BILL OFF QUANTITY (BOQ)
KEGIATAN PENGELOLAAN PENDIDIKAN SEKOLAH DASAR
SUB KEGIATAN REHABILITASI SEDANG / BERAT RUANG PERPUSTAKAAN SEKOLAH DASAR
PEKERJAAN REHABILITASI RUANG PERPUSTAKAAN
LOKASI UPTD SD NEGERI 2 DRUNTEN WETAN
SUMBER DANA DANA ALOKASI UMUM (DAU) TAHUN ANGGARAN 2024
JUMLAH
NO. URAIAN PEKERJAAN
(RP.)
JUMLAH PEKERJAAN KONSTRUKSI 108,540,608.89
A PEMBANGUNAN RUANG PERPUSTAKAAN
I PEKERJAAN PERSIAPAN 4,735,000.00
II PEKERJAAN TANAH DAN PONDASI 919,093.09
III PEKERJAAN PASANGAN 1,622,816.44
IV PEKERJAAN BETON 2,303,919.59
V PEKERJAAN KUSEN ALUMUNIUM 23,037,109.69
VI PEKERJAAN PENUTUP ATAP 40,520,659.49
VII PEKERJAAN PLAFOND 8,451,789.41
VIII PEKERJAAN PENUTUP LANTAI DAN DINDING 15,614,412.32
IX PEKERJAAN PENGECATAN 9,320,808.87
X PEKERJAAN LISTRIK DAN MEKANIKAL 2,015,000.00
a. JUMLAH TOTAL (A+B) 108,540,608.89
b. PPN 11% (a x 11%) 11,939,466.98
c. JUMLAH TOTAL (a+b) 120,480,075.87
d. DIBULATKAN 120,480,000.00
TERBILANG : Seratus Dua Puluh Juta Empat Ratus Delapan Puluh Ribu Rupiah
Indramayu …....................... 2024
Disetujui, Dibuat
Pejabat Pelaksana Teknis Kegiatan Penawar
(PPTK) PT/CV….................................................
TAUFIQULLAH.S.IP..M.A.P …........................................................
NIP. 19770918 200801 1004 Direktur
Dibuat
Pejabat Pembuat Komitmen (PPK)
Dinas Pendidikan dan Kebudayaan Kabupaten Indramayu
UNTUNG ARYANTO,S.Pd.SD
NIP. 19690804 199003 1007
BILL OFF QUANTITY (BOQ)
PEKERJAAN REHABILITASI RUANG PERPUSTAKAAN
SUMBER DANA DANA ALOKASI UMUM (DAU) TAHUN ANGGARAN 2024
LOKASI UPTD SD NEGERI 2 DRUNTEN WETAN
HARGA SATUAN JUMLAH TOTAL
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA
(Rp.) (Rp.)
a b c d e f g
REHABILITASI RUANG PERPUSTAKAAN
I PEKERJAAN PERSIAPAN
2 Pek. Papan Nama Kegiatan Digital Printing 1.00 Bh - 150,000.00 150,000.00
3 Biaya Administrasi Pelaporan & Dokumentasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Pengadaan Air + Listrik Selama Pekerjaan 1.00 Ls 1,000,000.00 1,000,000.00
Biaya Penyelenggaraan Sistem Manajemen Keselamatan dan kesehatan kerja
5
(SMK3)
a. Alat Pelindung Kerja dan pelindungan diri
- Topi Pelindung (Safety Helmet) 5.00 Bh Ls 75,000.00 375,000.00
- Pelindung Mata (Goggles, Spectacles) 5.00 Bh Ls 50,000.00 250,000.00
- Perlindungan Pernapasan dan Mulut (Masker) 5.00 Bh Ls 5,000.00 25,000.00
- Sarung Tangan (Safety Glove) 5.00 Bh Ls 25,000.00 125,000.00
- Sepatu Keselamatan (Ruber Safety Shoes and toe cap) 5.00 Psg Ls 150,000.00 750,000.00
b. Fasilitas sarana kesehatan, terdiri atas :
- Peralatan P3K 1.00 set 300,000.00 300,000.00
c. Rambu- Rambu, terdiri atas :
- Rambu Petunjuk 1.00 Bh LS 50,000.00 50,000.00
- Rambu Larangan 1.00 Bh LS 50,000.00 50,000.00
- Rambu Peringatan 1.00 Bh LS 50,000.00 50,000.00
-Bendera K3 1.00 bh Ls 50,000.00 50,000.00
6 Papan Prasasti Ukuran 30x40 Cm 1.00 Bh Ls 300,000.00 300,000.00
7 Biaya BPJS Kesehatan dan Keselamatan Kerja 1.00 Ls Ls 260,000.00 260,000.00
JUMLAH I 4,735,000.00
…...............
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Urg. Pasir alas lantai T .5 cm 2.79 M3 B.12 328,923.00 919,093.09
JUMLAH II 919,093.09
…...............
III PEKERJAAN PASANGAN
1 Pek. Pasangan dinding 1/2 bata 1 Pc : 5 Psr 3.49 M2 D.3 154,218.00 537,758.17
2 Pek. Plesteran 1 Pc : 5 Psr 7.49 M2 E.3 100,670.00 753,615.62
3 Pek. Acian Dinding 7.49 M2 E.6 44,275.00 331,442.65
JUMLAH III 1,622,816.44
…...............
IV PEKERJAAN BETON
1 Pek. Rabat Beton 1Pc:3Ps:5Kr T. 5cm 0.88 M3 G.1 1,116,839.00 977,234.13
2 Pek. Balok Liufel 10/10 Cm
- Beton Site Mix K-175 0.12 M3 G.2 1,323,315.00 161,444.43
- Besi beton terpasang U-24 35.53 Kg G.24 20,755.00 737,350.43
- Begisting Papan Terentang 2.44 M2 G.23 175,365.00 427,890.60
JUMLAH IV 2,303,919.59
…...............
V PEKERJAAN KUSEN ALUMUNIUM
1 Pek. Pasang Kusen Alumunium Type. P. 1 (1 Unit)
Frame Kusen Alumunium 4" Warna Putih Glossy 8.26 M' F.8 167,396.00 1,382,690.96
- Pintu Swing + Daun Pintu Kaca 5 mm lengkap (Uk. 60x210) 2.00 Unit Ls 1,200,000.00 2,400,000.00
- Pasang Kaca 5 mm 0.49 M2 L.8 212,756.00 104,675.95
HARGA SATUAN JUMLAH TOTAL
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA
(Rp.) (Rp.)
a b c d e f g
2 Pek. Pasang Kusen Alumunium Type. P. 2 (1 Unit)
Frame Kusen Alumunium 4" Warna Putih Glossy 6.56 M' F.8 167,396.00 1,098,117.76
- Pintu Swing + Daun Pintu Kaca 5 mm lengkap (Uk. 90x210) 1.00 Unit Ls 1,200,000.00 1,200,000.00
- Pasang Kaca 5 mm 0.25 M2 L.8 212,756.00 52,337.98
3 Pek. Pasang Kusen + Jendela Alumunium type J1 (4 Unit)
Frame Kusen Alumunium 4" Warna Putih Glossy 46.44 M' F.8 167,396.00 7,773,870.24
- Daun Jendela + Engsel Casment + Kaca polos 5 mm + Karet Tepi 8.00 Unit Ls 830,000.00 6,640,000.00
- Pasang Kaca 5 mm 5.49 M2 L.8 212,756.00 1,168,881.46
4 Pek. Pasang Kusen Alumunium type BV1 (1 Unit)
Frame Kusen Alumunium 4" Warna Putih Glossy 6.22 M' F.8 167,396.00 1,041,203.12
- Pasang Kaca 5 mm 0.82 M2 L.8 212,756.00 175,332.22
JUMLAH V 23,037,109.69
…...............
VI PEKERJAAN PENUTUP ATAP
1 Pek. Kuda-kuda + rangka atap baja ringan (Zincallume) 105.00 M2 H.18 205,550.00 21,581,927.80
2 Pek. Pasang Atap Genteng Metal berpasir 105.00 M2 H.30 163,228.00 17,138,287.09
3 Pek. Pasang Nok Genteng Metal 15.70 M' H.55 114,678.00 1,800,444.60
JUMLAH VI 40,520,659.49
…...............
VII PEKERJAAN PLAFOND
1 Pek. Pasang Rangka Plafond galvalume modul 60x60 Cm 55.02 M2 I.23 80,480.00 4,427,607.20
2 Pek. Pasang Plafond GRC 55.02 M2 I.11 73,147.00 4,024,182.21
JUMLAH VII 8,451,789.41
…...............
VIII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Pasang Lantai Kramik Ukuran 40X40 Cm 55.02 M2 M.7 283,821.00 15,614,412.32
JUMLAH VIII 15,614,412.32
…...............
IX PEKERJAAN PENGECATAN
1 Pek. Cat dinding tembok baru 7.49 M2 P.11 40,405.00 302,471.83
2 Pek. Cat dinding tembok Lama 177.40 M2 P.14 37,953.00 6,732,793.88
3 Pek. Cat Plafond 55.02 M2 P.15 41,544.00 2,285,543.16
JUMLAH IX 9,320,808.87
…...............
X PEKERJAAN LISTRIK DAN MEKANIKAL
1 Pek. Pasang Instalasi Titik Penerangan dan Stop Kontak 8.00 Ttk Ls 125,000.00 1,000,000.00
2 Pas. Stop kontak 2.00 Bh Ls 34,000.00 68,000.00
3 Pas. Saklar Tunggal 2.00 Bh Ls 34,000.00 68,000.00
4 Pas. Saklar Ganda 1.00 Bh Ls 39,000.00 39,000.00
5 Pas. Lampu Celling Lamp 7.00 Bh Ls 120,000.00 840,000.00
JUMLAH X 2,015,000.00
…...............
JUMLAH TOTAL 108,540,608.89