Kontak) A.11.4.8 12,00 Unit 2.904.891,00 34.858.692,00
f Pek. Medical Gas Outlet Tipe Japan Quick Conect Berbeda Derajat PIN
- Pek. Outlet Gas Medis Oksigen A.11.4.9 12,00 Buah 3.566.794,00 42.801.528,00
- Pek. Outlet Vacum Medik A.11.4.10 12,00 Buah 3.566.794,00 42.801.528,00
2 RUANG VK, TINDAKAN DAN RUANG ISOLASI
a Pek. Pipa Tembaga ASTM B819 Tipe L/Medical Grade
- Uk Pipa Tembaga 3/8 " A.11.4.12 20,30 m1 162.417,67 3.297.078,70
- Uk. Pipa Tembaga 1/2 " A.11.4.13 17,40 m1 221.296,77 3.850.563,80
- Uk. Pipa tembaga 5/8 " A.11.4.14 63,00 m1 298.544,20 18.808.284,60
- Uk. Pipa tembaga 3/4 " A.11.4.15 51,00 m1 349.561,57 17.827.640,07
b Pek. Cooper Fitting, Material Support & Consumable Ls 1,00 Ls 5.292.000,00 5.292.000,00
c Pek. Bedhead (1200 mm, Lampu Baca, Saklar, Stop Kontak) A.11.4.8 6,00 Unit 2.904.891,00 17.429.346,00
d Pek. Medical Gas Outlet Tipe Japan Quick Conect Berbeda Derajat PIN
- Pek. Outlet Gas Medis Oksigen A.11.4.9 6,00 Buah 3.566.794,00 21.400.764,00
- Pek. Outlet Medical Air Comprerss A.11.4.11 1,00 Buah 3.566.794,00 3.566.794,00
- Pek. Outlet Vacum Medik A.11.4.10 6,00 Buah 3.566.794,00 21.400.764,00
528.734.777,31
3 LANTAI II ELV. + 4.60
I PEKERJAAN BETON BERTULANG
1 Pek. Kolom Beton Bertulang Type K1 Uk. 60x60cm
a. Bekisting Kolom A.4.1.1.20b 496,00 m2 449.686,07 223.044.290,72
b. Besi A.4.1.1.15b 13.647,30 kg 32.033,14 437.165.871,52
c. Beton Mutu K250 A.4.1.1.8b 72,00 m3 1.814.488,06 130.643.140,32
2 Pek. Kolom Beton Bertulang Type K2 Uk. 40x40cm
a. Bekisting Kolom A.4.1.1.20b 13,44 m2 449.686,07 6.043.780,78
b. Besi A.4.1.1.15b 121,30 kg 32.033,14 3.885.619,88
c. Beton Mutu K250 A.4.1.1.8b 1,28 m3 1.814.488,06 2.322.544,72
803.105.247,94