REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN :: KEGIATAN PEMBANGUNAN LAPANGAN VOLLY PEMDA (INDOOR)
LOKASI : : KABUPATEN MALINAU
TAHUN : 2024
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp 85,928,000.00
II PEKERJAAN TANAH & PASIR Rp 3,080,280.50
III PEKERJAAN STRUKTUR BETON Rp 640,540,132.64
IV PEKERJAAN STRUKTUR BAJA Rp 3,215,720,268.67
V PEKERJAAN DINDING Rp 1,337,693,636.62
VI PEKERJAAN ATAP Rp 720,418,567.69
VII PEKERJAAN PENUTUP LANTAI Rp 743,708,064.00
VIII PEKERJAAN KUSEN, PINTU, DAN JENDELA Rp 378,315,426.31
IX PEKERJAAN INSTALASI LISTRIK Rp 115,217,668.00
X PEKERJAAN SANITASI Rp 20,139,210.00
XI PEKERJAAN PENGECATAN Rp 99,035,712.05
XII PEKERJAAN AKSESORIS Rp 154,572,075.60
Rp 7,514,369,042.09
PPN 11% Rp 826,580,594.63
JUMLAH Rp 8,340,949,636.72
DIBULATKAN Rp 8,340,950,000.00
TERBILANG :
#NAME?
Dibuat oleh,
CV/PT. ....................
....................
Direktur Cabang
RENCANA ANGGARAN BELANJA ( RAB )
PEKERJAAN : KEGIATAN PEMBANGUNAN LAPANGAN VOLLY PEMDA (INDOOR)
LOKASI : KABUPATEN MALINAU
TAHUN : 2024
NO Uraian Pekerjaan VOL
SAT HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 = 5 x 3
I PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Proyek 1.00 ls Rp 4 14,000 Rp 414,000.00
2 Mobilisasi-Demobilisasi 1.00 ls Rp 5 9,718,000 Rp 59,718,000.00
3 Perlengkapan Keselamatan & Kesehatan Kerja (K3) 1.00 ls Rp 2 5,796,000 Rp 25,796,000.00
Sub Total Rp 85,928,000.00
II PEKERJAAN TANAH & PASIR
1 Pek. Timbunan Tanah Lantai Ramp 21.13 m3 Rp 145,750 Rp 3,080,280.50
Sub Total Rp 3 ,080,280.50
III PEKERJAAN STRUKTUR BETON
1 a. Pek. Cor Plat Tribun (t=15 cm) 85.08 m3 Rp 1 ,592,135 Rp 135,463,589.02
Pek. Besi Ø10 - 20cm 9,333.98 kg Rp 1 7,984 Rp 167,861,290.99
Pek. Bekisting Plat; Bondeck 567.22 m2 Rp 3 78,500 Rp 214,692,982.71
b. Cor Dinding Tangga; Ramp Besi Ø16-15cm & Besi Ø10-15cm 7.06 m3 Rp 1 ,773,635 Rp 12,528,954.11
Pek. Besi Ø16 - 15cm (Tulangan Pokok Dinding) 1,114.70 kg Rp 1 7,984 Rp 20,046,638.94
Pek. Besi Ø10 - 15cm (Tulangan Geser Dinding) 435.85 kg Rp 1 7,984 Rp 7,838,261.23
Pek. Bekisting Dinding Ramp 35.32 m2 Rp 4 24,677 Rp 14,999,591.64
c. Footplat/dudukan dinding Ramp; Besi Ø16-15cm 3.72 m3 Rp 1 ,773,635 Rp 6,597,920.34
Pek. Besi Ø16 1,099.97 kg Rp 1 7,984 Rp 19,781,772.06
Pek. Pas. Bekisting 15.08 m2 Rp 2 65,103 Rp 3,997,749.47
2 Pek. Kolom Beton 15/15 1.45 m3 Rp 1 ,592,135 Rp 2,307,003.05
Berat Besi 4Ø10 158.94 kg Rp 1 7,984 Rp 2,858,346.68
Berat Besi Ø6 - 20cm 42.89 kg Rp 1 7,984 Rp 771,336.66
Pek. Bekisting Kolom 15/15 38.64 m2 Rp 4 24,677 Rp 16,409,519.28
3 Pek. Ring Balk Beton 15/15 1.61 m3 Rp 1 ,592,135 Rp 2,564,928.86
Berat Besi 4Ø10 132.53 kg Rp 1 7,984 Rp 2,383,435.04
Berat Besi Ø6 - 20cm 35.76 kg Rp 1 7,984 Rp 643,179.80
Pek. Bekisting Balok 21.48 m2 Rp 4 09,387 Rp 8,793,632.76
Sub Total Rp 6 40,540,132.64
IV PEKERJAAN STRUKTUR BAJA
- TRIBUN
1 Beam WF 350 x 175 x 7 x 11 6,169.41 kg Rp 6 9,374 Rp 427,997,931.54
2 Beam WF 300 x 150 x 6,5 x 9 22,361.94 kg Rp 6 9,374 Rp 1,551,342,816.05
3 Beam WF 250 x 125 x 6 x 9 1,217.65 kg Rp 6 9,374 Rp 84,473,555.51
4 Beam WF 200 x 100 x 5,5 x 8 2,571.41 kg Rp 6 9,374 Rp 178,389,871.44
5 Beam WF 150 x 75 x 5 x 7 1,612.10 kg Rp 6 9,374 Rp 111,838,228.43
6 Beam L 70 x 70 x 7 248.08 kg Rp 6 9,374 Rp 17,210,363.94
7 Plat 7,427.43 kg Rp 4 7,330 Rp 351,542,118.76
8 Anak Tangga; Plat 5mm 5,218.51 kg Rp 4 7,330 Rp 246,993,382.93
9 Protective coating 1,551.07 m2 Rp 1 58,556 Rp 245,932,000.08
Sub Total Rp 3 ,215,720,268.67
V PEKERJAAN DINDING
1 Pek. Dinding Bata Ringan 10 cm 900.90 m2 Rp 2 36,775 Rp 213,310,597.50
2 Pek. Plesteran Dinding 1,726.96 m2 Rp 8 5,729 Rp 148,049,690.36
3 Pek. Acian Dinding 1,726.96 m2 Rp 8 1,769 Rp 141,210,928.76
4 Dinding Panel Insulasi; Sandwich Panel 50mm (Atas Jalusi) 521.60 m2 Rp 8 44,342 Rp 440,408,613.33
5 Pek. Pas. Dinding Alumunium Composit Panel 357.60 m2 Rp 1 ,013,640 Rp 362,477,743.47
6 Pek. Keramik Dinding KM/WC; 30/30 Motif/Warna 114.60 m2 Rp 2 81,292 Rp 32,236,063.20
Sub Total Rp 1 ,337,693,636.62
VI PEKERJAAN ATAP
- KANOPI
1 Rafter WF 250 x 125 x 6 x 9 2,326.43 kg Rp 69,374 Rp 161,394,567.68
2 Purlin CNP 150x50x20x2.3 2,522.92 kg Rp 49,236 Rp 124,218,686.06
3 Lisplang, CNP 100x50x20x2.3 2,316.39 kg Rp 49,236 Rp 114,049,896.21
4 Sagrod dia. 12mm 39.23 kg Rp 49,236 Rp 1,931,692.40
5 Ikatan angin dia. 16mm 298.93 kg Rp 49,236 Rp 14,718,281.60
6 Beugel Talang L 50x50x5 1,425.00 kg Rp 69,374 Rp 98,858,306.25
7 Protective Coating 749.49 m2 Rp 158,556 Rp 118,836,242.59
8 Penutup Atap Trimdeck/Sejenis 234.24 m2 Rp 164,010 Rp 38,417,702.40
9 Penutup listplank spandek 0.4mm bmt biru bogowonto 146.40 m Rp 164,010 Rp 24,011,064.00
10 Nok 0.4mm biru bowonto 10.00 m Rp 150,453 Rp 1,504,525.00
11 Flashing 0.4mm biru bogowonto 149.40 m Rp 150,453 Rp 22,477,603.50
Sub Total Rp 7 20,418,567.69
VII PEKERJAAN PENUTUP LANTAI
1 Pek. Pas. Keramik Motif Granit 40/40 1,141.56 m2 Rp 376,992 Rp 430,358,987.52
2 Pek. Pas. Keramik motif/warna KM/WC 30/30 51.84 m2 Rp 281,292 Rp 14,582,177.28
3 Pek. Pas. Lantai Vynil 537.60 m2 Rp 555,742 Rp 298,766,899.20
Sub Total Rp 7 43,708,064.00
VIII PEKERJAAN KUSEN, PINTU, DAN JENDELA
1 Pek. Pas. Pintu Gate (1-4); Sliding Door Besi Plat 1.2 mm, Jarak 18 cm 4.00 bh Rp 27,516,397 Rp 110,065,589
2 Pek. Pas. Pintu Rg. Ganti & Gudang 3.00 bh Rp 2,964,390 Rp 8,893,169
3 Pek. Pas. Pintu KM/WC 10.00 bh Rp 1,500,000 Rp 15,000,000
4 Pek. Pas. Jendela Alumunium (Penutup=Akrilik) 10.68 m2 Rp 2,281,610 Rp 24,367,591
5 Pek. Pas. Jalusi & Flashing Alumunium 1,493.36 m' Rp 144,628 Rp 215,981,670
6 Pek. Pas. Lubang Angin 10.00 bh Rp 123,927 Rp 1,239,271
7 Pek. Pas. Bouven 10.00 bh Rp 276,814 Rp 2,768,136
Sub Total Rp 3 78,315,426.31
IX PEKERJAAN INSTALASI LISTRIK
1 Pek. Pas. Lampu 159.00 ttk Rp 126,500 Rp 20,113,500.00
2 Pek. Saklar Tunggal 24.00 bh Rp 50,000 Rp 1,200,000.00
3 Pek. Saklar Ganda 11.00 bh Rp 50,000 Rp 550,000.00
4 Pek. Stop Kontak 26.00 bh Rp 50,000 Rp 1,300,000.00
5 Pek. Box MCB 2.00 bh Rp 480,700 Rp 961,400.00
6 Pek. Papan Skor LED 1.00 bh Rp 10,987,600 Rp 10,987,600.00
7 Pek. Pas. Instalasi Listrik 223.00 ttk Rp 359,216 Rp 80,105,168.00
Sub Total Rp 1 15,217,668.00
X PEKERJAAN SANITASI
1 Pek. Pas. Kloset Jongkok 8.00 bh Rp 1,069,585 Rp 8,556,680.00
2 Pek. Pas. Kloset Duduk 2.00 bh Rp 3,621,585 Rp 7,243,170.00
3 Bak Air Fiberglass (VIP) 4.00 bh Rp 750,000 Rp 3,000,000.00
4 Pek. Pas. Kran Air 8.00 bh Rp 27,500 Rp 220,000.00
5 Pek. Floor Drain 8.00 bh Rp 139,920 Rp 1,119,360.00
Sub Total Rp 2 0,139,210.00
XI PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 1,961.56 m2 Rp 50,488 Rp 99,035,712.05
Sub Total Rp 9 9,035,712.05
XII PEKERJAAN AKSESORIS
1 Pek. Pas. Jumbo Font "GOR VOLLY PEMDA MALINAU", T=40CM/FONT 1.00 ls Rp 2 7,217,000 Rp 27,217,000.00
2 Pek. Pas. Jumbo Font "GATE 1, 2, 3, 4" 4.00 ls Rp 7 ,500,000 Rp 30,000,000.00
3 Logo Pemda, T=2,5M 1.00 ls Rp 6 ,250,000 Rp 6,250,000.00
4 Pek. Pas. Railing Tangga & Tribun 105.44 m2 Rp 7 32,628 Rp 77,248,243.60
5 Pas. Rangka Papan Skor 2,4 x 1,2 m2 2.88 m2 Rp 8 01,900 Rp 2,309,472.00
6 Pas. Rangka Lampu Sorot 14.40 m2 Rp 8 01,900 Rp 11,547,360.00
Sub Total Rp 1 54,572,075.60
JUMLAH Rp 7 ,514,369,042.09
PPN 11% Rp 826,580,594.63
TOTAL Rp 8,340,949,636.72
DIBULATKAN Rp 8 ,340,950,000.00
CV/PT. ...........................
.............................
.......................