BQ
REINSTALASI GENSET 1000 KVA
LANUD ATANG SENDJAJA
BOGOR 2024
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
(Rp.) (Rp.)
1 Genset 1000 Kva 1,00 unit 2.109.600.000,00 2.109.600.000,00
- Kapasitas : 1000 Kva
- Voltage - Phase : 220/380 Volt - 3 Phase
- RPM : 1500 Putaran/Menit - 50 Hz
- Test Report Generator
- Noise dB(A) @ 7m : 85 (Max)
2 Fuel Tank (Tangki Minyak) 1000 Lt + Instalasi BBM 1,00 unit 51.901.100,00 51.901.100,00
3 Grounding Genset 2,00 ttk 2.464.000,00 4.928.000,00
4 Kabel NYGBYY 4x240 mm2 (Genset Ke LVMDP) 84,00 m' 2.580.400,00 216.753.600,00
5 Scun 240 mm 32,00 bh 188.672,22 6.037.510,95
6 Kabel NYY 3x4 mm2 (MDP Ke Panel LP Gardu) 15,00 m' 36.949,50 554.242,50
7 Testing Commisioning 1,00 set 13.200.000,00 13.200.000,00
8 Bongkar Instalasi Kabel Lama (Genset Lama ke LVMDP) 1,00 ls 4.250.000,00 4.250.000,00
9 Alat Bantu 1,00 set 5.400.000,00 5.400.000,00
10 Galian Kabel 1,75 m3 154.523,38 270.415,92
11 Urugan Pasir dan Pasang Bata Pelindung Kabel 18,50 m' 125.000,00 2.312.500,00
JUMLAH… 2.415.207.369,37
PPN 11%... 265.672.810,63
TOTAL… 2.680.880.180,00
Pagu = 2.680.880.180,00