| Reason | |||
|---|---|---|---|
| 0940987241741000 | Rp 12,435,884,216 | - | |
| 0418969283722000 | Rp 12,477,220,499 | Tidak Melampirkan Jaminan Penawaran | |
Multi Conblock Nusantara | 03*0**4****41**0 | - | - |
R E K A P I T U L A S I
BOQ
Sub kegiatan : PENINGKATAN SISTEM DRAINASE PERKOTAAN
Pekerjaan : PENINGKATAN SALURAN DRAINASE JL. CIPTO MANGUKUSUMO KEL.GUNUNG PANJANG KEC. SAMARINDA SEBERANG
Lokasi : Kota Samarinda
JUMLAH HARGA TKDN JUMLAH BIAYA KDN JUMLAH BIAYA KLN
NO. URAIAN PEKERJAAN
( Rp. ) ( % ) ( Rp. ) ( Rp. )
A. PENERAPAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK) Rp 2 33.583.140,00 81,36% Rp 1 90.034.360,44 Rp 4 3.548.779,56
B. PEKERJAAN PERSIAPAN Rp 3 .272.554.153,08 74,30% Rp 2 .431.408.778,45 Rp 8 41.145.374,64
C. PEKERJAAN TANAH Rp 7 55.645.323,09 77,73% Rp 5 87.332.109,19 Rp 1 68.313.213,90
D. PEKERJAAN PEMANCANGAN & PASANGAN Rp 9 29.934.810,83 96,74% Rp 8 99.660.303,86 Rp 3 0.274.506,97
E. PEKERJAAN BETON PREACAST Rp 3 .819.591.985,35 73,40% Rp 2 .803.598.698,07 Rp 1 .015.993.287,28
F. PEKERJAAN BETON Rp 1 .950.649.852,36 87,11% Rp 1 .699.121.171,19 Rp 2 51.528.681,17
G. PEKERJAAN LAIN - LAIN & PERAPIAN AREA TAMAN TERBONGKAR Rp 2 97.888.883,91 77,52% Rp 2 30.916.012,74 Rp 5 2.257.318,75
JUMLAH HARGA PEKERJAAN : Rp 1 1.259.848.148,61 78,53% Rp 8.842.071.433,93 Rp 2.403.061.162,27
PAJAK : PPn Rp 1.238.583.296,35 Rp 972.627.857,73
TOTAL JUMLAH PEKERJAAN : Rp 1 2.498.431.444,96 Rp 9.814.699.291,66
PEMBULATAN HARGA : Rp 1 2.498.431.000,00 Rp 9.814.699.000,00
Samarinda, 2025
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KOTA SAMARINDA
PEJABAT PEMBUAT KOMITMEN
DEDY SUMBAWARDANA, ST.MM
NIP. 19780814 20091 1 002
RENCANA ANGGARAN BIAYA
BOQ PENINGKATAN SISTEM DRAINASE PERKOTAAN
Pekerjaan : PENINGKATAN SALURAN DRAINASE JL. CIPTO MANGUKUSUMO KEL.GUNUNG PANJANG KEC. SAMARINDA SEBERANG
Lokasi : Kota Samarinda
HARGA SATUAN JUMLAH HARGA TKDN% JUMLAH BIAYA KDN JUMLAH BIAYA KLN
NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
A. PENERAPAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)
1 Penyiapan dokumen penerapan SMKK
a. Pembuatan dokumen SMKK (RKK, RKPPL, RMLLP, dan RMPK) 1 ,00 set Rp 2.000.000,00 Rp 2.000.000,00 - - 2.000.000,00
b. Pembuatan prosedur dan instruksi kerja 1 ,00 set Rp 1.500.000,00 Rp 1.500.000,00 - - 1.500.000,00
c. Penyusunan pelaporan penerapan SMKK 1 ,00 set Rp 1.500.000,00 Rp 1.500.000,00 - - 1.500.000,00
2 Sosialisasi, Promosi dan Pelatihan: -
a. Induksi keselamatan konstruksi (Safety Induction) 1 ,00 kegiatan Rp 2.500.000,00 Rp 2.500.000,00 - - 2.500.000,00
b. Pengarahan keselamatan konstruksi (Safety Briefing) 1 ,00 kegiatan Rp 2.500.000,00 Rp 2.500.000,00 - - 2.500.000,00
c. Pertemuan keselamatan 1 ,00 kegiatan Rp 2.000.000,00 Rp 2.000.000,00 - - 2.000.000,00
d. Tools Box Meeting 1 ,00 kegiatan Rp 500.000,00 Rp 500.000,00 - - 500.000,00
e. Rapat keselamatan konstruksi 1 ,00 kegiatan Rp 1.000.000,00 Rp 1.000.000,00 - - 1.000.000,00
f. Patroli keselamatan 2 ,00 kegiatan Rp 500.000,00 Rp 1.000.000,00 - - 1.000.000,00
g. Spanduk (banner) 4 ,00 lembar Rp 150.000,00 Rp 600.000,00 - - 600.000,00
h. Poster/leaflet 1 0,00 lembar Rp 50.000,00 Rp 500.000,00 - - 500.000,00
i. Papan Informasi Keselamatan konstruksi 1 ,00 buah Rp 500.000,00 Rp 500.000,00 - - 500.000,00
3 Alat Pelindung Kerja dan Alat Pelindung Diri: -
a. APK, antara lain: -
1). Pembatas area (restricted area) 4 ,00 roll Rp 150.000,00 Rp 600.000,00 - - 600.000,00
b. APD -
1). Helm pelindung (safety helmet) 2 0,00 buah Rp 79.157,00 Rp 1.583.140,00 44,60% 706.080,44 877.059,56
2). Sarung tangan (safety gloves) 2 0,00 psg Rp 15.000,00 Rp 300.000,00 56,80% 170.400,00 129.600,00
3). Sepatu keselamatan (safety shoes, rubber safety shoes and t o e c a p ) 2 0,00 psg Rp 150.000,00 Rp 3.000.000,00 54,01% 1.620.300,00 1.379.700,00
4). Rompi keselamatan (safety vest 2 0,00 buah Rp 50.000,00 Rp 1.000.000,00 71,22% 712.200,00 287.800,00
5 Personel Keselamatan Konstruksi: -
a. Ahli K3 konstruksi atau ahli keselamatan konstruksi 5 ,00 org/bln Rp 15.000.000,00 Rp 75.000.000,00 100,00% 75.000.000,00 -
b. Petugas K3 konstruksi atau petugas keselamatan konstruksi 5 ,00 org/bln Rp 6.000.000,00 Rp 30.000.000,00 100,00% 30.000.000,00 -
c. Petugas pengatur lalu lintas 5 ,00 org/bln Rp 3.500.000,00 Rp 17.500.000,00 100,00% 17.500.000,00 -
d. Koordinator manajemen dan keselamatan konstruksi 5 ,00 org/bln Rp 5.000.000,00 Rp 25.000.000,00 100,00% 25.000.000,00 -
6 Fasilitas Sarana, Prasarana, dan Alat Kesehatan: -
a. Peralatan P3K (Kotak P3K, Alat pengukur suhu) 1 ,00 set Rp 2.500.000,00 Rp 2.500.000,00 - - 2.500.000,00
7 Rambu dan Perlengkapan Lalu Lintas: -
a. Rambu petunjuk 8 ,00 buah Rp 100.000,00 Rp 800.000,00 - - 800.000,00
b. Rambu larangan 8 ,00 buah Rp 100.000,00 Rp 800.000,00 - - 800.000,00
c. Rambu peringatan 8 ,00 buah Rp 100.000,00 Rp 800.000,00 - - 800.000,00
d. Rambu kewajiban 8 ,00 buah Rp 100.000,00 Rp 800.000,00 - - 800.000,00
e. Rambu informasi 8 ,00 buah Rp 100.000,00 Rp 800.000,00 - - 800.000,00
f. Rambu pekerjaan sementara 8 ,00 unit Rp 100.000,00 Rp 800.000,00 - - 800.000,00
g. Kerucut lalu lintas 8 ,00 unit Rp 150.000,00 Rp 1.200.000,00 54,89% 658.680,00 541.320,00
h. Pembatas jalan (water barrier) 1 0,00 unit Rp 1.500.000,00 Rp 15.000.000,00 55,24% 8.286.000,00 6.714.000,00
i. Lampu/alat penerangan sementara 2 ,00 unit Rp 500.000,00 Rp 1.000.000,00 - - 1.000.000,00
j. Rambu alat pemberi isyarat lalu lintas sementara 2 ,00 unit Rp 150.000,00 Rp 300.000,00 - - 300.000,00
k. Lampu darurat (emergency lamp) 2 ,00 unit Rp 750.000,00 Rp 1.500.000,00 25,38% 380.700,00 1.119.300,00
8 Konsultasi dengan Ahli terkait Keselamatan Konstruksi -
a. Ahli manajemen pelaksanaan K3 6 ,00 OB Rp 3.000.000,00 Rp 18.000.000,00 100,00% 18.000.000,00 -
b. Ass Petugas Pengatrur Lalu lintas ( Flagman) 6 ,00 OB Rp 2.000.000,00 Rp 12.000.000,00 100,00% 12.000.000,00 -
9 Kegiatan dan peralatan terkait Pengendalian Risiko Keselamatan Konstruksi: -
a. Manajemen mutu 1 ,00 ls Rp 5.000.000,00 Rp 5.000.000,00 - - 5.000.000,00
b. Bendera K3 2 ,00 buah Rp 100.000,00 Rp 200.000,00 - - 200.000,00
c. Patroli Keselamatan Konstruksi 1 ,00 kegiatan Rp 2.000.000,00 Rp 2.000.000,00 - - 2.000.000,00
JUMLAH : Rp 2 33.583.140,00 81,36% Rp 1 90.034.360,44 Rp 4 3.548.779,56
B. PEKERJAAN PERSIAPAN DAN LAIN LAIN
1 Rekolasi Utilitas Pipa PDAM:
Pengukuran kembali dan pematokan 1,00 ls Rp 20.000.000,00 Rp 20.000.000,00 100,00% 20.000.000,00 -
Mobilisasi dan demobilisasi alat 1 ,00 ls Rp 55.000.000,00 Rp 55.000.000,00 100,00% 55.000.000,00 -
Sewa lahan 6,00 Bln Rp 15.000.000,00 Rp 90.000.000,00 100,00% 90.000.000,00 -
2 - Rekolasi Utilitas Pipa PDAM:
PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DAN ACCESORIS JARINGAN PIPA DISTRIBUSI
A PEKERJAAN PENDAHULUAN
A.1 Mobilisasi Dan Demobilisasi 1,00 Ls Rp 15.000.000,00 Rp 15.000.000,00 100,00% Rp 15.000.000,00 Rp -
PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DAN ACCESSORIES JARINGAN PIPA DISTRIBUSI
B.1 PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA
B.1.1 PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA HDPE
1 Pipa HDPE Ø 400 mm SDR 17 (PN 10/PE 100)
a PIPA HDPE PE100 SDR17 PN10 Ø 400 mm 460,00 M Rp2 .109.272,00 Rp 970.265.120,00 47,70% Rp 462.816.462,24 Rp 507.448.657,76
b Pemasangan Pipa Ø 400 mm 460,00 M Rp 229.476,75 Rp 105.559.305,00 100,00% Rp 105.559.305,00 Rp -
c Pengetesan Pipa HDPE Ø 400 mm 460,00 M Rp 3.213,66 Rp 1.478.283,60 97,11% Rp 1.435.561,20 Rp 42.722,40
d. Galian Tanah (Mekanis) 414,00 M3 Rp 133.197,88 Rp 55.143.922,32 100,00% Rp 55.143.922,32 Rp -
e Timbunan Tanah Kembali (Mekanis) 356,19 M3 Rp 38.914,88 Rp 13.861.091,11 100,00% Rp 13.861.091,11 Rp -
B.1.2 PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA BAJA
1 Pipa Baja SCH 40 Ø 400 mm
a Pipa Baja SCH 40 Ø 400 mm 2,00 M Rp 3.261.550,00 Rp 6.523.100,00 60,41% Rp 3.940.604,71 Rp 2.582.495,29
b Pemasangan Pipa Baja SCH 40 Ø 400 mm 2,00 M Rp 560.423,75 Rp 1.120.847,50 100,00% Rp 1.120.847,50 Rp -
c Pengetesan Pipa Ø 400 mm 2,00 M Rp 3.213,66 Rp 6.427,32 97,11% Rp 6.241,57 Rp 185,75
d. Galian Tanah (Mekanis) 1,80 M3 Rp 133.197,88 Rp 239.756,18 100,00% Rp 239.756,18 Rp -
e Timbunan Tanah Kembali (Mekanis) 1,55 M3 Rp 38.914,88 Rp 60.318,06 100,00% Rp 60.318,06 Rp -
B.1.3 PEKERJAAN PENGADAAN DAN PEMASANGAN ACCECORIES PIPA
a ELBOW 45° STEEL Ø 400 MM 4,00 Bh Rp 3.264.000,00 Rp 13.056.000,00 34,82% Rp 4.546.099,20 Rp 8.509.900,80
b FLANGE STEEL Ø 400 MM 12,00 Bh Rp 1.729.816,00 Rp 20.757.792,00 25,07% Rp 5.203.978,45 Rp 15.553.813,55
c GATE VALVE Ø 400 MM (Resilient) (JOHNSON VALVE) 1,00 Bh Rp 79.219.200,00 Rp 79.219.200,00 0,00% Rp - Rp 79.219.200,00
d. STUB FLANGE HDPE Ø 400 MM 2,00 Bh Rp 4.722.267,00 Rp 9.444.534,00 47,23% Rp 4.460.653,41 Rp 4.983.880,59
e ULTRAGRIP FLANGE ADAPTOR Ø 400 MM (VIKING JOHNSON) 2,00 Bh Rp 96.566.400,00 Rp 193.132.800,00 0,00% Rp - Rp 193.132.800,00
F. Mur Baut 144,00 Bh Rp 15.000,00 Rp 2.160.000,00 100,00% Rp 2.160.000,00 Rp -
g Pengelasan 1.507,96 Cm Rp 6.040,38 Rp 9.108.651,42 67,98% Rp 6.192.061,24 Rp 2.916.590,19
C.1 PEKERJAAN REKONDISI
RENCANA ANGGARAN BIAYA
BOQ PENINGKATAN SISTEM DRAINASE PERKOTAAN
Pekerjaan : PENINGKATAN SALURAN DRAINASE JL. CIPTO MANGUKUSUMO KEL.GUNUNG PANJANG KEC. SAMARINDA SEBERANG
Lokasi : Kota Samarinda
HARGA SATUAN JUMLAH HARGA TKDN% JUMLAH BIAYA KDN JUMLAH BIAYA KLN
NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 Pembongkaran Aspal Galian Pipa 16,56 M3 Rp 338.436,74 Rp 5.604.512,41 100,00% Rp 5.604.512,41 Rp -
2 Perkerasan Beton Mutu fc' = 30 Mpa Fast Track 24 Jam 55,20 M3 Rp 3.097.402,37 Rp 170.976.610,82 93,44% Rp 159.760.545,15 Rp 11.216.065,67
3 Lapis Resap Pengikat 96,60 Liter Rp 21.079,50 Rp 2.036.279,70 59,80% Rp 1.217.695,26 Rp 818.584,44
4 Laston Lapis Aus (AC-WC) 25,39 Ton Rp 21.079,50 Rp 535.208,51 59,80% Rp 320.054,69 Rp 215.153,82
5 Pekerjaan Perbaikan Pipa Ø 100 mm 5,00 Ttk Rp 1.676.400,43 Rp 8.382.002,15 1,60% Rp 134.112,03 Rp 8.247.890,12
6 Pekerjaan Perbaikan Pipa Ø 75 mm 5,00 Ttk Rp 1.275.205,68 Rp 6.376.028,40 1,86% Rp 118.594,13 Rp 6.257.434,27
7 Perbaikan Sambungan Rumah (SR) 10,00 Ttk Rp 500.000,00 Rp 5.000.000,00 100,00% Rp 5.000.000,00 Rp -
D Rekolasi Utilitas yang ada di lapangan -
- Pergantian Prasarana Tiang Telekomunikasi ( Besi ) 4 ,00 Bh Rp 6.500.000,00 Rp 26.000.000,00 100,00% 26.000.000,00 Rp -
- Pergantian Prasarana Tiang PLN ( Beton ) 1,00 Bh Rp 70.000.000,00 Rp 70.000.000,00 100,00% 70.000.000,00 Rp -
- Pergantian Prasarana Tiang PLN ( Besi ) 1,00 Bh Rp 35.000.000,00 Rp 35.000.000,00 100,00% 35.000.000,00 Rp -
- Tiang lampu ( besi ) 8,00 Bh Rp 6.500.000,00 Rp 52.000.000,00 100,00% 52.000.000,00 Rp -
- Tiang lampu rambu 1 ,00 Bh Rp 12.000.000,00 Rp 12.000.000,00 100,00% 12.000.000,00 Rp -
- Tiang rambu/ Trafific Light 5,00 Bh Rp 12.000.000,00 Rp 60.000.000,00 100,00% 60.000.000,00 Rp -
Rp -
E Relokasi / perbaikan bangunan warga 1 ,00 ls Rp 100.000.000,00 Rp 100.000.000,00 100,00% 100.000.000,00 Rp -
F. Relokasi / perbaikan Kembali Jalan Crosingan Saluran
- Beton readymix fc'=20 Mpa 6 5,00 ls Rp 2.439.092,65 Rp 158.541.022,57 100,00% 158.541.022,57 Rp -
- Lapis Resap Pengikat - Aspal Cair/ Emulisi 494,00 Liter Rp 40.110,00 Rp 19.814.340,00 100,00% 19.814.340,00 Rp -
- Laston Lapis Aus ( AC-WC) 260,00 ton Rp 3.381.350,00 Rp 879.151.000,00 100,00% 879.151.000,00 Rp -
JUMLAH : Rp 3 .272.554.153,08 74,30% Rp 2 .431.408.778,45 Rp 8 41.145.374,64
C. PEKERJAAN TANAH
1 Galian tanah dan buangan tanah secara mekanis 2 .486,27 m3 Rp 187.240,02 Rp 465.529.255,62 76,31% 355.258.058,18 110.271.197,44
2 Galian tanah Keras dan buangan tanah secara mekanis 365,63 m3 Rp 653.910,90 Rp 239.089.443,92 75,89% 181.444.890,17 57.644.553,75
3 Timbunan tanah pilihan dan pemadatan 4 8,17 m3 Rp 212.635,00 Rp 10.242.627,95 96,12% 9.845.165,24 397.462,71
4 Timbunan Pasir dan pemadatan 125,36 m3 Rp 325.335,00 Rp 40.783.995,60 100,00% 40.783.995,60 -
JUMLAH : Rp 7 55.645.323,09 77,73% Rp 5 87.332.109,19 Rp 1 68.313.213,90
D. PEKERJAAN PEMANCANGAN & PASANGAN
1 Pancang galam dia. 8 panjang 4 meter 2.117,00 titik Rp 151.036,91 Rp 319.745.135,13 90,53% 289.470.628,16 30.274.506,97
2 Pancang kayu Ulin 8/8 Panjang 4 meter ( Crosisngan ) 390,00 titik Rp 472.954,75 Rp 184.452.352,50 100,00% 184.452.352,50 -
3 Pas. Batu Kosong 4 22,08 m3 Rp 1.008.665,00 Rp 425.737.323,20 100,00% 425.737.323,20 -
JUMLAH : Rp 9 29.934.810,83 96,74% Rp 8 99.660.303,86 Rp 3 0.274.506,97
E. PEKERJAAN BETON PREACAST
1 Pengadaan dan pemasangan U-Ditch 300X120X120 , fc' = 24 Mpa 4 17,00 unit Rp 9.159.693,01 Rp 3.819.591.985,35 73,40% 2.803.598.698,07 1.015.993.287,28
JUMLAH : Rp 3 .819.591.985,35 73,40% Rp 2 .803.598.698,07 Rp 1 .015.993.287,28
RENCANA ANGGARAN BIAYA
BOQ PENINGKATAN SISTEM DRAINASE PERKOTAAN
Pekerjaan : PENINGKATAN SALURAN DRAINASE JL. CIPTO MANGUKUSUMO KEL.GUNUNG PANJANG KEC. SAMARINDA SEBERANG
Lokasi : Kota Samarinda
HARGA SATUAN JUMLAH HARGA TKDN% JUMLAH BIAYA KDN JUMLAH BIAYA KLN
NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
F. PEKERJAAN BETON
1 Beton readymix fc'=24 Mpa 397,79 m3 Rp 2.703.017,65 Rp 1.075.233.392,94 94,98% 1.021.251.444,70 53.981.948,24
2 Pembesian ulir 7.585,65 kg Rp 22.707,21 Rp 172.248.947,54 55,77% 96.061.271,59 76.187.675,95
3 Pembesian polos 11.523,73 kg Rp 19.206,15 Rp 221.326.486,94 56,55% 125.152.880,69 96.173.606,25
4 Bekisting dinding 1 .773,76 m2 Rp 231.161,50 Rp 410.025.022,24 94,83% 388.819.423,98 21.205.598,26
5 Bekisting plat lantai 354,52 m2 Rp 202.572,50 Rp 71.816.002,70 94,46% 67.836.150,23 3.979.852,47
JUMLAH : Rp 1 .950.649.852,36 87,11% Rp 1 .699.121.171,19 Rp 2 51.528.681,17
G. PEKERJAAN LAIN - LAIN & PERAPIAN AREA TAMAN TERBONGKAR
1 Pasang Penutup Lantai Trotoar 30x30 430,50 m2 Rp 4 85.550,00 Rp 209.029.275,00 75,00% 156.771.956,25 52.257.318,75
2 Pasang Penutup Lantai Keramik yg terdampak bongkaran 50,50 m2 Rp 1.080.000,00 Rp 54.540.000,00 75,00% 40.905.000,00 13.635.000,00
3 Pengadaan dan Pemasangan Kanstin 43,40 m1 Rp 753.430,91 Rp 32.698.901,44 99,25% 32.452.652,75 246.248,69
4 Pengecatan Dinding Baru (Luar Ruangan) 13,02 m2 Rp 124.478,30 Rp 1.620.707,47 48,52% 786.403,75 834.303,72
JUMLAH : Rp 2 97.888.883,91 77,52% Rp 2 30.916.012,74 Rp 5 2.257.318,75